Costs by Category Purchasing hardware Purchasing software Purchasing computerized delivery system Adding bar codes to holdings Moving costs Changes to physical plant Miscellaneous supplies
Final Project Budget $400,000 over budget $100,000 over budget for Purchasing hardwarePurchasing hardware Purchasing softwarePurchasing software Purchasing delivery systemPurchasing delivery system
Final Project Schedule Two months over schedule
Key Strengths Estimated staff time requirements accurately Student workers handled bar coding efficiently
Lessons Learned Withhold money if supplier misses delivery deadlines Make supplier responsible for integrating hardware and software Hold Computer Services Department to same deadlines as off-site supplier Make moving contract bidders show equivalent experience
Benefits Holdings searches take 30% less time to complete Books spend 33% less time on the reshelf carts Research librarians spend 25% less time with each client Average student spends 15% less time searching for materials