LHC Cryogenics From cool-down to 1st beams Serge Claudet (LHC Cryo OP), On behalf of cryo teams involved.

Slides:



Advertisements
Similar presentations
LHC Cryogenics Status and Perspectives
Advertisements

Status of Cryogenics at point 4 following the power cut L. Tavian 20 August 2011.
Cryogenic system in P4: Possible options S. Claudet & U. Wagner LHC Workshop, “Chamonix XlV” January 2005 (Mostly for RF & beam scrubbing)
1 Ann Van Lysebetten CO 2 cooling experience in the LHCb Vertex Locator Vertex 2007 Lake Placid 24/09/2007.
Cryogenic Experts Meeting (19 ~ ) Helium distribution system for Super-FRS dipoles and multiplets MT/FAIR – Cryogenics and Magnets Y. Xiang,
Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
SC - 04Feb'13Cryo Heaters Review Cryogenic Heaters Review Operation use and wishes S. Claudet - A. Suraci LHC Cryogenic Operation.
LHC Experimental Areas Forum - 03/07/ ATLAS Helium Cryogenics Nicolas Delruelle on behalf of the AT / ECR group.
Large-capacity Helium refrigeration : from state-of-the-art towards FCC reference solutions Francois Millet – March 2015.
CRYOGENICS AND POWERING
LARP LQX and MQX Magnets Cryogenic Testing at Fermilab’s Industrial Building 1 Roger Rabehl Technical Division/Test & Instrumentation Department.
Session th January 2010 R.Schmidt TE/MPE Hardware Commissioning 2010 and beyond R.Schmidt.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
The cryogenic systems of the ATLAS and CMS detectors Johan Bremer on behalf of TE/CRG 06/06/2013AFF.
Accelerators for ADS March 2014 CERN Approach for a reliable cryogenic system T. Junquera (ACS) *Work supported by the EU, FP7 MAX contract number.
HC review - 12 May 2005Luigi SERIO - AT/ACR/OP1 SECTOR COOL DOWN AND CRYOGENIC COMMISSIONING L. Serio.
July LEReC Review July 2014 Low Energy RHIC electron Cooling Roberto Than CRYOGENICS SYSTEM.
Workshop Chamonix XIV Shortcuts during installation and commissioning: risk and benefit H. Gruehagen, G. Riddone on behalf of the AT/ACR group 18 January.
Workshop 12/04/2006AT/MTM SM18 Test Facility A. Siemko "Workshop on Test Facilities and measurement equipment needed for the LHC exploitation"
LHC Cryogenics: “From cool-down & HWC to operation with beam” S. Claudet, for LHC cryogenics Extended LTC, 3 Mar’08.
Introduction to LHC cryogenic system (layout, architecture) Preparation before cool-down (Purge, flushing) Transient operations to reach nominal operating.
Cryogenics in SPS & LHC (2 K / 4.5 K) LHC-CC11, 14 November 2011 L. Tavian, CERN, TE-CRG With the contribution of N. Delruelle, G. Ferlin & B. Vullierme.
Cryogenic update before Fermilab meeting (and after the helium tank review) Coordination meeting 6 th May 2015 K. Brodzinski HiLumi-LHC-CC-Cryo-PPT-18_v1.
Modeling and simulation of cryogenic processes using EcosimPro
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
S. Claudet - 31st May 2007Power refrigeration for LHC Power refrigeration at 4.5K & 1.8K for the LHC S. Claudet, CERN AT-ACR.
OLAV III Experience with the LHC Insulation Vacuum System S. Blanchard, P. Cruikshank, B. Jenninger, N. Kos, W. Maan, L. Mourier, N. Provot, J. Wallner.
N.Delruelle, 22th-26th September 2008 Cryogenics Operations 2008, CERN, Geneva, Switzerland 1 CRYOGENICS OPERATIONS 2008 Organized by CERN Design choices.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
L. Serio COPING WITH TRANSIENTS L. SERIO CERN, Geneva (Switzerland)
