Impact of Hurricane Ike on CenterPoint Energy’s Transmission System Paul Rocha Director, Transmission Planning Presented at October 2, 2008 ERCOT TAC Meeting.

Slides:



Advertisements
Similar presentations
Utility Needs and Smart Grid for Major Storm Events July 11, 2013 Edward Gray, PE Director – Transmission and Distribution Engineering.
Advertisements

Florida Public Service Commission 2007 Hurricane Preparedness Briefing May 23, 2007 Kissimmee Utility Authority Ken Davis Vice President Engineering &
Florida Public Service Commission Internal Affairs Hurricane Season Preparation Paul Davis, Director Energy Control Center June 5, 2006.
Hurricanes Katrina & Rita: A Tale of Two Hospitals.
After the Storm: Using GIS for Damage Assessment and Restoration October 2004 O ne GIS, Inc. One Platform, One Solution, One Company…
FPL Hurricane Assessment Operating Committee January 25, 2005.
PER
October 16, 2009 RPG Meeting ERCOT RPG Project Review Update Jeff Billo.
How to use this presentation. How Power is Restored After a Severe Storm Presented by YOUR NAME YOUR TITLE.
Company LOGO Cleco Planning Process. Models Cleco uses SPP’s annual series of models to determine the NERC reliability violations. Cleco uses SPP or VST.
Regional Planning Group Project
1 April 27, 2011 Southeast Tornado Event System Operator Conference September and September 25-27, 2012 Memphis, TN Rocky Williamson, SOS Chair Operations.
Goshen Area Bus Reconfiguration
IMO Perspective on Reliability A presentation to the IEEE Toronto Section Forum on Reliable Power Grids in Canada by Dan Rochester, Section Head - Assessments.
Connection of Wind Farms to Weak AC networks – ERCOT Experience and Challenges Shun-Hsien (Fred) Huang ERCOT System Planning CIGRE WG B4.62 Meeting June.
CenterPoint Energy Houston Electric 2011 Response to Contamination Conditions John Kellum Director of Transmission Operations August 3, 2011.
Hurricane Recovery Update MTAC November 2, HURRICANE RECOVERY TIME LINE OF EVENTS Hurricane Katrina Makes Landfall in Florida 6:30 P.M. Thursday,
AFFILIATED ENGINEERS, INC. THE UNIVERSITY OF TEXAS MEDICAL BRANCH (UTMB) AT GALVESTON Presented to Houston Area Association of Hospital Engineering July.
August 30, Hurricane Ike Timeline Saturday9/13/08 Hurricane Ike makes landfall Lynchburg Pump Station lost power at 1 a.m. Power was restored by.
April 15 and May 15, 2003 ERCOT System Disturbances ERCOT TAC Meeting June 4, 2003.
Houston Region Import Capacity Project August 27, 2013 Regional Planning Group Meeting.
Navarro to Houston Presentation to ERCOT RPG August 27, 2013.
Dealing with Catastrophic Storm Issues January 2009 SE Missouri Ice Storm Missouri PSC Storm Workshop Presented by Dave Wakeman Manager, Distribution Operating.
January 5, 2012 TAC Cross Valley 345 kV Project Jeff Billo Manager, Mid-Term Planning.
BRAZOS ELECTRIC COOPERATIVE Dobbin 345 Project David Albers, P.E. Manager – System Planning.
The Impact of Ice Nebraska Public Power District
Kenneth (Kenny) Mercado Division Vice President of Distribution Electric Operations Turning on the Lights.
1 Impact of the 2004 Hurricanes Hurricane Charley Landfall on August 13 th Customers affected Poles replaced Transformers replaced Miles of wire replaced.
Applying the Distribution System in Grid Restoration/NERC CIP-014 Risk Assessment Srijib Mukherjee, Ph.D., P.E. UC Synergetic.
Hurricane Rita. 2 ERCOT Preparation ERCOT started alerts to QSEs and TOs on 9/21 Did a site failover of EMMS system Austin Taylor Procured satellite voice.
1 The following are the planned transmission project at SCL for the next ten year. All the projects has no major impact to the bulk transmission system.
Warren Lasher Director, System Planning October 4, 2014 Our Energy Future.
