The MICE RF System K Ronald, University of Strathclyde For the MICE RF team 1MICE RF Review, 9th September 2015.

Slides:



Advertisements
Similar presentations
Andrew Moss ASTeC MICE RF workshop 16t h February 2012 Daresbury Laboratory Response to RF review for the MICE RF system.
Advertisements

RF Specification discussion MICE RF workshop 16 th April 2012.
Status of the MICE RF System K Ronald, University of Strathclyde For the MICE RF team MICE Project Board & RLSR, 24th November
Andrew Moss ASTeC MICE Project Board 28 th June 2011 MICE RF System.
Progress of the sub-harmonic bunching system (i.e. upgrading progress of BEPCII present bunching system) Pei Shilun for the SHBS team Accelerator center,
MICE Refurbishment of CERN RF equipment for MICE M. Vretenar, CERN AB/RF.
Collaboration meeting, RAL, 4 th – 7th November 2009 Andrew Moss ASTeC Collaboration meeting, RAL, 10 th – 13 th november 2009 MICE RF Amplifier Status.
RF systems for MICE Andrew Moss The MICE RF Group and the TIARA WP7 Team Contributions include Daresbury, RAL, CERN, LBNL, LANL, FNAL, Strathclyde & Sheffield.
Andrew Moss Daresbury Laboratory Collaboration Meeting th 19 th October 2012 RAL MICE RF System review.
Andrew Moss Daresbury Laboratory August 2013 Latest results of MICE amplifier testing.
Status of the MICE RF System K Ronald, University of Strathclyde For the MICE RF team 1MICE Project Board, 17th April 2015.
THE MICE RF SYSTEM J.F.Orrett* A.J.Moss, ASTeC, Daresbury Laboratory, WA4 4AD, UK Accelerator Science and Technology Centre
Paul drumm daq&c-ws august/september Cooling Channel.
Y. Karadzhov MICE Video Conference Thu April 9 Slide 1 Absolute Time Calibration Method General description of the TOF DAQ setup For the TOF Data Acquisition.
H. Haseroth Thursday, February 5-8, 2002 MUCOOL / MICE 1 RF & RF power H. Haseroth CERN  Situation of 88 MHz test cavity  Availability of amplifiers.
MuCool RF Status MICE Collaboration Meeting June 7-10, 2006, Fermilab A. Moretti June 9, 2006.
Status of the MICE RF System K Ronald, University of Strathclyde For the MICE RF team 1MICE Project Board, 17th April 2015.
Status of the MICE RF System K Ronald, University of Strathclyde For the MICE RF team 1MICE Project Board, 17th April 2015.
Andrew Moss ASTeC 7 th December 2011 MICE RF System.
Andrew Moss Daresbury Laboratory Collaboration Meeting th -16 th February 2013 Coseners House MICE RF HP System rprogress.
Collaboration meeting, DL, 19 h – 23 h October 2008 Andrew Moss ASTeC Collaboration meeting, DL, 19 th – 23 th October 2008 MICE RF distribution system.
201 MHz and 805 MHz Cavity Developments in MUCOOL Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory Nufact 2002 Workshop, London,
Emittance measurement: ID muons with time-of-flight Measure x,y and t at TOF0, TOF1 Use momentum-dependent transfer matrices iteratively to determine trace.
Progress on the MICE RF Systems K Ronald, University of Strathclyde For the MICE RF team 1MICE Project Board 14th November 2013.
1 MICE RF Daresbury Laboratory Support Joe Orrett - ASTeC.
Emittance measurement: ID muons with time-of-flight Measure x,y and t at TOF0, TOF1 Use momentum-dependent transfer matrices to map  path Assume straight.
Andrew Moss ASTeC Collaboration meeting CM29 15 th - 18 th February 2011 MICE RF System.
The status of the construction of MICE Step IV K. Long, on behalf of the MICE collaboration.
1 Status of EMMA Shinji Machida CCLRC/RAL/ASTeC 23 April, ffag/machida_ ppt & pdf.
Muon- RF Phase Determination K Ronald, Strathclyde Contributions from many MICE: Tim Stanley, Chris Rogers, Rutherford Lab, Yordan Karadzhov, Geneva, Paul.
Clustered Surface RF Production Scheme Chris Adolphsen Chris Nantista SLAC.
Andrew Moss ASTeC CM32 9t h February 2012 RAL MICE RF System.
Anders Sunesson RF Group ESS Accelerator Division
