The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,

Slides:



Advertisements
Similar presentations
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Advertisements

Collimation with retracted TCSGs R. Bruce, R. Kwee, S. Redaelli.
FLUKA studies: channeled ions on LHC IP7 L. Lari (CERN & IFIC (CSIC-UV)) D. Mirarchi (CERN & ICL) A. Lechner (CERN) ColUSM#32 December the 6 th,
Simulation priorities for 2015 R. Bruce for task 5.2.
SixTrack: Minor bug fixes and pencil beam R. Bruce.
LHC Collimation Working Group – 19 December 2011 Modeling and Simulation of Beam Losses during Collimator Alignment (Preliminary Work) G. Valentino With.
Critical beam losses during Commissioning & Initial Operation Guillaume Robert-Demolaize (CERN and Univ. Joseph Fourier, Grenoble) with R. Assmann, S.
1 Analysis of MD on IR1 and IR5 aperture at 3.5 TeV – progress report C. Alabau Pons, R. Assmann, R. Bruce, M. Giovannozzi, G. Müller, S. Redaelli F. Schmidt,
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
GRD - Collimation Simulation with SIXTRACK - MIB WG - October 2005 LHC COLLIMATION SYSTEM STUDIES USING SIXTRACK Ralph Assmann, Stefano Redaelli, Guillaume.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Tertiary Collimators in IP1/IP5 LARP Collaboration Meeting Pheasant Run, St. Charles, IL October 5-6, 2005 Fermilab LARP Collaboration Nikolai Mokhov,
LHC Studies Working Group – 03 July 2012 Beam Scraping and Diffusion + Asynchronous Dump MD G. Valentino, R. W. Assmann, F. Burkart, L. Lari, S. Redaelli,
Beam Background Simulations for HL-LHC at IR1 Regina Kwee-Hinzmann, R.Bruce, A.Lechner, N.V.Shetty, L.S.Esposito, F.Cerutti, G.Bregliozzi, R.Kersevan,
R. Bruce, Today’s meeting ATS optics proposed for use in 2015 (see LBOC, Evian) Several differences compared to nominal optics – Checks needed!
Stefano Redaelli, CERN, BE-ABP on behalf of the LHC Collimation Project and HiLumi WP5 LHC Collimation Status and Plans 2 nd Joint HiLumi LHC-LARP Annual.
Evian 2014 historical perspective run 1: 2010: L peak >10 32 cm -2 s -1  2x10 32 cm -2 s : produce >1 fb -1  delivered.
1 CC & MP - CC10 - CERN Crab LHC J. Wenninger CERN Beams Department for the LHC Machine Protection Panel.
Updates on FLUKA simulations of TCDQ halo loads at IR6 FLUKA team & B. Goddard LHC Collimation Working Group March 5 th, 2007.
Simulations of TCT beam impacts for different scenarios R. Bruce, E. Quaranta, S. RedaelliAcknowledgement: L. Lari, C. Bracco, B. Goddard.
AdColMat: Status of the Working Group and Recent Advancements Working Group on Advanced Materials for Collimators 4 th Meeting - 21/7/2014 A. Dallocchio.
Aperture in case of an asynchronous beam dump with ATS optics R. Bruce, E. Quaranta, S. Redaelli With valueable input from: A. Bertarelli, C. Bracco, F.
Simulation comparisons to BLM data E.Skordis On behalf of the FLUKA team Tracking for Collimation Workshop 30/10/2015 E. Skordis1.
Heat Deposition Pre-Evaluation In the context of the new cryo-collimator and 11-T dipole projects we present a review of the power deposition studies on.
Work in progress: Improved models of collimation margins with TCT damage limit R. Bruce, L. Lari 1 Input and discussions: R. Assmann, A. Bertarelli, C.
HIGHLIGHTS OF LAST MONTHS OF HSS ACTIVITIES AN EXCITING AND HECTIC PERIOD WITH THE LHC BACK IN OPERATION… ABP General Group meeting - HSS1.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
Collimator settings for 2012 R. Bruce, R. Assmann for the collimation team
Β*-dependence on collimation R. Bruce, R.W. Assmann C. Alabau Pons, F. Burkart, M. Cauchi, D. Deboy, M. Giovannozzi, W. Herr, L. Lari, G. Muller, S. Redaelli,
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
NM4SixTrack Implementation of new composite materials for HL-LHC collimator upgrades in SixTrack “Tracking for SixTrack” workshop – CERN, R.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Beam absorbers for Machine Protection at LHC and SPS
Progress with Beam Report to LMC, Machine Coordination W10: Mike Lamont – Ralph Assmann Thanks to other machine coordinators, EIC’s, operators,
Summary Session 5 Chamonix 2011, 24. – Session 5: “High Intensity: Present and Future” R. Assmann & S. Redaelli Thanks to Frank Z. for his notes…
HL-LHC WP14 2 nd meeting: Intercepting devices and failure cases to be studied Anton Lechner, Jan Uythoven.
Field Quality Specifications for Triplet Quadrupoles of the LHC Lattice v.3.01 Option 4444 and Collimation Study Yunhai Cai Y. Jiao, Y. Nosochkov, M-H.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
LHC Collimation Working Group Monday, 21 March 2016 Analysis of collimator BPMs in the 2015 run A.Valloni, G. Valentino with input from R. Bruce, A. Mereghetti,
How low can we go? Getting below β*=3.5m R. Bruce, R.W. Assmann Acknowledgment: T. Baer, W. Bartmann, C. Bracco, S. Fartoukh, M. Giovannozzi, B. Goddard,W.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Tracking simulations – where we are and what needs to be done R. Bruce on behalf of task 5.2.
Aperture measurements during LHC commissioning 2017
On behalf of the CERN Collimation Team and FLUKA team…
C. Bracco, R. Bruce, B. Goddard, C. Wiesner, A. Lechner, M. Frankl
TCT BLM response from tertiary halo at 6.5 TeV
Tracking simulations of protons quench test
Task 2. 5: Beam-beam studies D. Banfi, J. Barranco, T. Pieloni, A
Surviving an Asynchronous Beam Dump?
HL-LHC Aperture Update
On behalf of the CERN Collimation Team and FLUKA team…
Potential failure scenarios that can lead to very fast orbit changes and machine protection requirements for HL-LHC operation Daniel Wollmann with input.
Simulations of collimation losses at RHIC
TI8/WIC Incident & UJ87/UA87 Radiation Levels & Analysis
FCC hh dump kicker - switch topologies and impact on beam
Update on multi-turn particle debris tracking
Β*-reach in 2017 R. Bruce, S. Redaelli, R. De Maria, M. Giovannozzi, A. Mereghetti, D. Mirarchi Acknowledgement: collimation and optics teams, BE/ABP,
Federico Carra – EN-MME
Energy deposition studies in IR7 for HL-LHC
Tuesday TOTEM and transverse loss map (1) OK
The 4th International Particle Accelerator Conference, IPAC13
Beam halo and beam losses in IR1 and IR5
Collimation after LS1: cleaning and β* reach
BI cont. *** Summary Matching Monitor test *** We only had ~15minutes of inject and dump, but managed to see a profile with ~9e9 p (!)
Collimation margins and *
C. Adorisio Extracted from the presentation given at
FLUKA Energy deposition simulations for quench tests
Presentation transcript:

The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme, Grant Agreement Update on failure cases for asynch dump on collimators – worst case vs realistic L. Lari IFIC (CSIC-UV) & CERN R. Bruce, S. Redaelli Thanks to C. Bracco and B. Goddard 85th LHC Machine Protection Panel Meeting 85th LHC Machine Protection Panel Meeting

Outline Introduction/Scope of the work. Introduction/Scope of the work. Summary of the past results. Summary of the past results. Worst case for Post LS1 optics and HLLHCv1.0 optics. Worst case for Post LS1 optics and HLLHCv1.0 optics. Towards more realistic cases. Towards more realistic cases. Conclusions. Conclusions.

Introduction / Scope of the work …is to understand the beam loads in different collimators in case of asynchronous beam dump, in order to improve the LHC collimation system design by understanding realistic loss cases. Not looking at that from the beam dump point of view, but from the whole LHC collimation system point of view!

How? Using a modified SixTrack collimation routine to allow studies of asynchronous dump with the whole collimation system in place, including the study of different errors. Using a modified SixTrack collimation routine to allow studies of asynchronous dump with the whole collimation system in place, including the study of different errors. Input from the MKD pulse form each MKD and in case of single module pre-firing  considering the retriggering delay of ( *n) [ns] where n is the number of generators away from the one which pre-triggered. Input from the MKD pulse form each MKD and in case of single module pre-firing  considering the retriggering delay of ( *n) [ns] where n is the number of generators away from the one which pre-triggered. ~3  s extraction kicker rise time kick for a single MKD magnet MKD pulse form - Courtesy B. Goddard

