CONTENT: Beam characteristics and MP concerns BI configuration Operational settings Collimators Planning Shift breakdown Thanks to: P.Baudrenghien, G.Bellodi,

Slides:



Advertisements
Similar presentations
Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
Advertisements

Sat/Sun 26/27 th March Sat 18h20: Stable beams. Fill #1653. Sun 10h02: Stable beams continued. vdM scans. Length calibrations. 16h59: Beam dump. Delivered.
Wednesday 12 th September Pumping, removal of vacuum equipment from tunnel in the morning TOTEM & ALFA, RP movement tests: OK 11:50 pre-cycle started,
MD#2 News & Plan Tue – Wed (19. – 20.6.) DayTimeMDEiCMP Tue06: GeV  4 TeV: Ramp for chromaticity - missed A 08:00Ramp down 10: GeV: Large.
Lot’s of time lost due to cryo problem in IR8. Major impact, therefore review of MD program… Start discussion here, please let us know your input. Will.
The ATS MD part III (Achromatic Telescopic Squeezing scheme) Participants: Any (active) volunteers Goal: 1)MD1 (S. Fartoukh & R. Assmann  10h): “Pre-squeeze’’
* IP5 IP1 IP2 IP8 vertical crossing angle at IP8 R. Bruce, W. Herr, B. Holzer Acknowledgement: S. Fartoukh, M. Giovannozzi, S. Redaelli, J. Wenninger.
LHC progress with beam & plans. Of note since last time Transverse damper Beta beating in the ramp Collimation set-up at 450 GeV & validation LBDS – systematic.
02/09/2010 Access conditions for test of the RB.A23 at 17:30. Splice mapping. Complete machine closed by ~18:00.Problems in getting TI2 ready for injection.
● 08:30 Loaded by mistake squeeze function to 2 m  Dumped beams ● 10:30-13:00 Test of new algorithm for long. Emittance blow-up to minimize oscillations.
07-JUL-2003LEADE / JW1 Satellite bunches in the LHC Satellite “definition” Satellite luminosity Satellite detection & tolerances J. Wenninger AB/OP.
CONTENT: Beam characteristics and parameters Filling schemes Operational settings OP procedure and COLL setting Planning Shift breakdown To define the.
ION COMMISSIONING REVISITED 1 Thanks to: John Jowett, Walter Venturini. Matteo Solfaroli.
:00: Prepared new fill B1: Q X =0.293, Q Y =0.269; lifetime = 25h ✔ B2: Q X =0.297, Q Y =0.267; lifetime = 5h ✗ Strong 50Hz and 100hz lines.
Monday h00: End of fill #1640: 3.7 pb h14: RB S12 and S23 tripped before loading rampdown table, active filter. MPE piquet. Fip_Com_Lost.
LHC progress Report LHCC Wednesday 23 rd March 2011.
R. Assmann - LHCCWG Two Beam Operation R.W. Aßmann LHCCWG Acknowledgements to W. Herr, V. Previtali, A. Butterworth, P. Baudrenghien, J. Uythoven,
Tuesday 17 th April 04:00 Prepare second fill for v/d Meer scans. 06:22 Stable beams, v/d Meer scans for Alice and LHCb. 13:20 End v/d Meer scans.Dump.
MD Wed – Sat DayTimeMD Wed06:00UPS repair, ATS optics checks w/o beam 12:00Cycle, test ATS optics w/o beam 16: TeV: BPM offset determination for.
1 Commissioning and Operation of the machine protection system L. Ponce Acknowledgements: M. Zerlauth, J. Wenninger, D. Wollmann, V. Chetvertkova, G. Valentino,
06:00 – Ongoing injection problems on beam 2  07:42 – Start of injection investigations  11:11 – Injection problem fixed. Resteering of transfer line.
Saturday 11.9 ● From Friday – Minimum required crossing angle is 100  rad in 2010 – Plenty of aperture at triplets: > 13  (n1 > 10) – Can stay with 170.
Cryo back at 17:30 Beam back at 19:00 IR2 aperture until ~03:00 Since then no beam from the SPS:  Connector problem on MKD  Connector eroded, needs to.
Progress with Beam Report to LMC, Machine Coordination W10: Mike Lamont – Ralph Assmann Thanks to other machine coordinators, EIC’s, operators,
Thursday 27 th October 00:57 fill 2257 dumped during squeeze (RQTF.A67B1) 03:52 stable beams fill #2258 4:33 Dumped, problem of LBDS dilution kicker power.
28/01/2013LHC 8:30 meeting Summary of Week 4 pPb physics Machine Coordination: Mike Lamont & Jan Uythoven Ion coordination: John Jowett.
Tue 23/8 – Wed 24/8 09:00 Start 90 m optics run – Preparation and verification of the collimation functions – Re-generation of functions for Transverse.
Ion Commissioning: Thursday & Friday
Ralph Assmann, Giulia Papotti, Frank Zimmermann 25 August 2011
Wednesday 8.9 External crossing angles:
LHC Commissioning with Beam
Wednesday :06 Dump fill 3533: interlock BPMS in IP6
-9:00: Test IP transverse adjustment (CMS) and optics verification.
Saturday 21st April 00:33 Interlock during ramp on BLM HV
Friday 07:00 Power glitch on the EDF network. Point 8 affected.
Week 46 Week 46: Machine coordinators: Roger Bailey – Gianluigi Arduini Main aims of the week: Stable beams with ions Scheduled stop for ion source refill.
Fill 1410 revisited Peak luminosity 1.4e32 Beam current 2.68/2.65 e13
Tue :25 Beams dumped due to RF vacuum interlock
LHC Morning Meeting - G. Arduini
Tuesday TOTEM and transverse loss map (1) OK
Tuesday 23/11/10 8:00 Physics fill #1511 dumped
Thursday 17th May 01:11 Fill #2633 dump in squeeze arc circulator load channel Ad1B 03:16 Fill #2644 Stable beams, lumi 5.2e33 cm-2s-1 04:38 Dumped by.
LHCCWG Meeting R. Alemany, M. Lamont, S. Page
Week 35 – Technical Stop and Restart
MD#4 Progress MD Coordinators: Giulia Papotti, Frank Zimmermann
Friday morning 10:30 Optics measurements and corrections.
Wire almost entirely through beam before BLM triggers dump
450 GeV Initial Commissioning with Pilot Beam - Beam Instrumentation
Overall commissioning strategy for protons (estd. 2005)
LHC Beam Operations Past, Present and Future
BI cont. *** Summary Matching Monitor test *** We only had ~15minutes of inject and dump, but managed to see a profile with ~9e9 p (!)
Saturday 7th May Sat – Sun night
Summary Thursday h21: Stable beams fill #1303.
Aims for the week Recover from technical stop and precycle at 10A/s
MD#2 News & Plan Tue – Wed (19. – 20.6.)
Thursday 04/11 - Morning Access until ~13:00 Pre-cycle Proton checks:
Monday 8th December Morning used for RF work (IP z, injection), damper noise checks. Stable beams period with LHCb spectrometer OFF – lost beam after.
Monday morning 09:40 Dump fill 2838, integrated ~130 pb-1.
Summary for LPC (March 7th, Ralph Assmann)
Saturday :42 stable beams fill 3541
Monday :15 fill 3523 dumped by BPMs IP6
LHC Morning Meeting - G. Arduini
Summary Tuesday h23: Machine closed. Precycle started.
Wednesday 23/2 Thanks CRYO!!!.
Wednesday h18: 228b fill lost just before start of ramp.
Another Immortal Fill….
Beam commissioning plans, 2007 and 2008
HI2011 Commissioning Status
Monday 152 bunch operation summary
Saturday 29th October Friday during IP2 1 m squeeze test
Presentation transcript:

