Mu2e Accelerator Independent Design Reviews (IDRs) Steve Werkema Muon Department Meeting 17 December 2015.

Slides:



Advertisements
Similar presentations
Stefan Roesler SC-RP/CERN on behalf of the CERN-SLAC RP Collaboration
Advertisements

Executive Session Director’s CD-1 Follow-Up Review of the APUL Project November 2-3, 2009 Dean A. Hoffer.
Muon g-2 Inflector AEM Meeting 11/25/2013 Chris Polly Muon g-2 Project Manager.
Software Quality Assurance Plan
Neutrinos from Stored Muons STORM Target Station Conceptual Design 15-April-2013 Kris Anderson Fermilab/Accelerator Division/Mechanical Support Department.
Muon Campus Projects Mary Convery 1. Background on Muon Campus plan Earlier Plan had 5 Common Projects:  MC1 Building (GPP)  MC Beamline Enclosure (GPP)
1 Activation problems S.Agosteo (1), M.Magistris (1,2), Th.Otto (2), M.Silari (2) (1) Politecnico di Milano; (2) CERN.
Software Quality Assurance Inspection by Ross Simmerman Software developers follow a method of software quality assurance and try to eliminate bugs prior.
An updated Baseline Design for MICE From proposal to technical reference Paul Drumm, Dec 2003.
A Review ISO 9001:2015 Draft What’s Important to Know Now
NOvA meeting PIP Update W. Pellico. PIP Goals and Scope (Provided in 2011 – Directorate S. H. / DOE Talk ) Goals: Specific to the issues surrounding the.
Protection Against Occupational Exposure
Muon Campus Controls Update Brian Drendel 8/6/13.
NUMI NuMI Review of the Infrastructure – W, G & V 20 July 2001 WBS Page 1 1 Infrastructure Review - W.B.S Water Systems Water Systems –Upstream.
NuMI NuMI Overview NBI 2002 S. Childress (FNAL) 14 March ‘02 NuMI / MINOS Overview.
SNuMI 1 Outline Action Items PP2 Progress [Nancy/Elaine] –Org Chart Update –FY07 Budget/Plans Discussion –FY08 Summer Shutdown –Overall cost Reduction.
Muon Campus Projects Jerry Annala Jan 23, µ AIP Scope Recycler RF system to provide needed bunch structure to future Muon Experiments Recycler RF.
PA Department of Environmental Protection Continuous Source Monitoring Manual (Manual, Revision 8)
1 Status of EMMA Shinji Machida CCLRC/RAL/ASTeC 23 April, ffag/machida_ ppt & pdf.
Mu2e WBS 2 Accelerator Progress Report Mu2e WGM 6/15/2011 Steve Werkema L2 Manager for the Accelerator Systems.
NUMI NuMI Internal Review July 12, 2001 Infrastructure: Radiation Safety Page 1 Technical Components NuMI Beamline Radiation Safety Issues Radiation Safety.
J. G. Weisend II Deputy Head of Accelerator Projects April 2, 2014 Actions at ACCSYS Resulting from the Recommendations of the Annual Review.
WP2 Superbeam Work Breakdown Structure Version 2 Chris Densham (after Marco Zito version 1 )
July LEReC Review July 2014 Low Energy RHIC electron Cooling Edward T. Lessard ESHQ.
J. Pozimski UKNF WP1 meeting 10 March 2010 UKNF WP1 milestone table status.
1 BROOKHAVEN SCIENCE ASSOCIATES Storage Ring Commissioning Samuel Krinsky-Accelerator Physics Group Leader NSLS-II ASAC Meeting October 14-15, 2010.
Mu2e WGM 11/16/2011 R. Ray Mu2e Project manager. Review of the past few months In September it became apparent that the cost of Mu2e was well in excess.
Overview: Primary Sensitivities Nov S. Childress Page 1 NuMI Overview: NuMI Primary Beamline Sensitivities NuMI requirements are for a very large.
MICE Status & Plans MICE-UK paul drumm 15 th September 2004.
Conventional Construction Working Group Meeting Tom Lackowski L2 Conventional Facilities Mu2e Working Group.
Beam line Experiment area SC magnet Pion production target
Accelerator Issues Fermilab Antiproton Experiment Keith Gollwitzer Antiproton Source Department Accelerator Division Fermilab.
Radiation Protection aspects for SHIP Doris Forkel-Wirth, Stefan Roesler, Helmut Vincke, Heinz Vincke CERN Radiation Protection Group 1 st SHIP workshop,
MICE Coupling Coil Testing at Fermilab All Experimenters Meeting Ruben Carcagno March 19, R. Carcagno - MICE CC Testing at Fermilab3/19/2012.