Few reminders: worst cases for the 15 MKDs firing simultaneously limit only for the W collimators IP6 IP7 IP5 Beam2 HLLHCv1.0 IP1 IP7 IP6 limit only for the W collimators Beam1 Post LS1 On TCTH.4R5 4e+11 p+ (results 2.2e+11) 83th LHC Machine Protection Panel Meeting 83th LHC Machine Protection Panel Meeting Both loss maps refers to a very pessimistic scenario in which: 1.Retraction of IP6 2.+ Retraction of for “critical” collimators 3.+ of 1  closer to the beam 4.Optics error (R. Bruce)  Results refer to the worst case out of 1000 optics configuration with random errors Both loss maps refers to a very pessimistic scenario in which: 1.Retraction of IP6 2.+ Retraction of for “critical” collimators 3.+ of 1  closer to the beam 4.Optics error (R. Bruce)  Results refer to the worst case out of 1000 optics configuration with random errors On TCTH.4L1 1.5e+11 p+ (results 1.15e+11) Physics run with 0.15 m  * in IP1/IP5 Physics run with 0.60 m  * in IP1/IP5 Nom. setting

Few reminders: Collimation setting considered TCP.IP765.7 TCSG.IP777.7 TCLA.IP *80cm W TCP.IP315 TCSG.IP318 TCLA.IP320 TCT.IP1/IP TCT.IP2/IP830 TCL.IP1/IP5 (2 Cu +1 W)15 TCLI/TDI.IP2Tot opened TCDQ.IP689 TCSG.IP  retraction For Beam1 and Beam2 Nom. setting = Tungsten

In the next slides…. …will be presented a comparison between worst scenarios in terms of loads on delicate collimators for the cases in which: all the MKDs all the MKDs MKD fire (single module pre-firing + re- triggering) MKD fire (single module pre-firing + re- triggering)

Nom. setting [REF: A. Bertarelli et al. Updated robustness limits for collimator material, LHC Machine Protection Workshop, Annecy, France] Onset of plastic damage on Tungsten collimators : 5x10 9 p+ limit only for the W collimators IP6 IP7 Beam 1 – Post LS1 optics Limit for fragment ejection: 2x10 10 p+ Results are normalized to 1.x15 11 p+ (25 ns) IP1 Nom. setting TCDQs Note that the peak on IP1 TCT is factor ~2.9 higher with 1 MKD firing than with all 15 MKDs A6 O6 IP1 IP7 IP6 limit only for the W collimators On TCTH.4L1 1.5e+11 p+ Beam 1 On TCTH.4L1 4.3e+11 p+

limit only for the W collimators Nom. setting [REF: A. Bertarelli et al. Updated robustness limits for collimator material, LHC Machine Protection Workshop, Annecy, France] Onset of plastic damage on Tungsten collimators : 5x10 9 p+ IP6 IP7 limit only for the W collimators IP6 IP7 Beam 2 - HLLHCv1.0 optics Limit for fragment ejection: 2x10 10 p+ Results are normalized to 2.2x10 11 p+ (25 ns) Beam 2 IP5 On TCTH.4R5 4e+11 p+ On TCTH.4R5 1.5e+12 p+ Nom. setting TCDQs Note that the peak on IP5 TCT is factor ~3.5 higher with 1 MKD firing than with all 15 MKDs A6 O6

limit only for the W collimators Nom. setting IP6 IP7 limit only for the W collimators IP6 IP7 Beam 2 - HLLHCv1.0 optics Results are normalized to 2.2x10 11 p+ (25 ns) Beam 2 IP5 On TCTH.4R5 1e+12 p+ On TCTH.4R5 1.5e+12 p+ Nom. setting Note that the peak on IP5 TCT is factor ~1.5 higher with the 1 MKD firing closer to the TCDQs than with the 1 MKD firing at the O6 position. TCDQs MKDs A6 O6