Status of the MICE Project & Dashboard MICE Project Board 14 th November 2013 Roy Preece.
MICE RF System Power Supplies, Control and Monitoring Status report February 2012 Chris White, STFC Daresbury Laboratory MICE Collaboration Meeting CM32,
1 SPL Collaboration Meeting dec 08 - WG1 Introduction First SPL Collaboration Meeting Working Group 1 High Power RF Distribution System Introduction.
13 th April 2007FFAG 07 Carl Beard EMMA RF System Carl Beard, Emma Wooldridge, Peter McIntosh, Peter Corlett, Andy Moss, James Rogers, Joe Orrett ASTeC,
MICE Status & Plans MICE-UK paul drumm 15 th September 2004.
MICE RF Workshop Alain Blondel MICE = critical R&D for neutrino factory and muon collider 1 neutrino factory: accelerate muons and store to produce.
CLARA Gun Cavity Optimisation NVEC 05/06/2014 P. Goudket G. Burt, L. Cowie, J. McKenzie, B. Militsyn.
Ding Sun and David Wildman Fermilab Accelerator Advisory Committee
MICE: The International Muon Ionisation Cooling Experiment MOPLT106 Abstract The provision of intense stored muon beams would allow the properties of neutrinos.
Progress on the MICE RF High Power Drive Systems K Ronald, University of Strathclyde For the MICE RF team 1MICE CM38 RF Parallel Session.
A. Bross MICE CM17 February MuCool RF Program 805 and 201 MHz Studies.
Progress in the construction of the MICE cooling channel and first measurements Adam Dobbs, EPS-HEP, 23 rd July 2011.
Andrew Moss ASTeC TIARA Mid term meeting 12 th 14 th June 2012 CIEMAT ICTF Progress on the MICE RF System.
MICE RF System Overview Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory Andrew Moss STFC Daresbury Laboratory MICE UK.
Status of the MICE RF System K Ronald, University of Strathclyde For the MICE RF team 1MICE Project Board, 30 th April 2014.
RF Review CM37 Andrew Moss. Amplifier results at Daresbury 2MW at 35kV, good efficiency and gain.
650 MHz Solid State RF Power development at RRCAT
MICE Construction Project Update: SSs, PRY, Cavities, Tracker… 1MAP Friday Meeting – January 30, 2015 Alan Bross.
Status of the MICE RF System K Ronald, University of Strathclyde For the MICE RF team 1MICE Project Board, 6th April 2016.
201 MHz Cavity Plans Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory February 11, 2011 MAP Friday Video Conference Meeting.
MICE Demonstration of Ionisation Cooling Colin Whyte University of Strathclyde On behalf of the MICE collaboration 1RF Review 9th-10th Sept. 2015, Abingdon.
Standalone Commissioning Plan in MICE Hall K Ronald, University of Strathclyde For the MICE RF team 1MICE RF Review 9th Sept 2016.
RF Module Integration Colin Whyte University of Strathclyde on behalf of the MICE collaboration 1RF Review 9th & 10th Sept '15 Abingdon.
US Construction Project: SSs, PRY, Cavities and test program 1.
Linac RF System Design Options Y. Kang RAD/SNS/NScD/ORNL Project – X Collaboration Meeting April , 2011.
RF System to RF Module Interface C Whyte, University of Strathclyde For the MICE RF team 1 MICE RF Module Engineering Review LBNL Center for Beam Physics.
The RF Phase Determination for MICE Alexander Dick For the MICE RF Team.
Muon-transit RF Phase Determination K Ronald, University of Strathclyde For the MICE RF group 1MICE Optics Review, 15th January 2016.
Andrew Moss ASTeC, Daresbury Laboratory October 2010 MICE RF Amplifier Status.
Areal RF Station A. Vardanyan
Status of the MICE RF System
Completion of the MICE-US construction project
MuCool Test Area Dedicated facility built at the end of the Linac to address MuCool needs RF power 805MHz, 201MHz)
RF Layout 3pi/2 for Discussion
An X-band system for phase space linearisation on CLARA
Progress on the MICE RF Systems
SNS Fundamental Power Coupler History
Presentation transcript:

The MICE RF System K Ronald, University of Strathclyde For the MICE RF team 1MICE RF Review, 9th September 2015

