1 7/9/2009 PHENIX WEEKLY PLANNING 7/9/2009 Don Lynch.

Slides:



Advertisements
Similar presentations
1 12/3/2009 PHENIX WEEKLY PLANNING 12/3/2009 Don Lynch.
Advertisements

1 05/14/2009 PHENIX WEEKLY PLANNING 5/14/2009 Don Lynch.
1 6/25/2009 PHENIX WEEKLY PLANNING 6/25/2009 Don Lynch.
2/2/20121 PHENIX WEEKLY PLANNING 2/2/2012 Don Lynch.
1 9/3/2009 PHENIX WEEKLY PLANNING 9/3/2009 Don Lynch.
2/9/20121 PHENIX WEEKLY PLANNING 2/9/2012 Don Lynch.
PHENIX WEEKLY PLANNING 5/17/2007 Don Lynch. 5/17/2007 Weekly Planning Meeting 2.
PHENIX WEEKLY PLANNING 5/31/2007 Don Lynch. 5/31/2007 Weekly Planning Meeting 2 Schedule End of Run Party 6/29/07 Next Maintenance Day 6/6 or 6/13/07?
1 7/02/2009 PHENIX WEEKLY PLANNING 7/2/2009 Don Lynch No Meeting this week due to July 4 th holidays. Slides have been updated. Next planning meeting will.
1 2/12/2009 PHENIX WEEKLY PLANNING 2/12/2009 Don Lynch.
1 1/22/2009 PHENIX WEEKLY PLANNING 1/22/2009 Don Lynch.
1 1/13/2011 PHENIX WEEKLY PLANNING 1/13/2011 Don Lynch No Meeting Today Due to snow shortened work week, today’s planning meeting has been cancelled. Slides.
1/5/20121 PHENIX WEEKLY PLANNING 1/5/2012 Don Lynch.
8/9/20121 PHENIX WEEKLY PLANNING 8/9/2012 Don Lynch.
1 3/5/2009 PHENIX WEEKLY PLANNING 3/05/2009 Don Lynch.
12/26/2013-1/2/ PHENIX WEEKLY PLANNING Dec. 26, Jan. 2, 2014 Don Lynch.
PHENIX WEEKLY PLANNING 4/10/2008 Don Lynch. 04/10/08 Shutdown ’08 Schedule Purge Flammable Gas, Magnet & DAQ TestsDone Remove lock-out & open shield wallDone.
12/29/20121 PHENIX WEEKLY PLANNING 12/29/2011 Don Lynch.
PHENIX WEEKLY PLANNING 2/14/2008 Don Lynch. 1/31/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going CM Crane.
1 11/5/2009 PHENIX WEEKLY PLANNING 11/5/2009 Don Lynch.
1 2/26/2009 PHENIX WEEKLY PLANNING 2/26/2009 Don Lynch.
1 11/12/2009 PHENIX WEEKLY PLANNING 11/12/2009 Don Lynch.
PHENIX WEEKLY PLANNING 3/6/2008 Don Lynch. 3/6/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going CM Crane.
Technical Support /1/08 PHENIX WEEKLY PLANNING 5/1/2008 Don Lynch.
PHENIX WEEKLY PLANNING 6/29/06 Don Lynch. 6/29/2006 Weekly Planning Meeting 2 This Week TOF W tests continue, modification decisions made? New HV connector.
1 10/8/2009 PHENIX WEEKLY PLANNING 10/8/2009 Don Lynch.
PHENIX WEEKLY PLANNING 3/27/2008 Don Lynch. 3/27/2008 Weekly Planning Meeting2 Shutdown ’08 Schedule CM Crane ReviewMar Purge Flammable Gas, Magnet.
5/1/ PHENIX WEEKLY PLANNING May 1, 2014 Don Lynch.
PHENIX WEEKLY PLANNING 2/2/06 Don Lynch. Prep Schedule for Run 6 BBC N&S dried, tested re-installed, final tested [DONE] MuTr FEE and anode purge lines.
PHENIX WEEKLY PLANNING 11/2/06 Don Lynch. 11/2/06 Weekly Planning Meeting 2 New Detectors TOF West HBD RXNP MPC North.
PHENIX WEEKLY PLANNING 3/22/2007 Don Lynch. 3/22/2007 Weekly Planning Meeting 2 Schedule Re-Start 5 man shifts 3/20/07 Beam: blue ring 3/8/07, in yellow.
PHENIX WEEKLY PLANNING 1/10/2008 Don Lynch. 1/10/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC Tent preparationOn Going1/18 Gas.