Project X RD&D Plan Beam Transfer Line and Recycler Injection David Johnson AAC Meeting February 3, 2009.
Mu2e Mu2e CD-2 Review Template Eric Prebys Extinction October 21-24, 2014.
High Rate Tracking Test Beam Area David Christian & Richard Coleman.
Global Design Effort - CFS DESY Accelerator Design and Integration Meeting 1 ACCELERATOR INTEGRATION AND DESIGN MEETING CONVENTIONAL FACILITIES.
Risk Analysis P. Cennini AB-ATB on behalf of the n_TOF Team  Procedure  Documents in preparation  Conclusions Second n_TOF External Panel Review, CERN,
SNuMI 1 Outline Action Items PP2 Progress [Nancy/Elaine] –Org Chart Update –FY07 Budget/Plans Discussion –FY08 Summer Shutdown –Overall cost Reduction.
 A model of beam line built with G4Beamline (scripting tool for GEANT4)  Simulated performance downstream of the AC Dipole for core of beam using  x.
ILC 2007 Global Design Effort 1 Planning Damping Rings Activities in the Engineering Design Phase Andy Wolski Cockcroft Institute/University of Liverpool.
Proton-Driven Plasma Wakefield Acceleration CERN Project Structure Edda Gschwendtner, CERN Lisbon Meeting, 22 June 2012Edda Gschwendtner, CERN2.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Shielding Workshop R. Casey Activation Issues for NSLS-II March 28, 2007.
NuMI PS Specs June 2001 S. Childress Page 1 NuMI NuMI requirements are for a very large fraction of the available Main Injector intensity over a period.
Mu2e Mu2e Remote Handling Review Comparisons: Costs, Risks & Maintainability Ryan Schultz Deputy L3 Manager Target Station 3/3/2015.
Brian Drendel September 11, Funding and Deadlines Muon Campus Controls  Controls plan for existing buildings  Controls plan for new buildings.
Muon Department Meeting Jerry Annala Staged Commissioning of Muon Campus 17 December 2015.
Organization and Implementation of a National Regulatory Program for the Control of Radiation Sources Program Performance Criteria.
WBS – 30 Straight Section Reconfiguration g-2 Accelerator – 30 Straight Section Reconfiguration D. Still Fermilab Muon g-2 IDR, June 5-7.
Muon Long Term Schedule August 15, µ Points to discuss What is the schedule What is the schedule Shutdown schedules Shutdown schedules How do we.
MI Shielding Machine Protection Credit D. Capista March 7,2010.
K. Long, 25 June, 2016 IDR: structure and overall timeline: Slides are to introduce discussion of how we prepare IDR. Propose to revise slides as we discuss.
RFQ Installation Plan PIP-II Meeting, 14-July-2015 C. Baffes for R. Andrews, A. Chen, Y. Czajkowski, S. Kazakov, R. Pasquinelli, D. Peterson, O. Pronitchev,
Maximum Credible Beam Loss in the Main Injector D. Capista January 26, 2012.
1 Target Introduction Chris Densham STFC/RAL Mu2e Target, Remote Handling, and Heat & Radiation Shield Review Nov
Fermilab Limited Scope Accelerator Readiness Review (ARR) October 1 -3, 2013 Technical Breakout Session 2A Radiological Safety for 700 kW Operations.
Radiation Protection Standards for Prompt Radiation Don Cossairt, Radiation Protection Manager, ESH&Q Section October 1, 2013.
The ESS Target Station Eric Pitcher Head of Target Division February 19, 2016.
Primary Design Parameters July 13,2001 S. Childress Page 1 NuMI Besides design specifications driven by physics and Main Injector beam parameters, significant.
Shielding Design for LCLS Injector Operation – Phase one
News and brief overview of Beamline plans for the next few months
South Carolina Perspective on Part 61 Proposed Revisions
Spoke CDS PDR Closeout J. G. Weisend II June 10, 2016.
K. Tilley, ISIS, Rutherford Appleton Laboratory, UK Introduction
Review of TDR Chapter 11 “Safety”
PSS verification and validation
M. Kezunovic (P.I.) S. S. Luo D. Ristanovic Texas A&M University
Test Beamline System Requirements and Charge to PDR Committee
Charge and Agenda of the 18th TAC meeting
Presentation transcript:

Mu2e Accelerator Independent Design Reviews (IDRs) Steve Werkema Muon Department Meeting 17 December 2015

Mu2e Accelerator Systems Design Review Status Review Start Date StatusReport Proton Beam Absorber 2/23/2015CompleteFinal Resonant Extraction 8/25/2015CompletePending External Beamline10/6/2015CompleteFinal Instrumentation & Controls10/6/2015CompleteFinal Radiation Safety10/20/2015CompleteFinal Radiation Safety Simulation Review10/20/2015CompleteFinal External Extinction System11/02/2015CompleteFinal Extinction Monitoring System11/02/2015CompleteFinal Target (Target, Target Handling, HRS)11/16/2015CompleteDraft Delivery Ring RF11/19/2015CompleteDraft HRS Protection Collimator1/19/2016Delayed 12/17/2015S. Werkema | Mu2e IDRs2 CD-3c Director’s Review: Late March 2016 CD-3c DOE Review: ~June 2016

Review Recommendations Resonant Extraction (From closeout report) Resonant Extraction (From closeout report) 1.The spill correction system should be on the risk list. The backup option should be developed to the technical design level. 2.A more comprehensive analysis of beam faults and their detection needs to be done, with a focus on building a realistic fault matrix. 3.Simulations need to have a better model of the apertures and an improved model to anticipate operational conditions. 4.The impact of poor field quality needs to be quantified. 5.If found necessary, field quality of the magnets should be corrected to meet requirements. 6.Power supply ripple measurements need to be made to better determine the RFKO kicker strength, prior to construction. 12/17/2015S. Werkema | Mu2e IDRs3

Review Recommendations External Beamline External Beamline 1.Perform error analysis of the beam line optics including the full set of imperfections: magnet tilts, field calibrations and if practical, higher order field effects in the Delivery Ring extraction and final focus sections. 2.Do a beginning-­to-­end integrated calculation, including the effect of Production Solenoid on the optics of the final focus and beam transport. 3.Verify that activation of the LCW flowing through the HRS will not introduce radioactive contamination issues when that water is mixed with the general LCW system. In particular, if the LCW is also used to cool the SCR power supplies that are not in the tunnel. 4.Prepare a justification for the vacuum requirements that can be presented at the CD3 review. 5.Retain in the risk register all risks identified in the Technical Design Report or address as retired. This ensures that none of them slip through the cracks. Instrumentation and Controls Instrumentation and Controls 1.Pursue a location and test the remaining questions about the performance of the profile monitors in the fringe field of the production solenoid. 12/17/2015S. Werkema | Mu2e IDRs4

