Day-Ahead Market Discussion/Clarification TPTF April 24, 2006.

Slides:



Advertisements
Similar presentations
IMPACT TO FREQUENCY CONTROL DURING STARTUP AND SHUT DOWN OF UNITS
Advertisements

CRR Shortfall – Revenue Equalization Part 2 (Continuation from 2/21/08 TPTF discussion) Bill Barnes TPTF 3/5/2008.
March 13, 2013 Day-Ahead Market (DAM) Clearing Process follow-up from February WMS Matt Mereness, ERCOT Manager DAM & CRR.
Concerns with RUC Capacity Short Charge and Energy Trades.
NPRR 336, Authorize ERCOT to Procure Additional RRS During Severe Cold Weather Consideration of Tenaska and Luminant Comments.
ERCOT RMR Deployment and Cost Proposals By: Matt Mereness and Ino Gonzalez.
NPRRs NPRR680 Allow QSEs to Self-Arrange AS Quantities Greater Than Their AS Obligation. This Nodal Protocol Revision Request (NPRR) proposes to allow.
Lead from the front Texas Nodal 1 Texas Nodal Market Management System Requirement Documents November 7, 2006 Sai Moorty MMS Project.
NSRS deployment April John Adams ROS – May 12, 2005.
Load Distribution Factor Calculation Update for Market Applications and studies a Presentation for NATF 11/2/ NATF1Texas Nodal.
Lead from the front Texas Nodal 1 External Web Services Update Nodal Implementation Team Presentation July 7, 2009.
CRR Auction Scope John Moseley. To outline aspects of the CRR market process to assure that these proposed CRR market protocols (as interpreted by ERCOT.
Wholesale Market Subcommittee April 12, 2012 ERCOT Dynamic Ratings Application.
Lead from the front Texas Nodal 1 Texas Nodal Energy Management System Requirement Documents December 5, 2006 Jay Dondeti EMS Project.
1Texas Nodal Nodal Day-Ahead Market Update Special NATF Meeting July 19, 2010.
RPRS ERCOT System Wide Insufficiency Charge Presented at the Technical Advisory Committee June 1, 2006.
NPRR XXX: PRR 307 Inclusion in Nodal…Part II. Questions Raised 06/26/06 Section 3 –COP (resource parameters) –CLR participation limits –Telemetry Requirements.
January 21, 2010 Security Constrained Economic Dispatch Resmi Surendran.
PJM©2013www.pjm.com Economic DR participation in energy market ERCOT April 14, 2014 Pete Langbein.
Nodal Program Update and SEWG Update COPS 1/11/2011 Jim Galvin.
QMWG – Feb. 26, 2014 Discussion topic: NPRR585 Clarification of Administrative Pricing Requirements for Self-Committed Combined Cycle Combustion Turbines.
Nodal Credit Monitoring and Management – Business Requirements ERCOT CREDIT Department October 11, 2006.
CRR Shortfall – Revenue Equalization Part 3 (Continuation from 3/5/08 TPTF discussion) Bill Barnes/Sharon Wang TPTF 3/21/2008.
April 2, 2008 CRR Team Update PCRRs CRR Team UpdateApril 2, 2008 Table of contents 1.What is a PCRR? 2.Which NOIEs are eligible for PCRRs? 3.What.
1 Reliability Deployment Task Force (RDTF Meeting) December 20 th 2011 December 20, 2011.
Market Participant Data Access 1 Market Participant Data Access Jan Stephen Kerr.
Lead from the front Texas Nodal 1 Texas Nodal Startup Eligibility Day-Ahead and RUC Make-Whole Settlements ERCOT Settlements & Billing.
Congestion Management and Ramp Rate for Delivering Ancillary Services Resmi Surendran.
7 August, 2006 TPTF MMS Issues Review Brandon Whittle Lead, Real-Time Market Operations.
DAM Overview: Processes & Tools in the DAM Shams Siddiqi, Ph.D. Crescent Power, Inc. (512) April 2, 2008.
Texas Nodal © Electric Reliability Council of Texas, Inc. All rights reserved. 1 Nodal Verifiable Costs Process WMS Meeting May 15, 2007 Ino.
Commercial Operations Subcommittee Update to TAC September 7, 2012 Harika Basaran, COPS Chair 2012 Jim Lee, COPS Vice Chair 2012.