1 7/23/2009 PHENIX WEEKLY PLANNING 7/23/2009 Don Lynch.
PHENIX WEEKLY PLANNING 2/9/06 Don Lynch. Prep Schedule for Run 6 BBC N&S dried, tested re-installed, final tested [DONE] MuTr FEE and anode purge lines.
PHENIX WEEKLY PLANNING 9/14/06 Don Lynch. 9/14/06 Weekly Planning Meeting 2 PHENIX Shutdown Overview Task_NameStart_DateFinish_Date PHENIX Shutdown '065/1/200612/8/2006.
Technical Support /8/08 PHENIX WEEKLY PLANNING 5/8/2008 Don Lynch.
PHENIX WEEKLY PLANNING 12/6/2007 Don Lynch. 12/6/2007 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC Tent preparationOn GoingOn Going.
1 05/07/2009 PHENIX WEEKLY PLANNING 5/07/2009 Don Lynch.
1 3/10/2011 PHENIX WEEKLY PLANNING 3/10/2011 Don Lynch.
PHENIX WEEKLY PLANNING 10/4/2007 Don Lynch. 10/4/2007 Weekly Planning Meeting 2007 PHENIX Shutdown October 2007: Finish MPC South Installation, replace.
PHENIX WEEKLY PLANNING 12/7/06 Don Lynch. 12/7/06 Weekly Planning Meeting 2.
1 12/30/2010 PHENIX WEEKLY PLANNING 12/30/2010 Don Lynch.
3/20/ PHENIX WEEKLY PLANNING March 20, 2014 Don Lynch.
1/26/20121 PHENIX WEEKLY PLANNING 1/26/2012 Don Lynch.
1 10/15/2009 PHENIX WEEKLY PLANNING 10/15/2009 Don Lynch.
5/12/11 1 PHENIX WEEKLY PLANNING 5/12/2011 Don Lynch.
PHENIX WEEKLY PLANNING 3/15/2007 Don Lynch. 3/15/2007 Weekly Planning Meeting 2 Schedule Cosmic Ray Run (Run 6.9) Done All Up Commissioning On Going Re-Start.
1 8/27/2009 PHENIX WEEKLY PLANNING 8/27/2009 Don Lynch.
PHENIX WEEKLY PLANNING 3/02/06 Don Lynch. BLM Test.
Technical Support /15/08 PHENIX WEEKLY PLANNING 5/15/2008 Don Lynch.
5/24/20121 PHENIX WEEKLY PLANNING 5/24/2012 Don Lynch.
Technical Support /18/08 PHENIX WEEKLY PLANNING 12/30/2008 Don Lynch.
12/19/ PHENIX WEEKLY PLANNING Dec. 19, 2013 Don Lynch.
PHENIX WEEKLY PLANNING 5/7/2007 Don Lynch (Thursday is Monday this week)
PHENIX WEEKLY PLANNING 1/31/2008 Don Lynch. 1/31/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going Switch.
1 9/24/2009 PHENIX WEEKLY PLANNING 9/24/2009 Don Lynch.
1 12/17/2009 PHENIX WEEKLY PLANNING 12/17/2009 Don Lynch.
1 5/19/2011 PHENIX WEEKLY PLANNING 5/19/2011 Don Lynch.
1 1/29/2009 PHENIX WEEKLY PLANNING 1/29/2009 Don Lynch.
1 7/16/2009 PHENIX WEEKLY PLANNING 7/16/2009 Don Lynch.
Technical Support /16/08 PHENIX WEEKLY PLANNING 10/16/2008 Don Lynch.
PHENIX WEEKLY PLANNING 3/1/2007 Don Lynch March: in like a lion Out like a lamb.
1 6/4/2009 PHENIX WEEKLY PLANNING 6/4/2009 Don Lynch.
12/08/20111 PHENIX WEEKLY PLANNING 12/08/2011 Don Lynch.
PHENIX WEEKLY PLANNING 6/8/06 Don Lynch. 6/8/2006 Weekly Planning Meeting 2 This Week Rec’d TOF West Access: move HBD to Dead Turtle Position Sec’y of.
1 8/20/2009 PHENIX WEEKLY PLANNING 8/20/2009 Don Lynch.
1 11/25/2010 PHENIX WEEKLY PLANNING 11/25/2010 Don Lynch.
2/20/ PHENIX WEEKLY PLANNING Feb. 20, 2014 Don Lynch.
1 2/19/2009 PHENIX WEEKLY PLANNING 2/19/2009 Don Lynch.
PHENIX WEEKLY PLANNING 2/14/2008 Don Lynch. 2/14/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going CM Crane.
Presentation transcript:

1 7/9/2009 PHENIX WEEKLY PLANNING 7/9/2009 Don Lynch

2 7/9/2009 Remove interlock from Shield Wall (1 hr)Done Done Purge Flammable gas from IR detectorsDone Done Install electric circuits to burn-in test stand for AC and heaters & to storage racks for humidity controlDone Done Work permits for Shutdown start & DC repairDone Done HV warning lights for cosmic ray & dark current TS in factoryDone Done Work permits for RPC3, MuTrigger/MuTr N&S in progress 7/10 Fabricate RPC3 N base, pitch support, lifting fixtures and ½ octant 7&8 vertical support in progress 7/10 Disassemble and stow Wall & Base (3 -4 days) in progress 7/9 Fabricate Base Locking/Installation fixture in progress 7/10 Fabricate RPC3 N survey fixture in progress 7/10 Fabricate RPC3 adjustable ½ octant cradle in progress 7/10 cleaning and testing of MuTracker HV splitter boxes in progress 7/10 DC FEM Troubleshooting/Repair in progress 7/10 Order Tilt Table Lifters in progress 7/10 Order burn-in test cover and AC control in progress 7/10 Get list of RPC3N installation hardware and place orders in progress 7/10 Fan Tray replacement evaluation and priority plan in progress 7/10 Remove ladder & dumb waiter from EC (1/2 day)7/10 7/10 This Week 7/6 - 7/10 Task Start Date End Date

3 7/9/2009 Next Week 7/13 - 7/17 Task Start Date End Date Receive RPC3 N lifting fixture parts at factory7/137/13 Fold up EC platforms (1/2 day)7/137/17 Test base RPC3 N locking/installation fixture7/137/17 Test base RPC3 N survey fixture7/137/17 Test RMC higher comm speed on EC7/137/17 Simulated RPC installation at RPC Factory (practice/tests) commission all installation components base, locking/install, survey, cradle 7/137/31 Remove MuID collars7/157/15 Receive complete RPC3 N base, pitch support, lifting fixtures & ½ octant 7&8 vertical support 7/157/15 Test and commission RPC3N lifting fixtures at factory with S. Kane/designee as witness7/157/15 Move MMS South7/177/17

4 7/9/2009 Order MuID cable management components in progress 8/1 PC1 East repair fixture: order raw materials, order off-the-shelf components & hardware, receive and inspect components in progress 8/1 Prep RPC3 N racks for installation in progress 8/14 Review PHENIX RPC3 N lifting fixture design and run acceptance test in RPC Factory (3 days) waiting for parts 7/15 Assemble HV, experimental gas and N2 gas distribution and install tent in progress 7/15 Finalize gap 5 N cable and pipe reorganization in progress 7/15 Field Fit ½ octant retaining arm/clamps design to fit in progress 7/15 Assemble Dummy ½ octant and test with tilt table and Burn-in test stand field fit in progress 7/24 Order & receive parts for gap5 N cable management in progress 7/24 Evaluate Gap 5 grout at Factory in progress 7/24 Design concept for Base locking/Installation fixture for RPC3N in progress 7/24 Design RPC3 adjustable ½ octant cradle in progress 7/24 Receive and test MuTrigger FEE’s in progress 7/24 Receive MuTrigger FEE’s cable and connectors, prep and bundle for installation in progress 7/24 Continuing Tasks currently underway Task Start Date End Date