Content 2 The MICE experiment Outline of the key features of the apparatus Role of and requirements for the RF system MICE RF Cavities Summary of key features Brief statement of status RF drive system Review of RF drive systems- key components RF and modulator systems LLRF will be addressed by Andy Moss Distribution network Review of simplified ‘over the top’ configuration Muon-RF phase determination Requirements and proposed solution MICE RF Review, 9th September 2015

MICE Experiment 3 MICE will demonstrate the reduction of the emittance of a muon beam Transit of muons through low Z absorbers One primary LiH absorber and two secondary absorbers Secondary absorbers provide some cooling Primarily present to protect detectors Partial restoration of translational momentum by RF cavities Measurement of the emittance both upstream and downstream By scintillating fibre trackers in strong 4 T solenoid fields Each particle measured separately Particle flux is completely asynchronous MICE RF Review, 9th September 2015

MICE High Power RF systems 4 MICE HPRF system requirements have changed Only two cavities, no coupling coil Two cavities bracketed by two thin LiH absorbers, sandwiching main absorber Required operational date on the beamline is Summer 2017 Potential to pre-commission hardware: Starting Aug 2016 Exploit proposal for the RF cavities modules delivered UK Spring 2016 Enables demonstration of ionisation cooling with re-acceleration First results complete before end US fiscal year 2017 MICE RF Review, 9th September 2015

MICE RF system: Accelerating gradient 5 2MW peak output from RF drive amplifiers BUT assume LLRF ~10 % overhead to achieve regulation Estimated <10 % reduction in operating into transmission line and reactive load Power delivered to each cavity 1.62 MW Each cavity fed from two couplers Output from each amplifier split in 90 o hybrids Line lengths balance 90 o phase shifts Anticipated gradient in each cavity 10.3 MV/m Slight uplift in gradient from 7.2 MV/m in each ‘STEP V’ cavity Cavity Q and shunt impedance from simulation Cavity 1 RF Amp 1 LLRF Beamline HPRF RF Drive LLRF Feedback RF RF Amp 2 HPRF Cavity 2 RF Drive MICE RF Review, 9th September 2015

MICE High Power RF cavities 6 RF cavities and couplers The cavities are large room temperature copper cavities built by LBNL Feature large aperture with very thin Be ‘beam’ window for Muon transit Mechanically tuned by mechanical elastic deformation Electropolised to enhance surface quality- mitigate breakdown risk High Q- 50,000, Shunt impedance implies 8 MV/m for 1 MW of input power Fill time ~200  s, 1.62 MW of input power implies 10.3 MV/m This is estimate of power available from a single amplifier chain Only feasible to complete two amplifier chains (one per cavity) in time for operation in 2017 Pragmatically defines the achievable gradient Couplers and RF windows are evolved from the MuCool cavity prototypes Two magnetic loop couplers are required- installed on ‘equatorial’ ports Revised design and coatings inhibits sparking (even in B field) Tested at MTA Production couplers will be further revised to make easier to obtain critical coupling MICE RF Review, 9th September 2015

MICE High Power RF cavities 7 Cavities and Couplers MICE RF Review, 9th September 2015

MICE High Power RF cavities 8 Cavities and Couplers Operation experience at MTA Showed couplers were not easy to tune- now redesigned Relatively minor change to the flange location Showed minor issues associated with tuner actuators- redesigned to remove gas drive chambers from vacuum Tuners shown to be able to keep cavity on frequency Tests to 14MV/m with and without strong magnetic fields No evidence of breakdown with upgraded components B fields are broadly comparable to those at MICE At relatively short pulses (MICE 1ms cf MTA 250  s) MICE RF Review, 9th September 2015

RF drive chain 9 Complex Chain of Amplifiers Source (LLRF) will drive an SSPA (~4kW) SSPA drives a tetrode valve pre-amplifier (250kW) Burle/Photonis 4616 based system Tetrode amplifier drives triode valve amplifier (2MW) Thales TH116 based system MICE has four ‘New’ TH116 valves Production of more could be ‘difficult’ MICE RF Review, 9th September 2015

RF drive chain 10 Tetrode Amplifier and modulator MICE RF Review, 9th September 2015

RF drive chain 11 Triode Amplifier and Modulator MICE RF Review, 9th September 2015