CONTENT: Beam characteristics and MP concerns BI configuration Operational settings Collimators Planning Shift breakdown Thanks to: P.Baudrenghien, G.Bellodi, B.Goddard, J.J.Gras, D.Jacquet, J.Jowett, M.Lamont, S.Redaelli, F.Roncarolo, M.Sapinsky, R.Steinhagen

Beam Characteristics 12/10/ LHC BBCWGW.Venturini - M.Solfaroli2 Bunch intensity = 7x10 7 ions (5.74 x10 9 charges/bunch) Squeezed to 3.5m Transverse normalized emittance ~1.5/0.8 μm (nominal/used, for the same beam size as for protons) First setup with 2 bunches/beam (still safe and collisions in all IPs Nominal filling scheme (128b) for luminosity production being finalized (see J.Jowett’s slides) Energy of the nominal beam (128b) ~400kJ Possibility of quench in the DSs negligible with this intensity SBF reduction factor still to be decided. Proposal for 2 or 2.5 as it’s the maximum we can do while keeping safe beam measurable (2b beam still

12/10/ LHC BBCWGW.Venturini - M.Solfaroli3 Beam Instrumentation SYSTEMRESPONSIBLECOMMENT Wire ScannerDehning – Sapinsky Safe beam for wire damage ~2.2e13 p and ~9.4e9 ions (including safety factor). Last estimation for p 2.8e13 No quench at 3.5 TeV with 1e13 p. BLMDehningNo change is foreseen on threshold BPMJones – LefevreNo problem – to be used on High sensitivity BCT – FBCTLudwigOK BSRABoccardi It should be OK IF the requested MD time for commissioning/check is allocated BGIDehning – SapinskyTo be commissioned during the MD BSRTRoncarolo Differences in light spectrum and intensity: 3.5TeV: no problem 450GeV: ~1/100 signal intensity w.r.t. protons pilot (close to limit of camera sensitivity). Some possible improvement of the setup could give enough signal Q – Q’Steinhagen * Q depends only on 'frev' which supplied via the BST timing system. * Q' depends only on the Q measurement and the dp/p modulation amplitude. ‘dp/p -> df’ differences are small but can be re-programmed online if necessary. * FBs operate based on the momentum, distributed by the slow timing system.