Review Recommendations Radiation Safety Radiation Safety 1.Recommend that as new shielding analysis is completed, that those documents be added to the applicable PSA document database entry for inclusion in the final shielding assessment. 2.To facilitate the final Shielding Assessment (SA) Review, Safety Assessment Document development, and Accelerator Readiness Review processes, it is recommended that the Mu2e Shielding Assessments cover the entire assessment boundary of their primary and secondary beam from the AP1/MI line extraction critical devices in F sector through the experimental hall. 3.The final SA should cover or list all the penetrations within the assessments boundaries. The PSA appears to be missing the penetrations from the enclosure to the AP-10, 30, and 50 service buildings and the site riser penetrations. 4.Beams Doc 4611 and Beams Doc 4513 sections to 2.2.9, are practically identical sections, word for word. Clearly this is a style comment, however even with this now known, the number for the exhaust fan changes from 800 to 900 respectfully. Recommend that the fan speed be defined and consistently used within the final SA and associated supporting analysis documents. 5.Beams Doc 4494-v7 is the justification for the critical devices that clearly describes the lack of primary transportation of protons. However it doesn’t analyze where the lost beam would go, and the areas affected, such as prompt dose rates into the MC-1 since its occupancy status is unclear. Recommend updating the analysis with the effects of the beam loss in the critical device. 6.Beams Doc 4513 Section 2.2.1, 40 mrem/hr is high for a DC rate of beam loss. This section calls out that the building will be posted as a Radiation Area. The parking lot dose rates are also noted as several mrem/hr and additional shielding or fencing could be used if necessary. Recommend initiating discussions with relevant stakeholders and the AD Operational RSO to determine the access limits and operational effects. 7.Recommend the ODH analysis calculations be completed, identify the location of air isolation curtain locations, and how the air isolation curtains affect the movement of radioactivated air. 8.Recommend identifying which organization, AD or PPD, is responsible for enclosure oxygen monitoring. 9.Recommend either AD or PPD be responsible for all tunnel oxygen monitoring. 10.Recommend initiating discussions with the AD Operational RSO to determine where operational airborne activation monitoring will be needed and where that scope fits into the overall project structure. 11.Groundwater and surface water was covered in section and 2.2.8, with a reference to document Mu2e Doc However this document did not cover the AP-30 extraction region where a known loss point occurs. In addition this document, 1553, reflects earlier versions of MARS and earlier versions of the construction design of the facility. Recommend updating both the MARS model to the current civil design and adding the MI-30 extraction region the groundwater and surface water activation analysis. 12.In the FESS review of the proposed in tunnel shielding for the MI-30 resonant extraction region, Mu2e-doc-6152_ADMSD14-001_FESS_Review.pdf, the reviewer "TL" stated "I have not performed a numerical check but a detail check should be made. The bearing on the concrete slab shall be limited to 1400 psi." It is recommended that this detailed check be performed and documented. 13.It is mandatory that prompt dose and air activation MARS simulations are always done down to thermal neutron energy of 1.e-12 GeV. The committee has checked this for a few cases, but recommends to be sure that this is always the case. 14.It is mandatory that all calculations in the categories presented at the Review are done with one of the two variance-reduction techniques in the MARS code: (1) A track-length probability scoring mode, INDX 6=T, or (2) Multi-stage method. Each of these has its own pros and cons. The first one is more appropriate for thick shielding of complex geometry, provides accurate estimate of statistical errors, is easy to use, but can be more CPU-time consuming. The second one requires less CPU time, but more human efforts with calculation of correct statistical errors being a non-trivial task. At high statistics, both methods converge to the same result. All the results presented at the Review are obtained with the second method that is quite acceptable for the configurations and shielding thicknesses considered in the project. The committee recommends to run MARS with the first method for one of the cases with thickest shielding to check for the consistency of the results and statistical errors. 15.An advanced module newly developed for very detailed air activation calculations will be available in the next release of the MARS15 code in November. It is recommended to redo with the new version one of the typical simulations presented at the Review to see a possible difference in the results and rescale the earlier data if needed. 12/17/2015S. Werkema | Mu2e IDRs5

Review Recommendations Extinction Extinction 1.The committee recommends building a 1m, 18mm gap prototype magnet. Extinction Monitoring Extinction Monitoring 1.Thecommitteerecommendstheearlydevelopmentofacommissioningpl anforthefullextinctionandmonitoringsystem. 12/17/2015S. Werkema | Mu2e IDRs6

Review Recommendations Target Station (DRAFT Report) Target Station (DRAFT Report) 1.HRS stagnant water next to the welds in the maximum radiation area may accelerate corrosion in the welded areas, leading to a leak into the vacuum space. This risk needs to be evaluated. 2.The coil design needs to be reviewed to assure it can support the weight of the HRS during installation. 3.Further develop all the remote handling room monorail operations. Using a standard hoist with no hook rotate feature will significantly affect operations along with the design of the lifting fixtures and components being lifted. 4.Remote handling system Instrumentation and Controls design, including the operator control station, should be considered in the near term to better understand ramifications on the hardware design. Considerations should include feedback sensor requirements. 5.Consider remote viewing needs. The single borescope on the remote handling system may not be adequate for totally remote operations. Additional cameras on the remote handling system will likely be required. All this may dictate a more sophisticated viewing station. 12/17/2015S. Werkema | Mu2e IDRs7

Review Recommendations Delivery Ring RF (Draft Report) Delivery Ring RF (Draft Report) 1.Additional simulations should be performed to include the phase and energy variations. Simulations using the Recycler Ring model should be performed with the inclusion of the cavity impedances. The effects of the Higher-Order Modes of the cavities should be investigated. The documentation of the simulations needs to be updated for the CD-3c review. 2.The beam studies that the experiment and the Accelerator Division would like to be capable of performing must be specified and the final configuration of the LLRF system must be determined and reviewed. Considerations for beam study modes must also include radiation shielding limits. 12/17/2015S. Werkema | Mu2e IDRs8