High Power Driver System Amplifiers have achieved required performance ~10dB gain 2.06MW output RF At required duty 34kV bias voltage 129A forward average current  =46% (electronic) Gain 10.8dB Input port return loss -12.5dB VSWR 1.6 Drive from Tetrode 170kW output RF 18kV bias voltage 15.5A forward average current  =61% (electronic) Gain 19dB Drive from SSPA 2.27kW Drive from oscillator 3.7dBm 12 a)HT feedline, b)Output 9 inch coaxial line, c)Input 3 inch line MICE RF Review, 9th September 2015

Installation at RAL Status First amplifier set have been constructed and installed in Daresbury test facility First set of modulator racks completed and installed Achieved required peak power levels At required duty Key lessons: Problems with the HT crowbar on the triode circuit Resolved by changing the HT switch However triode switch peak voltage spec marginal Solution- crowbars for both valve amplifiers will be changed From Thyratron/Ignitron valves to solid state switches Gives higher headroom (triode) and eliminates warm up delay (tetrode) Racks now back at Daresbury for commissioning of triode no 2. Upgrades to modulators will happen during this commissioning phase 13MICE RF Review, 9th September 2015

New Crowbar Tests Tests carried out: – Circuit tests using second switch as a load to trigger the crowbar and measure “arc” energy 14 Test voltage: 24 kV Capacitor: 140 uF Dump resistor: 5 ohms Overcurrent set point: 180 A CH 1 Overcurrent detector (trigger) CH 2 Firing pulse to crowbar CH 3 Capacitor current (10 dB) CH 4 Current in Load Timebase 2.5 us / div Peak current in crowbar: 4.6 kA Peak current in load: 1.2 kA Estimated energy into load: <10J MICE RF Review, 9th September 2015

High Power Driver System: RAL installation Status First amplifier set have been installed at RAL and tested at reduced power levels 15MICE RF Review, 9th September 2015

High Power RF Drive: System Status 16 MICE RF drive systems demonstrated 2MW, at MHz, for 1Hz First amplifier tested in MICE hall Triode amplifier (output stage) remains installed Tetrode and all modulator racks shipped to Daresbury New higher voltage solid state crowbar tested Key lessons: Problems with the HT crowbar on the triode circuit Resolved by changing the HT switch However triode switch peak voltage spec marginal Solution- crowbars for both valve amplifier s will be changed From Thyratron/Ignitron valves to solid state switches Gives higher headroom (triode) and eliminates warm up delay (tetrode) Triode 2 will be tested using No. 1 tetrode and modulators Use upgraded Triode No.1 modulator Each major No. 1 subsystem will be swapped for No. 2 sequentially Make fault finding more rapid Remote control system being developed Test during commissioning of No. 2 valve systems Dependent on electrical engineering resource availability No 1 tetrode re-commissioning commenced at DL Triode No 2 testing with No 1 racks and tetrode autumn 2015 Design/Build Control Rack for No 1 PSU’s autumn-winter 2015 MICE RF Review, 9th September 2015

Flexible coax Line Trimmers Hybrid Splitter Directional Coupler in each line 4616 Pre Amplifier TH116 Amplifier 500kW Load Directional Coupler 6 inch RF network 17 Simplified distribution network- feasible to route overhead Off-centre mounting of hybrid takes up phase shift Orientation of load arbitrary- align with the 6” distribution line and share mountings Minimised length of 4” line- minimises losses MICE RF Review, 9th September 2015

RF network 18 2 nd amplifier moved to 3 rd position behind wall to ease installation in congested area With 2 RF amplifiers now relatively straightforward to place auxiliary systems (cooling) Water cooling for load will need to route over the air gap on the transmission lines Load on each splitter to absorb unbalanced reflections Retracted crane hook clears coax over the wall. Support from present ‘shield wall’ and yoke MICE RF Review, 9th September 2015

RF network 19MICE RF Review, 9th September 2015

Power Distribution Network 20 New experiment will demand higher power (1MW peak, 1kW average) in 4” lines 4” components rated to 1.12MW peak in air at 1 bar A full reflect (during cavity fill or spark) will double line voltage (eq. to 4MW) Mitigate with insulating gas MICE RF Review, 9th September 2015

Timing System, Desired Specification We wish to know the difference between Transit time of any of our muons (in essence through ToF1) A zero crossing of the RF system in any cavity- choose the first cavity Specification for RF timing is ~3x stricter than ToF resolution 50ps 21 ToF 1 Cavity 1 RF Amp 1 LLRF Beamline HPRF RF Drive LLRF Feedback TDC’s (ToF) TDC’s (RF) Digitisers Datarecorders RF Clock Trigger Discriminators (RF) Discriminators (ToF) ToF Signals RG MHz LLRF MO MO Signal (RG213) Computers RF Amp 2 HPRF Cavity 2 RF Drive Cavity 2 (RG213) Cavity 1 (RG213) MICE RF Review, 9th September 2015