5 7/9/2009 Install MuTrigger FEE Sta 2/3 cable Management and cable runs behind MMS in progress 7/28 Move PHENIX-North tunnel shielding, remove PHENIX-North vapor barrier and crystal palace, repair/replace area lighting in progress 7/31 Move MuID piping, piping supports out of Gap 5 to temporary store area in progress 7/31 Move MuID cables and cable tray out of Gap 5 to temporary store area in progress 7/31 Plan and install 2 new PHENIX gas pad expansion pads in progress9/4 Spec, purchase, install and test instrumentation and monitoring, cables, etc.for rack room AC3 and new electronics water chiller in progress 10/31 Spec, purchase, install and test instrumentation and monitoring, cables, etc.for non-PHENIX fire alarm status panel in progress 10/31 Spec, purchase, install and test power wiring for new DCM racks in progress 10/31 Start Design supports for Beampipe upgrade in progress 11/30 Design & Fabrication support for VTX in progress 11/30 Design support for FVTX in progress 11/30 Design support for FOCal in progress 11/30 Fan Tray replacements (as time permits) in progress 11/30 Continuing Tasks currently underway (cont’d) Task Start Date End Date

6 7/9/2009 Aerogel BBC EMCal HBD (may change) MPC MuID RICH RXNP (no work anticipated) TEC TOF TOF West Detector Subsystems with no specific shutdown support requests

7 7/9/2009 Expected IR Configuration During Shutdown ’09 7/6 – 7/17 Run configuration EC and WC can be moved east/west ~3 ft 7/17-7/22 MMS moved south, CM in run position EC & WC can be moved east/west ~3 ft 7/22-7/28MMS north, Run configuration WC can be moved east/west ~3 ft EC in AH 7/28-10/1 MMS south, CM in run position, EC in AH WC in west position (against wall), scaffolding in station 1 and station 2/3 south 9/25-11/10 MMS, CM & WC positions TBD, EC in AH 11/10–12/1 MMS & CM in run position, EC and WC can be moved east west ~3 ft These dates are approximate and subject to change

8 7/9/2009 Task Start Date End Date Disconnect EC and Move to AH7/207/22 Open MMN hatch and O2 check atmosphere7/207/24 Install ladder/access platform and work platforms for work above MuID steel (3 days)7/207/24 Move MuID plumbing rack on pedestal away From gap 57/207/30 Move MMS North7/227/22 Install IR floor plates, 12 ton cart & manlift7/227/22 Move MuID collars to AH7/237/23 Remove 4 MMS lampshades (2-3 days)7/247/28 Reinstall ladder and dumb waiter on EC in AH and fold down EC platforms (1 day)7/247/31 ID/label gap 5 N cables & pipes and move out of gap 57/277/30 Troubleshoot MUTrigger FEE’s in MMN7/278/31 Troubleshoot MUTr decaps in MMN7/278/31 Move MMS South7/287/28 Install Station 1 Scaffolding (3 days)7/287/30 Inspect Station 1 Scaffolding (1/2 day)7/307/31 Install MuTrigger Station 1 S FEE cable management7/307/31 Remainder of July Schedule

9 7/9/2009 Task Start Date End Date Reconnect EC utilities for shutdown mode8/38/7 Survey tapped holes on MuID5 steel and survey east and west RPC3 N support bases (3 days)8/38/14 Drill and tap MuID gap 5 steel top and north 8/38/14 Install RPC3 N support base & grout (4 days)8/38/14 Install Station 3 N pitch control (unistrut rails) on pedestal and east and west gap 5 north walls and attach to support bases (tall column)8/38/14 Install MMS station 2/3 scaffolding8/38/14 Install Station 1 FEE’s & Electronics and connect cables8/38/28 MuTr decapacitations & MuTr FEE trouble-Shooting in MMS Sta 1&3 8/38/28 MuTr Rack 2 troubleshooting8/38/28 Vendor install Ar dewar & vaporizer8/38/28 Install rails and fences on gas pad8/38/28 DCM rack electric prep8/38/30 MuTr HV and FEE test and evaluation as MuTrigger FEE’s & RPC’s are installed8/311/30 Set up PHENIX “stage” for Summer Sunday Tour8/58/7 Tear down and remove PHENIX “stage” for Summer Sunday Tour8/108/11 August Schedule

10 7/9/2009 Task Start Date End Date Erect PC1 repair tool8/128/14 First ½ octant ready for installation8/178/17 Disassemble DC/PC1 cables & piping8/178/28 Install Station 1 MuTrigger FEE air & water and test8/179/11 Install new gap5 N cable & pipe supports, cables and piping and leak test piping8/179/30 Install RPC3 N ½ Octants (16 days)8/179/30 Final leak test new Ar dewar/vaporizer and Closeout job8/289/4 Move DC on EC to access PC1 east8/319/4 Install Empties racks on gas pad8/319/4 Install MuTrigger FEE station 2/3 FEE’s & Electronics & connect cables8/319/25 August Schedule