12/10/ LHC BBCWGW.Venturini - M.Solfaroli4 Settings management Ramp and Squeeze functions are ready in a dedicated Hypercycle (EARLY-IONS_3.5TeV) Most settings identical to protons but: RF (  functions are ready) Xing angles in collisions Collimation To minimize the changes, Xing settings maintained as for p throughout INJECTION, RAMP and SQUEEZE: Xing angle to be set at: 0 μrad for IP1 and IP μrad (external angle) for IP2. As ALICE wants to flip the spectrometer polarity during the run the external angle will be later set at +140 μrad Same Xing angle as for protons and parallel separation for IP8 (no collision required)

12/10/ LHC BBCWGW.Venturini - M.Solfaroli5 Collimation system (I) If possible, no changes to IP7 and IP3 settings all over the cycle –Cross calibration of orbit reading with protons: Inject high intensity p bunch (LOW BPM sensitivity) Correct against reference orbit Inject low intensity p bunch and record orbit (HIGH BPM sensitivity) Inject an Ions bunch and check that orbit is the same Define it as Ions reference orbit –Test ramp with safe Ions beam (2b), collimators at injection settings and OFB on to establish reference orbit up to high energy –During squeeze use same orbit reference as for protons and measure the optics

12/10/ LHC BBCWGW.Venturini - M.Solfaroli6 Collimation system (II) Subsequent ramp with the same collimator settings as for p till the end of the squeeze, then: Keep IP8 separation and Xing angle Change Xing angles as required in IP1, IP2 and IP5 Set-up of TCTs around new collision orbit –As a result only one collimator set-up to be done at top energy Loss maps: –done in 5 configuration for p –Suggested a minimum of 3 (~4 fills) for Injection End of squeeze Collisions SHADOWING OF ZDC…OPEN PROBLEM – to MPP

12/10/ LHC BBCWGW.Venturini - M.Solfaroli7 Planning >

12/10/ LHC BBCWGW.Venturini - M.Solfaroli8 Shift Breakdown from start to first collisions J.Jowet Bunches Total Time [days] both rings Comments I0Re-commission protons11 Following technical stop, establish orbit with low-intensity BPM settings. I1Injection and first turn1(0.25)Magnetically identical to protons; 1 bunch/beam. I2Circulating beam10.25 Magnetically identical to protons. Synchronisation of transfer lines and RF capture at -5 kHz frequency shift. Check lifetime in particular. I3 450 Z GeV initial commissioning Cross-calibration of BPMs from protons. Beam instrumentation setup. Wire-scanner, BGI. I4 450 Z GeV optics checks with two beams 2(0.5) Magnetically identical to protons but do minimal check of energy matching, beta-beating. >0.4 nominal bunch intensity I5450 Z GeV - two beams20.5Otherwise magnetically identical to protons I6Collimation20.5Set-up single stage collimation, loss map to compare with protons. I7Ramp10.5 Start with two beams, Magnetically identical to protons. Check beam dump at various energies. I83.5 Z TeV flat top checks10.5Performed following successful ramp. Collimation setup and loss map. I9 Setup for collisions Z TeV 10.5 Squeeze and transition to zero real crossing angle in ALICE, CMS & ATLAS. LHCb separated, squeezed. Collimation setup. I10Loss maps10.5 Measure to verify hierarchy appropriate for ion beams. test predictions. Verify protection. Stable beam1(0.1)See machine backgrounds ?

12/10/ LHC BBCWGW.Venturini - M.Solfaroli9 Shift Breakdown from start to first collisions J.Jowet Bunches Total Time [days] both rings Comments TOTAL to prepare 5+(1) I11 First collisions+physics 21.5Ramp with two beams, squeeze, checks I12Increase intensity1281Increase bunch number to 128 (Early++ Scheme). Physics128 Parasitic measurements during physics (luminosity evolution, BFPP, etc,...) to test our models and prepare future runs.

12/10/ LHC BBCWGW.Venturini - M.Solfaroli10 Open questions Transverse emittance: as low as possible? 0.8 μm? ADT off? Longitudinal emittance: start without blow-up (in case of need it should be ready (Philippe B.)) Re-steering of transfer lines? LBDS - special tests? Loss maps configuration to be decided Shadowing of ZDC…OPEN PROBLEM – to MPP LHCb dipole and compensator off?