Cold mass procurement, status and plan, QA-QC H. Prin With contribution from S. Becle, O. Housiaux, R. Principe, J.-L. Rudeiros Fernandez, F. Savary 3.

Slides:



Advertisements
Similar presentations
Christian Löffler Collaring to cold mass finishing 2 Outline Available tooling and operational status CMM of 5.5m coils Instrumentation Pairing.
Advertisements

COIL & ASSEMBLY READINESS REVIEW, SEPT 2013 D. Smekens.
11 September 2007 FP7-IA HFM JRA proposal G. de Rijk (CERN)1 FP7-IA HFM JRA proposal   Outline Motivation General description Proposed Work Packages.
HLTC 15 th April 2014 EDMS: Y. Muttoni EN-MEF-INT with the contribution of P. Fessia.
HL-LHC Standards and Best Practices Workshop (11-13 June 2014)
11 T Dipole informal coil and assembly readiness review Long coil and fabrication tooling development status and plans September 22 nd, 2013 – F. Savary.
CS 4310: Software Engineering
Software Quality Assurance Activities
From Research Prototype to Production
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
DOE Review of LARP – February 17-18, 2014 Helene Felice P. Ferracin, M. Juchno, D. Cheng, M. Anerella, R. Hafalia, Thomas Sahner, Bruno Favrat 02/17/2014.
CERN Accelerators Topology Configuration and Change Management Engineering Department Thomas Birtwistle, Samy Chemli – EN/MEF/DC.
Thoughts about the MQXF development plan P. Fessia Thanks to discussions within the MDT section (P. Ferracin, J. C. Perez, E. Todesco, P. Ferracin), L.
HL-LHC Configuration Management Keywords : HW Baseline, Naming, Parameters, Layout DB, Change Control The HiLumi LHC Design Study (a sub-system of HL-LHC)
TS, Length of YETS EYETS LIU & CONS Project
11 T Nb3Sn Demonstrator Dipole R&D Strategy and Status
HLRF DRAFT Global Design Effort 1 Defining EDR* Work Packages [Engineering Design Report] Ray Larsen SLAC ILC Division for HLRF Team DRAFT April.
F. Savary. Click here to add footer 2 Outline Context Constraints & Boundary conditions Project plan Production strategy A few words on QA Conclusions.
CLIC Project breakdown structure: organization, documentation and cost estimate Beam Instrumentation Workshop, June 2-3, 2009 CLIC Project breakdown structure:
LHC Hardware Commissioning Review May 2005, CERN, 1211 Geneva 23 1 LHC Hardware Commissioning Review Contribution ID: 20 – Quality assurance and.
THE PROJECT LIFE CYCLE PROJECT MANAGEMENT LIFE CYCLE LSU 01/18/2005 PROJECT LIFE CYCLE 1.
11 T Dipole Informal Coil and Assembly Readiness Review CERN September 2013 Review committee: Herman Ten Kate CERN (Chair) Fred Nobrega FNAL Davide.
Margarita Saifoulina BE/RF/SR. Outline Data Management EDMS & MTF for RF structures Future prospects for EDMS/MTF solution Data Management EDMS & MTF.
Samy Chemli – Configuration Management - S. Chemli EN-MEF – Contents Configuration Management Hardware Baseline Change Management.
MTF – Manufacturing and Test Folder Large Scale Deployment of MTF Sonia Mallón Amérigo Elena Manola-Poggioli on behalf of the EDMS Team, TS-CSE.
LIU-PSB Configuration Management EDMS Documentation, Layout and ECRs Thomas Birtwistle EN-MEF-DC.
1 Global Design Effort: Controls & LLRF Controls & LLRF Working Group: Tuesday Session (29 May 07) John Carwardine Kay Rehlich.
F. Savary Question 1 A. Magnet design criteria for the prototype and production magnet to be tested before the installation into the tunnel.
Hi-Lumi Conductor Procurement A.Ballarino, B. Bordini, L. Oberli HL-LHC/LARP International Review of Superconducting Cable for the HL-LHC Inner Triplets.
Summary The process and the components The tooling Production back log estimation The handles and the estimated cost and delay.