11 7/9/2009 Task Start Date End Date Close MMN Hatch and closeout WP9/19/1 Rack room re-organization9/111/30 CM Power upgrade (as toime permits)9/1 11/30 Labor Day Holiday – no work9/79/7 Remove failed PC1 east module9/89/11 Install spare PC1 east module9/89/11 Install 2 RPC3 N racks (1/2 day)9/89/18 Test PC1 spare and verify operation9/149/17 Install MuTrigger FEE station 2/3 air & water plumbing and test9/1410/9 Move DC on EC back to normal position9/189/18 Reconnect cables and piping on DC and PC1 East9/219/25 Remove station 1 south scaffolding9/219/25 Install rack components in RPC3 N racks9/219/30 Final verification tests on PC1 east repair9/289/30 September Schedule

12 7/9/2009 Task Start Date End Date Disassemble and store PC1 east repair fixture10/110/2 Attach cables to RPC3 N racks and to Detector ½ octants 10/110/9 Install new PHENIX north tunnel thermal/vapor barrier replacing crystal palace (1 week)10/110/30 DCM rack supply& Return plumbing10/510/16 Remove MMS Sta 2/3 scaffolding10/1210/23 Commission RPC3 N racks and detectors10/1210/30 DCM rack internal plumbing10/1910/30 Reinstall MMS lampshades (2 days)10/2610/30 October Schedule

13 7/9/2009 Task Start Date End Date November Schedule Install heaters and thermostat(s) for RPC3N thermal control11/211/6 Reinstall PHENIX North tunnel shielding (3 days)11/211/6 Cooldown for Run 10 Starts11/711/7 Move MuID Collars to IR 11/711/7 Disconnect electric & Fiber in EC11/211/7 Remove ladder & dumb waiter from EC & Fold up EC platforms in AH (1 day)11/911/10 Veterans Day Holiday – no work11/1111/11 Remove IR Floor plates and move 12 ton cart to AH 11/1211/12 Move EC to IR11/1211/13 Reconnect electric and fiber to EC11/1611/20 Reinstall ladder & dumb waiter on EC & Fold down EC platforms in IR (1 day)11/1611/20 Pink sheets, white sheets, blue sheets11/1612/1 Move MMS north, Install MuID Collars11/2311/25 Assemble shield wall base and wall in AH11/2311/30 Thanksgiving Holiday – no work11/2611/27 Roll in shield wall11/3011/30 Start Run 10, All shutdown activities completed12/112/1

14 7/9/2009

15 7/9/2009 Other potential work this shutdown: 1. Remove the RPC prototype absorber 2. Prep Bridge for future upgrades

16 7/9/2009 Roof leaks in utility bathroom at northwest corner behind tech offices and over door between rack room and assembly hall. Heat wrap tape for trailer bathroom toilet drains to prevent freeze/clogging in winter. Improved Rack Room AC performance (This item has been addressed time and again but unsatisfactorily. Currently the AC fails periodically and is repaired only to fail again. On-condition maintenance is not adequate…an engineered solution is needed.) Icy conditions at mixing house north stairs Mixing House loose board ? 2009 Building Maintenance Issues

17 7/9/2009 Safety, Security, etc. The shutdown has started. We want to be a model of safety at PHENIX. Some things to remember. 1. Use appropriate PPE: gloves when handling materials, hard hats when cranes are in use or when working on lower levels of scaffolds with others working above. 2. During shutdown, PHENIX engineers and technicians, CAD engineers and technicians, bargaining unit workers, etc. may direct you to obey safety rules, barriers, etc. Willful violation of such requests may result in disciplinary actions from PHENIX or Lab management. When we work safely we are ultimately more efficient. 3. Remember to lock up at the end of each day, shifts are over. Techs will lock up before they leave, but others who work late must make sure they lock the doors behind them. 4. Read, understand and sign (original) work permits for tasks you are working on. PDF copies of all PHENIX 2009 shutdown work permits and referenced PHENIX controlled procedures are/will be available on the PHENIX engineering web site.

18 7/9/2009 Where To Find PHENIX Engineering Info Links for the weekly planning meeting slides, archives of past meeting slides,long term planning, pictures, videos and other technical info can be found on the PHENIX Engineering web site: Let’s make this a successful shutdown!