NPRRs 663NPRR Ancillary Service Insufficiency Actions. This Nodal Protocol Revision Request (NPRR) specifies the actions ERCOT will take to ensure sufficient.
1 Tests for Reasonable LMPs & Price Validation Tool Overview October 27, 2009 NATF.
March 13, 2007 – Slide 1 ERCOT Nodal 101 COPS Market Guide Commercial Operations Market Guide Section 5 a. Overview of ERCOT ERCOT Overview Market Overview.
Scheduling and Operating Transmission Devices in the Nodal Environment.
1 Nodal Stabilization Market Call December 03, :30 PM.
November 27, 2012 NPRR322, Real-Time PTP Option Modeling Implementation Overview.
DAM Self-Commitment Issues & Solutions Shams Siddiqi, Ph.D. (512) March 3, 2008.
DAM Self-Commitment Issues & Solutions, Part 2 Shams Siddiqi, Ph.D. (512) April 21, 2008.
Cutover Update NATF 2 November Today’s Agenda Reminders Program Status 24 Hour LFC Test Update Cutover Update Soft Launch 2 November 2010NATF.
Lead from the front Texas Nodal 1 High-Level Overview of draft NPRR implementing PUCT Rule Posting Requirements January 8,
1 Nodal Stabilization Market Call December 27, 2010.
1/07/2014 QMWG – RUC and AS update QMWG – ERCOT Update ERCOT Market Analysis.
NPRR680 background concept Carrie Bivens Manager, Day-Ahead Market PRS February 12, 2015.
Texas Nodal © Electric Reliability Council of Texas, Inc. All rights reserved. 1 Verifiable Costs for Nodal WMS Meeting.
1 Market Trials DAM/RUC/SASM Weekly Update March 19, 2010.
ERCOT Monthly Operational Overview (January 2015) ERCOT Public February 15, 2015.
Operations Update Kent Saathoff TAC Meeting March 6, 2003.
Real Time Balancing (RTB) & Resource Plan Statuses Change to the QSE practice of showing offline units as online and available ERCOT Presentation to ROS.
1 Nodal Stabilization Market Call December 16, 2010.
Texas Nodal © Electric Reliability Council of Texas, Inc. All rights reserved. 1 Day-Ahead Mini Market Mini Market Walk Through for Day-Ahead.
07/27/2006 Overview of Replacement Reserve Procurement ERCOT Staff PRS RPRS Task Force.
Lead from the front Texas Nodal 1 Texas Nodal Market Management System Update on TPTF Comments on MMS Clarification Notes May 21,
Overview of FIP Issues in the RUC, Verifiable Cost, and other Nodal Market Processes November 12, 2008 VCWG Meeting.
Money Transfer Due to Real-Time Irresolvable Constraint Resmi Surendran ERCOT.
Settlement of Ancillary Service Infeasibility ERCOT QMWG April 15, 2016.
1 February, 2012 QMWG S&B Protocol Clarifications QSE-Requested Decommitment of a DAM Commitment ERCOT Mandy Bauld.
Lead from the front Texas Nodal 1 Texas Nodal EDS4 - Approach 11/28/2007.
Lead from the front Texas Nodal 1 Texas Nodal Energy & Market Management System EMS/MMS Projects Requirement Documents November.
Texas Nodal Program ERCOT Readiness & Transition (ERT) Supplemental Information TPTF January 12, 2009 Kevin Frankeny.
Use of ONTEST Resource Status over Telemetry: – ERCOT protocol permits the use of telemetered Resource Status code “ONTEST” during periods of start-up.
August 11, 2008 TPTF EDS Sequence and Durations Discussion Daryl Cote.
ERCOT Market Education Market Role in Emergency Operations OTS 2016.
CRR Deration and NPRR821 WMS 09/06/2017.
Nodal Program Update to Cops
NPRRs 815NPRR Revise the Limitation of Load Resources Providing Responsive Reserve (RRS) Service.  This Nodal Protocol Revision Request (NPRR) revises.
John Dumas Director, Wholesale Market Operations
Ancillary Service Trades and Ancillary Service Settlement
Load Distribution Factor Calculation for Market Applications and Studies a Presentation for NATF 9/21/ NATF 1 Texas Nodal.
Presentation transcript:

Day-Ahead Market Discussion/Clarification TPTF April 24, 2006

1.DAM delay due to A/S Offer Insufficiency 2.Derating PTP Options declared to be settled in RT 3.Ancillary Service Procurement and Unit Commitment 4.Evaluation of A/S Capacity Insufficiency 5.Load Forecast Distribution Factor ISSUES

Protocol Requirements (4.5.2): 1)ERCOT shall determine if there is an insufficiency in A/S offers before executing the DAM; 2)ERCOT shall declare an A/S insufficiency and issue an Alert; 3)ERCOT shall request additional A/S offers; 4)QSE resubmit offers or submit additional offers; 5)ERCOT must reduce the A/S Plan for DAM purpose if A/S offer insufficiency continues. Issue 1: DAM delay due to insuff. A/S offers

ERCOT Determines A/S Insufficiency ERCOT Declares A/S Insufficiency and Issue Alert QSE Starts to Resubmit A/S Offers ERCOT Reduce A/S Plan for DAM Purpose Execute DAM ERCOT Requests add’l A/S offers 30 min? 10:00? x min? Note: Normally x shouldn’t be more than 10 minutes

Issue 1: DAM delay due to insuff. A/S offers Execute DAM 10:00 Execute DRUC 14:30 ?  Should DRUC be delayed too if DAM (including communicating DAM awards, QSE updating COP, etc) is delayed?  If yes, what’s the new timeline?

Protocol Requirements (4.5.1(8)): The directional network element flows for PTP Options declared for settlement in Real-Time must be properly accounted for in determining available transmission network capacity in the DAM. In the event the available transmission capability in the DAM cannot accommodate all PTP Options declared for settlement in Real-Time, any PTP Option declared for settlement in Real-Time that impacts overloaded directional network elements must be appropriately derated for DAM modeling purposes only, in proportion to that impact. Issue 2: Derate PTP Options

In which market should the amount of PTP options derated be settled? One option is: –settle in DAM those derated MWs with offer price lower than DAM market clearing price –settle in RTM those derated MWs with offer price higher than DAM market clearing price Issue 2: Derate PTP Options

Derating in proportion to impact is easy to do when there is only there is only one network element involved. Derating in proportion to impact cannot be accurately done when more than one network elements are involved. Issue 2: Derate PTP Options

Issue 3: A/S Procurement and Unit Commitment Ancillary Service Offer Criteria (1)Each Ancillary Service Offer must be submitted by a QSE and must include the following information: (a)The selling QSE; (b)The Resource represented by the QSE from which the offer would be supplied; (c)The quantity in MW from that Resource for this specific offer and the specific quantity in MW of any other Ancillary Service offered from this same capacity; (d)The first and last hour of the offer; (e)A fixed quantity block, or variable quantity block indicator for the offer; (f)The expiration time and date of the offer. There is no reference to the Resource’s online/offline status.