Hardware Commissioning  Preparation Documentation MTF Programme  Status The Review The commissioning activity in Resources  Outlook The new.
LHC Cryogenics HWC day 19 March 2009 Serge Claudet TE-CRG-OA (LHC Cryo OP)
Process Definition of the Operation Modes for Super-FRS Magnet Testing CSCY - CrYogenic department in Common System, GSI, Darmstadt Y. Xiang, F. Wamers.
8 th November 07-OP Workshop Machine Checkout E. VEYRUNES CRYOGENICS 8 th November 2007 OP Workshop Machine Checkout E. VEYRUNES AB/OP 2008 AB/OP CRYO.
Luigi Serio CRYOGENICS PERFORMANCE AND OPERATION L. Serio, on behalf of the LHC Cryogenics Operation and Cryogenics Performance Panel.
LHC Cryogenics for sector 45 and Perspectives S. Claudet, for LHC cryogenics HWC Review, 28 Fev’08.
Heat loads and cryogenics L.Tavian, D. Delikaris CERN, Cryogenics Group, Technology Department Accelerators & Technology Sector Friday, October 15, 20101HE-LHC'10.
MAGNET#1MAGNET#2MAGNET#3 SATELLITE VB#1 SATELLITE VB#2 SATELLITE VB#3 PRECOOLER#1PRECOOLER#2 DISTRIBUTION VALVE BOX DVB CP#1CP#3CP#2 BUFFER DEWAR LHe 5m.
Can we change a magnet without warming-up a full arc ? Serge Claudet, With help from P. Cruikshank & J-P. Tock (Chamonix Jan’10)
Training LHC Powering - Markus Zerlauth Powering Interlocks Markus Zerlauth AB/CO/MI.
TE-CRG Activities D. Delikaris, TE-CRG.
MPP Meeting 07/03/2007 MPP Main Ring Magnet Performance Panel Meeting Wednesday 7th March 2007 Agenda: 1)Matters arising 2)Recommendations for the case.
Date 2007/Sept./12-14 EDR kick-off-meeting Global Design Effort 1 Cryomodule Interface definition N. Ohuchi.
LHC CRYOGENICS – new experience of run with increased beam energy and intensity Krzysztof Brodzinski CERN, Geneva, Switzerland With contribution from:
ITER Liquid Helium Plants Status and Test Protocol ICEC June 29th, 2015 / Grenoble / FranceY. FABRE.
LHC Commissioning Status Gianluigi Arduini CERN – AB Department For… 23/10/20081LHC Commissioning Status - G. Arduini.
5-year operation experience with the 1.8 K refrigeration units of the LHC cryogenic system G. Ferlin, CERN Technology department Presented at CEC 2015.
LHC Cryogenics, equipment & interventions around P3/P7 S. Claudet, “volunteer” for TE_CRG 16 Oct’14.
Bruno Vullierme Sept LHC-CC09 - 3rd LHC Crab Cavity Workshop Slide 1 CRAB CAVITY INTEGRATION CRYOGENICS INSTALLATION.
R. van Weelderen Overview of the LHC cryogenic system.
FCC Infrastructure & Operation Update on the cryogenics study Laurent Tavian CERN, TE-CRG 28 October 2015.
Max-Planck-Institut für Plasmaphysik 1 ICEC 26- ICMC 2016 March 7-11, 2016, New Delhi, India Michael Nagel Cryogenic commissioning, cool down and first.
LCLS-II Technical Requirements
ILC Cryogenics: Study of Emergency Action and Recovery - in progress -
M Chorowski, H Correia Rodrigues, D Delikaris, P Duda, C Haberstroh,
Innovative He cycle Francois Millet.
Dana M. Arenius Jefferson Laboratory Cryogenics Dept Head
SPS cryogenic proximity equipment and SM18 validation
The LHC - Status Is COLD Is almost fully commissioned
CRYOGENICS – strategy, unavailability root causes and limitations
Dynamic simulations: a useful tool for cryogenic installations
Coordination of Hardware Commissioning
Hollow e- lens, Cryogenic aspects
SHMS Cryogenics and Q2(Q3Dipole) Cool Down
TEST PLANS for HL LHC IT STRING
HiLumi P1/P5, Cryogenic interfaces for sc links, DFX 2nd review
Summary post TCC#54_02Aug’18
Cryogenic management of the LHC Run 2 dynamic heat loads
Laurent Delprat CERN, Geneva, Switzerland
Presentation transcript:

LHC Cryogenics From cool-down to 1st beams Serge Claudet (LHC Cryo OP), On behalf of cryo teams involved

S. ClaudetLHC Cryogenics - CryoOps 2008 Content Introduction to LHC cryogenics Cool-down, cryo tuning for magnets HWC Functional analysis - Controls - Availability Perspectives Summary

S. ClaudetLHC Cryogenics - CryoOps 2008 Layout of cryogenics 8 x 4.5 K 1’800 sc magnets 24 km & K 36’ K 120 t He inventory

S. ClaudetLHC Cryogenics - CryoOps 2008 LHC Cryogenics architecture Large variety of large scale refrigerators, AND Large variety of valve boxes and large scale lines

S. ClaudetLHC Cryogenics - CryoOps 2008 Cryogenic sub-systems Point 8 Storage Sector 7-8Sector 8-1 Surface Cavern QSCA QSCB QSRB QURC QUIC QURA Shaft QSCC Tunnel QURC QSRA Qualified with performance assessment before being put together

S. ClaudetLHC Cryogenics - CryoOps 2008 LHC Sector 4-5 scheme 4.5 K 1.9 K 3.3 km 4’ K ≈ 10/15tHe

S. ClaudetLHC Cryogenics - CryoOps 2008 LT836 LT837 LT864 LT865 LT866 LT867 ≈ 5 m Electrical Feed Boxes (DFB’s)

S. ClaudetLHC Cryogenics - CryoOps 2008 Content Introduction to LHC cryogenics Cool-down, cryo tuning for magnets HWC Functional analysis - Controls - Availability Perspectives Summary

S. ClaudetLHC Cryogenics - CryoOps 2008 Flushing sectors before cool-down Dust Debris Kapton Reports And possible shorts in diodes ! But the sooner the best !!!

S. ClaudetLHC Cryogenics - CryoOps 2008 Christmas and water maintenance shut-down Short in connection cryostats and repairs Open Days Cooling 8 sectors + Cryo tuning + Powering tests activities UX85 Ph1 works All sectors at nominal temperature Simultaneous Cryo start/maintain First beams around LHC First cool-down of LHC sectors

S. ClaudetLHC Cryogenics - CryoOps 2008 Cool-down speed for LHC sectors Availability for LN2 (trucks & staff) Cool-down speed [K/day] Average temperature of magnets [K] Dispersion due to particular process (HX & Turbines) and timing for thermal shield/ Line B

S. ClaudetLHC Cryogenics - CryoOps 2008 An idea of time constants ! m’ = Ro. V. S From QUI to QRL_RM ≈ 3300m Changes on « supply conditions » may have an effect some hours later …

S. ClaudetLHC Cryogenics - CryoOps 2008 Present reference with Jun’08 constraints (staff, LN2, controls) 25 d 3 d 2 d LHe 18 d 2 d 1.5 d Updated installed capacity At best: 21.5 d Duration of phases Target 2008: 5 wks

S. ClaudetLHC Cryogenics - CryoOps 2008 LHC Cryogenic commissioning 4.5K stand-alone magnets –Cool-down to < 10K –Adjust instrumentation LT/EH –Control LHe at 50%  Fill-up and boil-off to determine appropriate set-point Electrical Feed Boxes (DFB’s) –Cool-down shield (if any) –Cool-down leads at 150K, then cool- down phase separator –Adjust instrumentation LT/EH –Control LHe at nominal  Fill-up and boil-off to determine appropriate set-point  Tuning of Temp. control loops 2 K magnets in ARC –LT/EH at return modules –LT of SSS in ARC –EH at lowest point –EH of cold masses & beam screens  Possible pump-down and cool-down of magnets, including tests with cold compressors Identified and tuned for sector 4-5, Implemented for sector 5-6, 7-8, and now in 8-1, 2-3, 6-7 during the (target =two) weeks after ARC 4.5K

