BI MD#4 05.11.2011 - BSRT Measurements Beam 1 and 3.5 TeV 2 bunches with different emittances Bumps: -4, -2,0,2,4 mm Results: 3.5TeV.

Slides:



Advertisements
Similar presentations
Commissioning LHC Beam Instrumentation for Nominal Bunch Intensities Beam Commissioning Working Group June 15 th 2010 Rhodri Jones (CERN Beam Instrumentation.
Advertisements

Emittance dilution due to misalignment of quads and cavities of ILC main linac revised K.Kubo For beam energy 250 GeV,
Emittance dilution due to misalignment of quads and cavities of ILC main linac K.Kubo For beam energy 250 GeV, TESLA-type optics for 24MV/m.
ECFA-DESY workshop, NIKEF 1 st April, 2003Nick Walker, DESY Energy Spread Measurement in the TESLA Extraction Line Nick Walker - DESY.
Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
LHC 18 & 19 April 2015 At 450 GeV with bumps, no increased MUFO activity. Beam screen 15R8 warming up to 80 K, ongoing for the day 09:00: Orbit studies.
RF de-bunching problem  The Beam Phase module measures the phase of each individual bunch and makes an average that is passed to the Low Level for updating.
BSRT Optics Design BI Days 24 th November 2011 Aurélie Rabiller BE-BI-PM.
Analysis of ATF EXT/FF Orbit Jitter and extrapolation to IP (Data of ) ATF2 Project Meeting K. Kubo.
Introduction to collimators Integration of BPM Mechanical design Electrical design Processing Simulations Results Conclusions & Outlook.
● 08:30 Loaded by mistake squeeze function to 2 m  Dumped beams ● 10:30-13:00 Test of new algorithm for long. Emittance blow-up to minimize oscillations.
Draft HPS Run Plan March 30, Next Steps Beamline Setup Trigger Commissioning Beam Stability Studies SVT Commissioning Data Taking Checking the.
Energy calibration at LHC J. Wenninger. Motivation In general there is not much interest for accurate knowledge of the momentum in hadron machines. 
ION COMMISSIONING REVISITED 1 Thanks to: John Jowett, Walter Venturini. Matteo Solfaroli.
:00: Prepared new fill B1: Q X =0.293, Q Y =0.269; lifetime = 25h ✔ B2: Q X =0.297, Q Y =0.267; lifetime = 5h ✗ Strong 50Hz and 100hz lines.
1 BROOKHAVEN SCIENCE ASSOCIATES Storage Ring Commissioning Samuel Krinsky-Accelerator Physics Group Leader NSLS-II ASAC Meeting October 14-15, 2010.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Tuesday 17 th April 04:00 Prepare second fill for v/d Meer scans. 06:22 Stable beams, v/d Meer scans for Alice and LHCb. 13:20 End v/d Meer scans.Dump.
Collimator BPM electronics – Results from the lab, SPS and LHC
BSRT CALIBRATION MD SUMMARY LSWG #6-15/09/2015 BSRT TEAM.
MD Wed – Sat DayTimeMD Wed06:00UPS repair, ATS optics checks w/o beam 12:00Cycle, test ATS optics w/o beam 16: TeV: BPM offset determination for.
, Dan Peterson Apparent inconsistencies and other issues in the xBSM measurements of IBS Scans We have studied the pinhole and CodedAperture.
Shortened program (2 days), as decided in LMC. MD program worked very well  all MD’s on plan with ~foreseen beam time. LHC in very good shape with excellent.
ATF2 beam operation status Toshiyuki OKUGI, KEK The 9 th TB&SGC meeting KEK, 3-gokan Seminar Hall 2009/ 12/ 16.
Optics studies for the LHC beam in the TT2-TT10 line and effect of the QKE58 suppression E.Benedetto, A.Franchi Thanks: G.Arduini, D.Jacquet, O.Berrig,
Injection and protection W.Bartmann, C.Bracco, B.Goddard, V.Kain, M.Meddahi, V.Mertens, A.Nord, J.Uythoven, J.Wenninger, OP, BI, CO, ABP, collimation,
CONTENT: Beam characteristics and MP concerns BI configuration Operational settings Collimators Planning Shift breakdown Thanks to: P.Baudrenghien, G.Bellodi,
Progress with Beam Report to LMC, Machine Coordination W10: Mike Lamont – Ralph Assmann Thanks to other machine coordinators, EIC’s, operators,
1Ben ConstanceCTF3 working meeting – 09/01/2012 Known issues Inconsistency between BPMs and BPIs Response of BPIs is non-linear along the pulse Note –
RHIC Status April 8, 2011 RSC Meeting Haixin Huang.
Monday 19 th March 07:33 Lost (another) beam in the squeeze, beyond 2 m, B2 hits 1/3 resonance. 08:30 Start (another) ramp  Try to correct coupling and.
Low-Emittance Tuning at CesrTA Jim Shanks Cornell Laboratory for Accelerator-Based Sciences and Education.
Comparison of simulated collimator BPM data to measured data, obtained during SPS collimator MD (8 June, 2011) A. Nosych Fellow, BE-BI-QP Collimator prototype.
G. Trad on the behalf of the BSRT team Emittance meeting 04/11/2015.
Beam Commissioning Adam Bartnik.
LHC Wire Scanner Calibration
Beam instrumentation MDs
Friday Access in shadow of SPS interventions (RF, extraction septa power supply) Lead into problem on the cooling of the extraction septa in SPS Both beams.
Beam Energy & Intensity: One bunch during full cycle
Cryo Problem MD Planning Tue (1.11.) C B Day Time MD MP Tue 01:00
MKD Waveform Measurements
Emmanuel Tsesmelis TS/LEA 26 January 2007
Saturday 21st April 00:33 Interlock during ramp on BLM HV
MD2490 Measurement of the TMCI threshold at flat-top
Monday h00: Ramp 10 A/s (chromaticity, crossing angle non-closure, beta-beating): At 7m and 3.5m, put in one by one crossing angles, calculated.
Friday 07:00 Power glitch on the EDF network. Point 8 affected.
Fill 1410 revisited Peak luminosity 1.4e32 Beam current 2.68/2.65 e13
Thursday morning – optics correction
Alice solenoid – orbit distortion
Lost at 12:05 to power converter (RTQX2.R1) problem
HyCal Energy Calibration using dedicated Compton runs
Monday February 28th 8h00: Injection
Beam-Based Alignment Results
450 GeV Initial Commissioning with Pilot Beam - Beam Instrumentation
Wednesday 09 March …:09:00: beta* measurement (1.5 m) by K-modulation and with AC-dipole excitation. 1/17/2019 LHC 8:30 meeting.
LHC Closed Orbit For Beam 2
Saturday 7th May Sat – Sun night
Collimation margins and *
Summary Thursday h21: Stable beams fill #1303.
Summary of week 19 Machine Coordinators: G. Arduini, M. Lamont Main aim: Luminosity production.
450 GeV Preliminary Commissioning: Measurement Programme
Wednesday 10:00 test of the un-squeeze to 90 m at 4 TeV.
Thursday 04/11 - Morning Access until ~13:00 Pre-cycle Proton checks:
LHC Position Data The presentation follow-up from:
LHC Morning Meeting - G. Arduini
Fri :52 Stable beams fill #2536
Another Immortal Fill….
Thursday Morning/Afternoon
LHC BIF test setup - update
Monday 152 bunch operation summary
Presentation transcript:

BI MD# BSRT Measurements Beam 1 and 3.5 TeV 2 bunches with different emittances Bumps: -4, -2,0,2,4 mm Results: 3.5TeV Still to test: -influence of camera gain setting on sigma -Calibration 450 GeV

→ 15 minutes MD instead of 1 hour → Beam intensity was ~ 9e9 p → No time for intensity ‘scan’ up to 8e10 Goal was to validate the new system - check sensitivity of the new detector (scan intensity 1.2 to 8e10p) - check timing setup - check delay BI MD# Matching Monitor Test

1 st turn 2 nd turn 10th turn Beam was seen turn/turn with 9e9 p Too close to the limit to use for measurements Better signal with new optics (achromatic lenses – gain to be measured) With Present design, measurements could be done by increasing a bit the intensity Need commissioning time for timing and delay tests BI MD# Matching Monitor Test

BE-BI-QP / E. Calvo, A. Nosych, R. Steinhagen 50  m 13  m 20  m 1. Correction with single-term polynomial: For this BPM (60mm aperture) at 4mm offset the error is around 40  m, however at 7mm the error goes up to 280  m! The non-linearity error rises drastically with the increase of BPM aperture. The single-term polynomials are currently used for orbit correction of LHC. Inner triangle: expected beam position Outer circle: measured+corrected position 2. Correction with cross-term polynomial: it is possible to keep the error level below 5 microns within 50% area around BPM’s geometrical center. The cross-term polynomial can be derived through EM simulation and using various mathematical approaches. mm Button BPM model: two correction methods Errors between expected beam position and corrected positions

BE-BI-QP / E. Calvo, A. Nosych, R. Steinhagen Target: to scan a BPM to estimate the non- linearity error of existing orbit correction Measurement: bump-map 21 points within [-4,4]x[-4,4] mm area (1mm/2mm bumps). BPMWA.A5L4.B1 scan (Nov 5, 2011) Initially we planned to scan the BPMS and with higher offsets, but due to time constraints we could only use BPMWA. However, this should suffice to show the difference and significance of using cross-term polynomials for accurate position correction. 50  m 13  m error 20  m Inner triangle: expected beam position Outer circle: measured+corrected position Verification: the results are compatible with the model, we see similar errors at 4 mm offsets. 45  m error Mapping of BPMS/SW with larger beam offsets is desired for next BI MD.