Issue 3: A/S Procurement and Unit Commitment Is UC required to clear A/S offers from an offline Resource? Y N w 3-part Offerw/o 3-part Offerw 3-part Offer: ( As the QSE doesn’t know whether its Resource will be committed or not, it will have difficulties to decide whether it’s A/S offer should include startup and min energy costs. ) w/o 3-part Offer Make-Whole? Deduct A/S Revenue from Make-Whole Payment? Y N End A/S offer still considered valid? N End Y Create generic 3-part offer for the Resource Make-Whole? Deduct A/S Revenue from Make-Whole Payment? Y N End 3-part Offer cleared? N No Make- Whole Y Make-Whole; No A/S revenue deduction from Make-Whole payment A/S offer validation: No DRS offers will be allowed; only URS and RRS offers allowed. Self-commitment if A/S offer cleared; No Make- Whole payment

NSRS offers can be cleared with or without unit- commitment If both NSRS offer and 3-part supply offer are cleared, there may be a make-whole payment. If NSRS offer is cleared but not 3-part supply offer, there will be no make-whole payment. For NSRS, the QSE will have difficulties deciding whether it should include Start-Up and Min Energy costs in its NSRS offer. Issue 3: A/S Procurement and Unit Commitment NSRS

Issue 4: Evaluation of A/S Capacity Insufficiency During AP and RT Evaluation and Maintenance of Ancillary Service Capacity Insufficiency (1) ERCOT shall evaluate Ancillary Service requirements and capacity insufficiency using the Ancillary Service Capacity Monitor, described in Section , Ancillary Services Capacity Monitor, throughout the Adjustment Period and Operating Period and may procure Ancillary Service in the Adjustment Period for: (a)Increased need of Ancillary Services capacity above that specified in the Day-Ahead; (b)Replacement of Ancillary Services capacity that is undeliverable due to transmission constraints; or (c)Replacement of Ancillary Services capacity due to failure to provide Ancillary Services Capacity Monitor (1) ERCOT shall calculate the following every 10 seconds and provide Real- Time summaries to ERCOT operators and all Market Participants using the MIS Secure Area and ICCP, giving updates of calculations every 10 seconds, which shows the Real-Time total system amount of…

Issue 4: Evaluation of A/S Capacity Insufficiency During AP and RT A/S Capacity Monitor provides system capacity information based on real-time telemetry, not on COP. COP should be given more weight when ERCOT evaluates A/S sufficiency to open a supplement A/S market for future hours. Should ERCOT also consider other factors such as sudden weather changes and observed binding transmission constraints?

Issue 5: Load Forecast Distribution Factor 4.5.1(5) ERCOT shall determine the appropriate Load distributions to allocate offers, bids, and source and sink of CRRs at a Load Zone across the Electrical Buses that are modeled with Load in that Load Zone. The default distribution is the State Estimator hourly distribution for the seven days before the Operating Day. If ERCOT decides, in its sole discretion, to change this distribution for reasons such as anticipated weather events or holidays, ERCOT shall select a State Estimator distribution from a proxy day reasonably reflecting the anticipated distribution in the Operating Day.

What if there is a planned bus outage? The original distribution factors may allocate offers/bids to that bus anyway. Can ERCOT adjust the distribution factors? Issue 5: Load Forecast Distribution Factor

Dynamic rating Outage schedules Network model Network topology builder Load distribution factor Generic constraints (voltage limit & stability limit) AS requirement RMR offers DAM Clearing RAPs & SPSs DAM QSE: Energy offers/bids, A/S offers, CRR offers declared to settle at RT PTP obligation bids, COPs, etc Network topology & limits AS sufficiency check QSE: AS self-arrangements AS offers QSE AS obligations Notify awards to QSE Post market information Notify AS insufficiency to DRUC CRR Day-ahead Feasibility Test De-rate: CRR options declared to settle in RT DAM Information to settlement Price validation & correction ?

State Estimator runs every five minutes. Should the hourly distribution be the average of the 12 five-minutes or any of those 12 five-minutes? Issue 5: Load Forecast Distribution Factor