S. ClaudetLHC Cryogenics - CryoOps 2008 Recovery Time after Limited Resistive Transitions More than 14 cells or full sector: recovery up to 48 hours In case of fast discharge (even w/o quench): 2 h recovery (heating due to eddy currents) (Predictions at design stage) Achieved or achievable From x3 down to x1.5 w.r.t design values Without losing helium, and powering permit on other powering subsectors

S. ClaudetLHC Cryogenics - CryoOps 2008 Content Introduction to LHC cryogenics Cool-down, cryo tuning for magnets HWC Functional analysis - Controls - Availability Perspectives Summary

S. ClaudetLHC Cryogenics - CryoOps 2008 Cryogenics P&F diagram A large and complex fluid distribution system ! More than 500 PID control loops Complete functional analysis: - global process phases and families - automation request for each phase - synoptics - “propagate order” tools

S. ClaudetLHC Cryogenics - CryoOps 2008 Standard cells (≈27) QRL Filling valves Q D DD Cool-down using mostly Flow controlers P, T, L controlers at operating conditions Q D DD Q D DD Q D DD Magnets 1.9K control Beam screen T control

S. ClaudetLHC Cryogenics - CryoOps 2008 Electrical feed boxes (4 to 8) QRL Cool-down using mostly Flow controlers T, L controlers at operating conditions Filling valve Current leads control

S. ClaudetLHC Cryogenics - CryoOps 2008 Cryo conditions for powering Cryo Start: set of conditions to allow powering of concerned sub-sector (rather strict = good stability of process) Cryo Maintain: Few important conditions checking integrity of HW, with slow power abort in case this signal is lost

S. ClaudetLHC Cryogenics - CryoOps 2008 LHC Cryogenics power permit The cherry on the cake ! 20 months after start of cool-down

S. ClaudetLHC Cryogenics - CryoOps 2008 Downtime - Availability  Rather good availability already a few weeks after 5 TeV qualification  Failure rates of services to be improved  Cryo recovery time to be improved with more robust automation Open Days Training Quenches Power failures Promising period ! Target Autumn’08: < 12 h for stop CC [OK] < 36 h for full sector stop [24h]

S. ClaudetLHC Cryogenics - CryoOps 2008 Content Introduction to LHC cryogenics Cool-down, cryo tuning for magnets HWC Functional analysis - Controls - Availability Perspectives Summary

S. ClaudetLHC Cryogenics - CryoOps 2008 Organisation of resources Cool-down of 8 sectors: –Performed with “cryo island” based teams HWC of many sectors in parallel: –Since mid Jan’08, operators up to 22h and Saturdays –Since Spring’08, two shifts (week) and Saturdays (day) First beams: –We do not have CERN staff (alone) for any kind of shift –Various type of shifts possible via our industrial partner, with CERN experts and local control rooms (day time) in back-up After July 2009: –End of present operation contract, with in-sourcing plus “Field Support Unit” as reference solution, to be re-evaluated end 2008 Sept. to Nov’08: 2 x (3x8h-7d/7d) in CCC LHC Cryo OP Learning to master LHC cryogenics, education of teams while updating controls based on ecperience, towards sites-machines-operations duties

S. ClaudetLHC Cryogenics - CryoOps 2008 Summary Confirmation of cooling principle, heat loads, thermometry channels, machinery, global system behaviour The LHC cryogenic system has been progressively put into service with obvious signs of “learning curve”, and promising periods for possible beams Consolidation program started and continued (valves, DFB’s, instrumentation & controls, helium guards) now extended as well to services Slowly preparing the switch from HWC to operation for beam, with reasonable confidence but with minimal tools and staff