11 T Dipole Project Cold mass integration status & plan F. Savary / TE-MSC-LMF.
Equipment Management Folder / MTF Travellers. Product Data Management A huge amount of product and engineering data stored in CERN databases – Design.
11 T Dipole Project CERN Status M. Karppinen 11 T Management meeting 1 July 2013.
Review of the processes released in the framework of the MMP Goran Perinić.
Philip Schwarz TE-MSC-MNC 1 Engineering Specifications for ELENA ring and TL magnets Philip Schwarz on behalf of WP 2.2 ELENA IIC meeting 5 th December.
ELENA Documentation and Data Management Items, Assets, Functional Positions T. Birtwistle EN-ACE-CL With input from T. Krastev EN-ACE-EDM.
MQXFB design, assembly plans & tooling at CERN J.C Perez On behalf of MQXF collaboration team MQXF Workshop on Structure, Alignment and Electrical QA.
Storage Areas 865, 879, 954 and 955 G. Schneider J. Simon N. Sharmazanashvili G. Schneider BE-BI BI Beamline Operational Spares Strategy 2 (BOSS.
HiLumi-LARP Annual Meeting November 2014 MQXF pre-series and series magnets fabrication plans Ruben Carcagno November 19,
ESS | title of presentation | 2012-xx-xx | name of presenter Roles and Responsibilities sub title.
Product Lifecycle Management with the CERN EDMS David Widegren CERN, TS/CSE 8 Nov 2005EDMS:
DOE Review of LARP – February 17-18, 2014 Helene Felice P. Ferracin, M. Juchno, D. Cheng, M. Anerella, R. Hafalia, Thomas Sahner, Bruno Favrat 02/17/2014.
Fermilab LCLS-II Cryomodule QA/QC Model and Software Tools ESS Cryomodule Workshop, 16-Oct-2014 Jamie Blowers Head of Machine Shop and Quality & Materials.
Logo area 11 T Wire: Procurement Strategy and QA/QC B. Bordini, A. Ballarino, M. Macchini Acknowledgments: thanks to E. Charifoullina for her contribution.
Workshop summary Outline  Workshop’s aims  Highlights from the presentations (my selection!)  Costing Exercise – What we learnt  Summary - Roadmap.
11T Quality Assurance O. Housiaux, R. Berthet, S. Menu, R. Principe 3rd International Review on the 11T dipoles at collimator Section for the HL-LHC 6-8.
2 nd LARP / HiLumi Collaboration Mtg, May 9, 2012LHQ Goals and Status – G. Ambrosio 11 LHQ Goals and Status Giorgio Ambrosio Fermilab 2 nd LARP / HiLumi.
LIU Configuration Management EDMS Documentation, Layout and ECRs This presentation follows the LIU-PSB specific presentation done on 9 th October 2014.
Long coil manufacturing plan and QC at CERN F. Lackner, P. Ferracin, H. Prin, M. Duret, F. Savary, L. Favier, S. Triquet, S. Luzieux, R. Principe, C. Scheuerlein,
WP3 Quality Assurance Rosario Principe Richard Berthet, Olivier Housiaux, Sabine Menu, Paula Alvarez Lopez International Review of the Inner Triplet Quadrupoles.
Scope of PCP Phase 1: Solution Design of Q4 First-of-a-kind prototype QUACO Bid Conference, CERN, 07 th July 2016 Arnaud Foussat, CERN TE MSC-LMF Helene.
Closing Session Report
HL-LHC Magnet components and assemblies
Lessons learnt from CERN experience
Cold mass design, assembly plans and QA/QC at CERN
11 T Dipole Integration & Plans M. Karppinen
Cryostat procurement, status and plan, QA/QC
Configuration Management and Layout Database ELENA Project
Purchasing supplies at CERN
Mechanics: (Tim).
Status report on MQYY (Q4)
Introduction to the technical content The Q4 magnet (MQYY) for HL-LHC
Parts exchange for HL-LHC AUP Q1&Q3
The 11T cryo-assembly: summary of design and integration aspects
Communication and Documentation Needs exemplified on WP 71
Paolo Ferracin, Giorgio Ambrosio
Peer Review Agenda (Suggested).
MQXF updates P. Ferracin October 9th, 2014.
DOE Review of the LCLS Project October 2006
Presentation transcript:

Cold mass procurement, status and plan, QA-QC H. Prin With contribution from S. Becle, O. Housiaux, R. Principe, J.-L. Rudeiros Fernandez, F. Savary 3 rd International Review on the 11 T Dipoles at Collimator Section for the HL-LHC 6-8 April 2016 CERN

Outline  Cold Masses Overall Schedule  Cold Masses Main Components  What is already available, on-going procurement, manufacturing to be launched (MCS!)  Cold Masses Project  Associated Equipment Codes  WP11 project structure and Hardware Baseline  The same documents and items will be used in WP11 Project Structure (lifetime of the project) and the Hardware Baseline (long term archiving recipient)  Document Types  E-BOM  Cold Masses Procurement  On going procurement for the 1st prototype  Shells and laminations timeline  Components that do not require Divisional Order  Procurement for the 4xfirst cold masses (after prototype)  Procurement is linked to the lessons learnt with prototype assembly and testing. Nevertheless some procurement could be started earlier (foreseen early 2017) 3rd International Review on the 11 T Dipoles at Collimator Section for the HL-LHC H. Prin2

Outline  Quality Assurance  Assembly procedures and documentation adapted from main dipole and insertion quadrupole cold masses  Interface specification is under preparation  Implication of LMF-QA team to share the QA procedures writing and the QC registration of results in EDMS  EDMS Item navigator view, documentation handling (drawing, folders, fabrication & control procedures, reports…)  From QA to QC  LHC-LBH-FRM-0003 worksheet handled by LMF-QA that puts together all documentation from components procurement (QA) to reception (QC)  Quality Control  MTF Asset navigator view, documentation handling (sub-equipment, relevant data, relevant manufacturing steps, non conformity reports, manufacturing documentation, history)  Components logistics in the LMF Section  Risk and Mitigation  Summary 3rd International Review on the 11 T Dipoles at Collimator Section for the HL-LHC H. Prin3

Risk and Mitigation for the 1 st prototype and 4 associated cold masses  Risk:  Procurement is not found, e.g. 316LN as specified for the MB  Internal design is changed. Already procured pieces are no longer usable. New procurement to do  Interface design is changed. Idem.  Pieces from third-party is not available. Assembly cannot be achieved  Insulation pieces redesign due to dielectric (magnet leads proximity)  Mitigation:  Work with EN-MME to define new material specification with less procurement risk  Use as much as possible standard (interchangeable) elements  Internal design. Control 3 to detect impact on procurement. Control 2 is enough if checks on procurement is done at the same time as the functional check.  Interface design. Control 3 is mandatory to detect impact. ECR might be needed to track changes  Possible use of existing spare parts with adaptation?  On going studies and development on the 2-in-1 models to increase the current path and the insulation redundancy 3rd International Review on the 11 T Dipoles at Collimator Section for the HL-LHC H. Prin4

Risk and Mitigation for the 2 nd prototype and 8 associated cold masses 3rd International Review on the 11 T Dipoles at Collimator Section for the HL-LHC H. Prin5  Risk (on the top of previous risks):  Major change of design of collared coils implies change of the cold mass design  Mitigation:  to avoid a re-design of the cold mass, the interfaces must remain the same (length, diameter). Approval process (control 3) for the collared coils drawings is mandatory. Tooling issues will be addressed in F. Lackner’s talk

Summary  The 11T cold masses design for the first generation (RRP cable) is completed, the control process is started.  e-BOMs are generated thanks to CAD & PLM software and give a clear definition of the cold mass and sub-assemblies structure.  Management and follow-up tools exist and are mastered in the WP11 project structure and the Hardware Baseline.  Collaboration with LMF-QA led to a mastered Project Documentation accessible through many different points. Teamwork, collaborative working environment and daily exchanges insures an up-to-date and detailed information that can be shared between all the participants in the project.  Trained personal is required to ensure a draconian procurement follow-up (component availability in the firms and on the shelves, documentation, QC & QA…) 3rd International Review on the 11 T Dipoles at Collimator Section for the HL-LHC H. Prin6