Managing Schedule Slack/Float PMI Scheduling Forum January 6, 2015 January 6, 2015 Presented by: Ric Albani, PMP, PMI-SP, PMI-RMP, MCTS.

Slides:



Advertisements
Similar presentations
Project Management Concepts
Advertisements

Lecture Network Analysis
DISTRICT FIVE CONSTRUCTION CONTRACT ADMINISTRATION UPDATE TRAINING Submission of Working Schedule Specification SP A.
CP Chapter 4 Schedule Planning.
Work Breakdown Structures
CSSE Sep.2008 Constructing and Analyzing the Project Network Diagram Chapter 6.
Developing a Project Plan
Advanced Project Management - CPH
CSSE 372 Week 6 Day 2 Constructing and Analyzing the Project Network Diagram  PERT Chart PERT was invented for the Nautilus submarine project. Ok, maybe.
Critical Path and Gantt
CS3500 Software Engineering Project Management (1) In 1986 one well-known software engineer (Tom DeMarco) made the simple but important observation: “You.
5.8 Project Management Chapter 37 HL - Only.
Systems Analysis and Design 9th Edition
Systems Analysis and Design 8 th Edition Chapter 3 Managing Systems Projects.
Copyright © 2009 T.L. Martin & Associates Inc. Chapter 2 Key CPM Scheduling Terms.
Importance of Project Schedules
Systems Analysis and Design 8th Edition
©Ian Sommerville 2004Software Engineering, 7th edition. Chapter 1 Slide 1 Project management.
Class 28: Chapter 16: Project Management Class 28 Agenda –Collect Player Diary 2 and Conduct Player Audit No ed diaries – 5 PM Deadline –Discuss Grade.
©Ian Sommerville 2004Software Engineering, 7th edition. Chapter 5 Slide 1 Project management.
Project Time Management
Project Management Methodology Project monitoring and control.
HIT241 - TIME MANAGEMENT Introduction
© 2006 ITT Educational Services Inc. System Analysis for Software Engineers: Unit 5 Slide 1 Chapter 3 Managing the Information Systems Project.
Toolkit 4.
Chapter 3 : Managing the Information Systems Project.
Lesson №2. is the unique activity that has a beginning and an end time, aimed at achieving a predetermined result/goal, the creation of a specific, unique.
Amin Salari, CCM, PMP, LEED AP – Lundgren Management
Cristina MîndruţăSoftware Project Management Slide 1 Software Project Management Course 5.
Project Management OPER 576 Resource Allocation Greg Magnan, Ph.D. May 6, 2004.
4 th European Project Management Conference, London, 6-7 June 2001 Resource Critical Path Approach to Project Schedule Management Vladimir Liberzon, PMP.
Project Time Management One Minute Thirty Second Overview One Minute Thirty Second Overview.
Lecture 3 Scheduling CSCI – 3350 Software Engineering II Fall 2014 Bill Pine.
IT Project Management, Third Edition Chapter 6 1 Chapter 3: Project Time Management.
BIS 360 – Lecture Two Ch. 3: Managing the IS Project.
Lecture 7. Review of Lecture 6 Project Scheduling: The process of defining project activities, determining their sequence, estimating their duration Scheduling.
1 L U N D S U N I V E R S I T E T P rojektledning och Projektmetodik.
Managing Project Resources. Project Resources Human Resources Project stakeholders: – Customers – Project team members – Support staff Systems analyst.
© The McGraw-Hill Companies, Software Project Management 4th Edition Resource allocation Chapter 8.
1IT Project Management, Third Edition Chapter 6 Chapter 6: Project Time Management.
PMP, CAPM, PgMP, PMI-SP, PMI-RMP, OPM3 and PMBOK are registered marks of Project Management Institute, Inc Inov8Solutions Inc – Quality Educational Services.
Advanced Project Management Project Time Management Ghazala Amin.
Chapter 6: Project Time Management Information Technology Project Management, Fourth Edition Using Critical Chain Scheduling, PERT, and MS Project 2003.
Chapter 3 Managing the Information Systems Project
Chapter 7 – PERT, CPM and Critical Chain Operations Management by R. Dan Reid & Nada R. Sanders 4th Edition © Wiley 2010.
Project Time Management Ashima Wadhwa. Schedule Development – Determining start and finish dates for project activities – Without realistic dates, project.
Dependencies and Network Diagrams. Agenda Dependencies Milestones The Network Early/Late Start/End dates Slack/Float Critical Path.
Microsoft Project 2010 ® Tutorial 5: Tracking Progress and Closing the Project.
SOFTWARE PROJECT MANAGEMENT
Project Management Fundamentals - Planning Tools 1.
Develop Schedule is the Process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule.
GAO’s Cost and Schedule Assessment Guides U.S. Government Accountability Office Applied Research and Methods Cost Engineering Sciences Jason T Lee, Assistant.
Develop Schedule is the Process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule.
BSBPMG503A Manage Project Time Manage Project Time Project Time Processes Part 2 Diploma of Project Management Qualification Code BSB51507 Unit Code.
Understanding the Scheduling Formula and Critical Path Calculation PMI Scheduling Forum October 5, 2010 Presented by: Ric Albani, PMP, PMI-SP, MCTS.
MANAGEMENT of INFORMATION SECURITY, Fifth Edition.
Time Planning and Control Time-Scaled Network
Establishing and Managing a Schedule Baseline
Software Development & Project Management
In this tutorial you will:
Time Planning and Control Time-Scaled Network
Project Time Management
1 Total Slack A 3d Task Early Start Late Start Early Finish
Project Time Management
Project Time Management
Project Time Management
Importance of Project Schedules
Project Time Management
Managing Project Work, Scope, Schedules, and Cost
Presentation transcript:

Managing Schedule Slack/Float PMI Scheduling Forum January 6, 2015 January 6, 2015 Presented by: Ric Albani, PMP, PMI-SP, PMI-RMP, MCTS

Introduction U.S. Government Accountability Office (GAO) Published a Schedule Assessment Guide for Scheduling Best Practices. Developed as an accompaniment to a previously published Cost Estimating and Assessment Guide. Used across the federal government to develop, manage, and evaluate capital programs. Based on the concept that a well-planned schedule is a fundamental management tool for ensuring public funds are spent effectively. 2

Introduction GAO Schedule Assessment Guide 10 Best Practices: 1.Capturing all activities 2.Sequencing all activities 3.Assigning resources to all activities 4.Establishing the duration of all activities 5.Verifying that the schedule can be traced horizontally and vertically 3

Introduction GAO Schedule Assessment Guide 10 Best Practices: 6.Confirming that the critical path is valid 7.Ensuring reasonable total float 8.Conducting a schedule risk analysis 9.Updating the schedule using actual progress and logic 10.Maintaining a baseline schedule 4

Introduction Why care about float? Float is an indicator of a schedule’s flexibility. A delay to an activity does not always delay downstream activities unless float is evaluated. Activities with the lowest float values constitute the highest risk to schedule completion or interim milestones. An activity’s delay causes total float to decrease, thus increasing the risk of not completing the project on time. 5

Introduction On some projects: Effective management of both the critical path and float is lacking. Too much emphasis is placed solely on start and finish dates. Not everyone knows that two sets of scheduled dates exist for every activity: -Early Start/Late Start -Early Finish/Late Finish Not everyone knows that for most scheduling software: Start=Early Start and Finish=Early Finish 6

Calculating Total Float 7 Task A Task B Task D Task E Task C Task F StartFinish Forward Pass  calculates “early” dates  Backward Passcalculates “late” dates The difference between late and early dates is float

Calculating Total Float 8 Task A Task B Task D Task E Task C Task F StartFinish Path A-B-C is critical due to having zero slack Path D-E-F is non-critical with 1 day of slack

Float Definition Two Types of Float: Total Float is the amount of time an activity can be delayed or extended before the delay affects the project’s finish milestone. Free Float is the portion of an activity’s total float that is available before the activity’s delay affects its immediate successor. 9

Float Facts Can be positive, negative, or zero. Negative float usually results from having a constraint on an activity which is earlier than its calculated late finish. An activity with zero or negative total float is considered critical. Knowing the amount of time an activity can or cannot be delayed is essential to successful resource allocation and to completing the project on time. 10

Float Facts Float should not be treated as schedule contingency. Schedule contingency should be applied to specific activities according to prioritized risks. Activities on the same network path share total float. 11 Task X 5 days Task Y 3 days Task Z 1 day

Common Barriers to Valid Float Unreasonable amounts of total float usually result from missing or incomplete logic. Missing activities, missing or convoluted logic, and date constraints prevent the valid calculation of total float. Unrealistic activity durations; or un-statused work will distort the value of total float. Good schedule development techniques are imperative to having valid float 12

Reasonableness of Float Float will differ among activities given their logical sequence in the network and overall project duration. Large amounts of float may be justified given the activity’s place in the flow of work. Assess whether it makes sense logically that an activity with high float can slip that far without affecting the project’s finish date. If too little float is built into the schedule, then recovery from inevitable delay may be limited. Float should be evaluated equally along with start/finish dates 13

Float Management Management must: Know that the critical path can’t be correctly monitored without also monitoring float. Understand the amount of time an activity can or cannot be delayed to allocate resource and to re-sequence work. Balance the use of float knowing that float is shared along a path of activities. Know that free float is important in resource leveling since leveling usually targets activities with free float first. Determine what float value constitutes ‘critical’ by evaluating the project’s risk, urgency, technological maturity, complexity, and funding profile. 14

Total Float Checklist Ensure that:  Total float values calculated by the scheduling software are reasonable and accurately reflect true scheduling flexibility.  The project really has the amount of schedule flexibility indicated by the levels of float.  Any activities with high float are examined for missing or incomplete logic.  Total float values that are excessive are documented for justification.  Float for deliverables and milestones are evaluated for reasonableness. 15

Total Float Checklist Ensure that:  Total and free float are used to inform management as to which activities can be reassigned resources.  Management balances the use of float knowing that total float is shared along a path of activities.  Periodic reports are used to show the amount of float consumed in a period and remaining on critical and near- critical paths.  Date constraints causing negative float are justified. 16

Questions? 17

Ric Albani