More realistic imperfections Preliminary analysis of probabilities for orbit drifts Preliminary analysis of probabilities for orbit drifts Considering 2012 BPM data at TCTs and in IR6, joint with the 5% RMS beta-beat converted to mm, to estimate cumulative distribution function of total drifts. Considering 2012 BPM data at TCTs and in IR6, joint with the 5% RMS beta-beat converted to mm, to estimate cumulative distribution function of total drifts. Results : Results : Probability of 1 sigma drift at TCT combined with 1.2mm in IR6 is below numerical error of model (~1e-3) Probability of 1 sigma drift at TCT combined with 1.2mm in IR6 is below numerical error of model (~1e-3) Probability of 0.2mm drift at TCT and 0.9mm in IR6 has approximately 1% probability. Study this case for more realistic errors. Probability of 0.2mm drift at TCT and 0.9mm in IR6 has approximately 1% probability. Study this case for more realistic errors. R. Bruce

limit only for the W collimators Nom. setting IP6 IP7 limit only for the W collimators IP6 IP7 Beam 1 – Post LS1 optics Results are normalized to 1.15x10 11 p+ (25 ns) IP1 TCDQs MKDs A6 O6 Beam 1 Nom. setting On TCTH.4L1 9.4e+9 p+ On TCTH.4L1 3e+10 p+ Note that the peak on IP1 TCT is factor ~1.5 higher with the 1 MKD firing closer to the TCDQs than with the 1 MKD firing at the O6 position.

limit only for the W collimators IP6 IP7 Beam 2 - HLLHCv1.0 optics Results are normalized to 2.2x10 11 p+ (25 ns) IP5 On TCTH.4R5 4.5e+9 p+ Preliminary results using a 2  retraction collimation setting show that we are closer to the limit for W collimators (5e+9 p+). TCDQs MKDs A6 O6 2  retraction

Conclusions A preliminary comparison between worst scenarios in terms of loads on delicate collimators for the cases in which all the 15 MKDs or 1 MKD fire (single module pre- firing + re-triggering) not synchronously with the abort gap, were presented. A preliminary comparison between worst scenarios in terms of loads on delicate collimators for the cases in which all the 15 MKDs or 1 MKD fire (single module pre- firing + re-triggering) not synchronously with the abort gap, were presented. A factor ~3 higher with the with 1 MKD firing than with all 15 MKDs was found. A factor ~3 higher with the with 1 MKD firing than with all 15 MKDs was found. In terms of protection from an asynchronous dump accident, the 2  retraction collimation settings (baseline for the startup, if no impedance problem) is more tolerant for the Post LS1 and HLLHCv1.0 optics. In terms of protection from an asynchronous dump accident, the 2  retraction collimation settings (baseline for the startup, if no impedance problem) is more tolerant for the Post LS1 and HLLHCv1.0 optics. The tools developed for this studies are applied to the recent HL-LHC optics, working in collaboration with the HSS optics team with the scope of supporting and improving the development of HL-LHC optics. The tools developed for this studies are applied to the recent HL-LHC optics, working in collaboration with the HSS optics team with the scope of supporting and improving the development of HL-LHC optics. Realistic error scenarios chosen are based on BPM 2012 data analysis made by R. Bruce, that will be presented in the detail in a future collimation related meeting. Realistic error scenarios chosen are based on BPM 2012 data analysis made by R. Bruce, that will be presented in the detail in a future collimation related meeting. For the realistic errors scenarios studies for both optics (i.e. HLLHCv1.0 and Post LS1), the SixTrack outputs are available for future FLUKA and structural analysis study on actual W (Beam2) IP1 (Beam1). For the realistic errors scenarios studies for both optics (i.e. HLLHCv1.0 and Post LS1), the SixTrack outputs are available for future FLUKA and structural analysis study on actual W (Beam2) IP1 (Beam1).

Phase advance 7TeV nominal  55 cmSLHC_3.1b  15 cmHL-LHC v1.0  15 cm Beam1 TCTH.4L1.B TCTH.4L2.B TCTH.4L5.B TCTH.4L8.B Beam2 TCTH.4R1.B TCTH.4R2.B TCTH.4R5.B TCTH.4R8.B Calculated from the MKD.4O6 (the furthest away form TCDQs) [See also R.Bruce et al. Collimation requirements for the IR1/5 layout and on-going WP5 studies, 8 th HL-LHC Extended Steering Committee meeting, 13/08/2013, CERN] Improved! Post LS1 optics

Possible mitigation actions to be evaluated & some future possible steps New collimation materials for TCT jaws with higher limit damage. New collimation materials for TCT jaws with higher limit damage. MDs for Beam2 to benchmark simulation results in IP5. MDs for Beam2 to benchmark simulation results in IP5. BPM buttons used to improve control on orbit. BPM buttons used to improve control on orbit. Tighter collimation position limit. Tighter collimation position limit. Improve the phase in IP5 for the HLLHCv1.0 optics. Improve the phase in IP5 for the HLLHCv1.0 optics. Include as first the BPM buttons in the critical collimation locations. Include as first the BPM buttons in the critical collimation locations.