NRG Comments/Concerns with HIP Assumptions January 21, 2014 RPG Meeting NRG Comments/Concerns with HIP Assumptions - January 21, 2014.
Sandia is a multi-program laboratory operated by Sandia Corporation, a Lockheed Martin Company, for the United States Department of Energy’s National Nuclear.
10/03/ Report on Existing and Potential Electric System Constraints and Needs Within the ERCOT Region October 3, 2002.
March 8, 2007 Robert D. Sloan Executive Vice President & General Counsel Entergy Corporation Hurricane Katrina: The Entergy Experience.
January 2009 SEMO Ice Storm Extreme Measures IEEE-PES St Louis Chapter Meeting June 18, 2010 Presented by David Wakeman Vice President, Energy Delivery.
National Communications System Briefing Template Hurricane Isabel: Government-Industry Partnership in Planning, Response and recovery CAPT J. Katharine.
BTA Workshop May 22, 2008 Ten-Year Transmission Plan for the Santa Cruz Water & Power Districts Association (“Santa Cruz”) 10/26/2015K.R. Saline & Assoicates,
Lee County Electric Cooperative 2007 Hurricane Preparedness Activities.
Hurricane Recovery EPA Water Program Overview Briefing for ACWI.
Jones Creek Project Submitted to RPG on July 7, 2014 July 22, 2014 Regional Planning Group Meeting.
AEP Corpus Christi TDC Advance Outage Scheduling Initiative.
1 CenterPoint Energy Response to ‘Hurricane Rita’ CenterPoint Energy’s Response to Hurricane Ike COPS Update October 14, 2008.
TAC02/01/2007 DW 1 TAC Briefing on: - Report on Constraints and Needs: Five Year Plan Development - Long Term System Assessment (LTSA) - Entergy Integration.
Jesus A. Guerra, P.E. Distribution System Reliability CenterPoint Energy SWEDE 2011.
Hurricane Rita October 12, Hurricane Rita’s Aftermath Second worst storm in Entergy history At the peak, 766,000 customers without power in Texas.
1 CenterPoint Energy Response to ‘Hurricane Rita’ CenterPoint Energy Response to Hurricane Rita RMS Update October 12, 2005.
Operating Guide and Planning Guide Revision Requests Blake Williams, ROS Chair September 13, 2012.
TRANSMISSION CONSTRAINTS KENNETH A. DONOHOO, P.E. Manager of System Planning, Technical Operations
2009 Hurricane Season Preparations Florida Public Utilities Company May 6, 2009.
2015 HURRICANE SEASON PREPARATIONS March 18, 2015.
2014 Hurricane Season Preparation Informal Meeting for Electric Utilities with Florida Public Service Commission Staff March 26, 2014.
2006 Hurricane Preparedness June 5, 2006 Sumter Electric Cooperative, Inc R. Ben Brickhouse: Director of Engineering & IT John J. LaSelva: Director of.
Hurricane Season Preparation Briefing Florida Public Service Commission May 1, 2008 Kevin Wailes General Manager – Electric Utility.
FRCC System Restoration 2016 FRCC System Operator Seminar.
2015 Hurricane Season Preparedness Briefing Jorge Puentes Engineering Manager – Northeast and Northwest Divisions March 18, 2015.
2014 Hurricane Season Preparedness Briefing Jorge Puentes Technical Projects Manager – Northeast and Northwest Divisions March 26, 2014.
Long Term Transmission Integration Planning at the California ISO Intermittency Analysis Project (IAP) Energy Commission Staff Workshop February 13, 2007.
2006 Preliminary Reliability Study Results Bryan Guy September 7, 2006.
1 Electric Utility Power Systems Generation of Electricity.
Florida Keys Electric Cooperative Association, Inc. Storm Hardening Florida Public Service Commission May 1, 2008 Scott Newberry, CEO John Stuart, COO.
Biggest Power Outages in US History A Presentation of Current Solutions PC.
Utility Needs and Smart Grid for Major Storm Events
Impact of Hurricane Ike on
Hurricane Rita.
“FRCC RESTORATION PLAN (BLACKOUT & BLACK START)” - TRAINING -
Pacific Power Seismic Preparedness Update
Distributed Energy Resources (DER) Experiences at CenterPoint Energy
TxMAG presentation
Presentation transcript:

Impact of Hurricane Ike on CenterPoint Energy’s Transmission System Paul Rocha Director, Transmission Planning Presented at October 2, 2008 ERCOT TAC Meeting

Hurricane Ike 9/12/ PM Energized Out Restored 0 Circuits Out

Hurricane Ike 9/12/ PM 14 Circuits Out Energized Out Restored

Hurricane Ike 9/13/ AM - Landfall 36 Circuits Out Energized Out Restored

Hurricane Ike 9/13/ AM 67 Circuits Out Energized Out Restored

Hurricane Ike 9/13/ AM 90 Circuits Out Energized Out Restored

Hurricane Ike 9/13/ PM 97 Circuits Out Energized Out Restored

Hurricane Ike 9/13/2008 Restoration – 7% 90 Circuits Out Energized Out Restored

Hurricane Ike 9/14/2008 Restoration – 41% 58 Circuits Out Energized Out Restored

Hurricane Ike 9/15/2008 Restoration – 70% 30 Circuits Out Energized Out Restored

Hurricane Ike 9/16/2008 Restoration – 87% 13 Circuits Out Energized Out Restored

Hurricane Ike 9/17/2008 Restoration – 94% 6 Circuits Out Energized Out Restored

Hurricane Ike 9/23/2008 Restoration – 100% 0 Circuits Out Energized Out Restored

Pole Damage 31

Pole Replacement 32

CenterPoint MW Load Restoration 33

Seawall Substation

Stewart Substation 35

West Bay Substation

Moody Substation

Galveston Substation

West Galveston Substation 39

Mobile Substation

Network Changes  After reviewing damage assessments and analyzing power flow study results, CenterPoint Energy decided not to restore the 69 kV portion of damaged West Galveston substation and 69 kV Ckt. 13, Lamarque – West Galveston  Removal of damaged 69 kV connections to Galveston Island could cause some increased loading on remaining three 138 kV connections to Galveston Island  Timing depends on rate of load restoration and growth on Galveston Island  CenterPoint Energy believes upgrades of remaining 138 kV facilities would be more practical, cost-effective, and timely than restoration of damaged 69 kV facilities  CenterPoint Energy will evaluate upgrades to remaining 138 kV connections to Galveston 41

42 Galveston Island Network Changes - Temporary

Galveston Island Network Changes - Permanent 43

Emergency Entergy Connection  Implemented emergency interconnection from CNP’s Crosby substation to Entergy’s Dayton substation 9/15/2008  From Dayton substation, CNP used new transmission line built by Entergy after Hurricane Rita to restore power to water plant on the Trinity River normally served by Entergy  Disconnected Entergy emergency connection 9/19/

Planned Transmission Outages  Deferred all planned outages during restoration process  CenterPoint Energy expects to resume planned outages next week 45

Mutual Assistance  No report would be complete without noting the tremendous mutual assistance support from other utilities across North America  Far too many to list here, but we want to say… Thank You!!! 46

Transmission Network Summary  Transmission Network Was Quickly Restored  Network restored to necessary functionality within 4 days  However, storm surge affected Galveston Island, including CNP substations  Grid stability maintained despite tie-line and other outages  ERCOT actions to adjust for increased probability of line outages was effective  Generators performed well  2007 completion of STP– Hillje– WAP tie-line helped  Availability of mobile substations aided restoration effort  New Entergy 138 kV line expedited water plant restoration  Relay and Control infrastructure performed well  Hurricane training and drills were effective in preparing personnel 47