Subsample Digitisation of Signal Artificially increase the sample rate of the under sampled signal –Reduces the initial recorded data size reduced Undersampled Signal 22 Reconstructed Signal

Demonstration of subsample approach Butterworth Filter with flat 2MHz passband Very precise reproduction of signal Variation in phase difference Between original and reconstruction Sensitive to original sub-sampling rate

Demonstration of subsample approach Reconstructing by DSP gives high fidelity to filtered raw signal- filter completely suppresses the DC offset (blue is Raw, Red is DSP) Phase offset and slew appears to be a systematic function of (sub) sample rate Random variation ~5ps

Summary of Subsample approach Gives accurate reproduction of filtered real cavity signals from MTA tests Can be implemented using VME instruments closely related to the CAEN TDC’s used for the ToF detectors Need to be able to synchronise timebases with TDC’s- at least fix t=0. t=0 can be defined by an external trigger to zero all timebases This could be done just before accelerating gradient reaches maximum OR Just before start of RF pulse Use a pulse generator to provide 40MHz clock, and provide trigger by logical AND between clock and trigger pulse- should sync start of timebases CAEN V1761 have external clock drive for acquisition rate 10 bit rather than 8 bit units currently recording MTA data Facilitate interfacing with 40MHz clocks of TDC’s (requires programming of the clock controller) Need to understand trigger jitter statement?

TDC approach This is currently planning to use the TDC (CAEN 1290) that are already being used to record the ToF signals RF signal driving discriminators, use TDC time stamps to find cavity ‘zero crossings’ 25 ps bin size Same electronics enhances confidence that any drift in time accuracy will be similar Unfortunately LeCroy discriminators seem problematic at 200MHz Input impedance wanders with frequency, at MHz, 98+j68  Could be matched with L-branch network, but still doesn’t fix rate problem RF signal amplitude and spectrum is very well known: no need for a CFD Threshold trigger system is much less complex Quote obtained from Phillips Scientific for updating and non-updating leading edge discriminators 3ns double event resolution and 300MHz bandwidth, <30ps jitter

Absolute Calibration Providing we can correlate the ToF to the RF with a random variation of <20ps we will not upset the time resolution from the ToF and Trackers However both measurements have a number of unknown systematic delays It is probably possible to figure these out with high fidelity for the RF system- not clear that all the particle detector systematics can be completely known Simple MAUS simulations inject particles at defined entrance time- study effect of entrance time on the change of particle momentum and energy Compare to estimates of the tracker resolution and hence infer potential calibration of phase Simulation set up: Input Momentum: 228MeV/c, RF Gradient 10.2MV/m Input Emittance 6mm, No. of spills: 200 (per injection time)

Axial Energy/Momentum Variation Assume the trackers to have a p z resolution of about+/- 1.4 MeV/c Estimate ~ +/- 135ps uncertainty in absolute phase (+/- 2.7% of the cycle, ~ +/- 10 o ) Emittance reduction flat over this range

Summary 29 Cavities RF cavities provide axial acceleration gradient Anticipated gradient is 10.3 MV/m Cavities tested (short pulse) to 14MV/m at MTA Including in magnetic field- no evidence of relevant sparks RF drive system Completed first High Power RF driver Both valve amplifiers and modulators, tested and installed in MICE hall Upgrades to modulator crowbars planned and in hand RF distribution network Simplification possible for new 2 cavity accelerator scheme Overhead scheme eliminates both physical and schedule interference Enhances accessibility Now require insulation with SF 6 (or similar insulating gas) RF – muon phase determination Sub sample approach appears promising Variation in the precision affected by sample rate- attempting to understand Inexpensive hardware procurement required to test TDC system MICE RF Review, 9th September 2015

RF network: STEP V/VI 30 4 off 6 inch coax lines over wall Pressurised to increase power handling Manually adjustable line trimmers installed at cavity to take up assembly errors in coax length Flexible coax final feeds Allows for small misalignments 10 hybrid splitters Split power for the opposed couplers of each cavity Lines pressurised with 2Bar Nitrogen Amplifiers behind Shield Wall Distribution Network to MICE MICE RF Review, 9th September 2015