2 Presentation outline  Pender County water utility history  Why schedule was critical  Key time-saving decisions  Pre-project  Preliminary engineering  Design  Summary  Progress update

3 Pender County Water Utility History

4 Water and Sewer Districts PENDER COUNTY Rocky Point/Topsail Scotts Hill Maple Hill Central Pender Moore’s Creek Columbia-Union

5 System capabilities, growth and financing  General Obligation (GO) bonds  November 7, 2006  $72 M for MCWSD and CPWSD  7 years for GO bond sale (November 7, 2013)  One 3-year extension approved (November 7, 2016)  Pender County water supply capabilities  Original system  System growth  Water treatment plant

6

7 The Challenge Maximize service capabilities under the original referendum Define project Identify financing source Execute before referendum expires

8 The Challenge Define the project

9 Basis for referendum (master plan)  Moore’s Creek WSD  1,027,000 LF of pipe up to 42-in diameter  1 elevated tank  1 booster pump station  $45 M  Central Pender WSD  600,000 LF of pipe up to 16- inch diameter  2 elevated tanks  $27 M  Total: 308 miles of pipe, 3 tanks, and 1 booster station

10 Determine what is feasible  Identify system for 20-year needs  Consider projected customer density  Consider anticipated customer interest  Determine hydraulic requirements  238 miles of mains; 1 elevated tank  Identify Phase I system for affordable rates  Existing customer density and interest  Size lines to fit 20-year system  75.5 miles of mains; 1 elevated tank

11 The Challenge Identify financing source

12  Reviewed available sources  Decided to pursue USDA funding  $18.9 M  $11.3 M (loan)  $7.4 M (grant – 40%)  $160 k (local)

13 The Challenge Beat the referendum deadline

14 Primary project milestones Begin PER November 2013 Design Complete April 2015 Bidding August 2015 Bond Sale October 2016  PER, EA for USDA  Design, permitting and construction  75.5 miles of mains up to 16-in diameter  0.5 MG elevated storage tank

15 Key Time-Saving Decisions

16 Pre-project selection  Consultant teaming  Identified critical project success factors  Established preliminary schedule and critical path  Began coordination with potential funding agencies  Positioned client to choose USDA at project outset  Allowed coordination in earnest immediately after selection

17 Preliminary engineering  Aerial survey  Drawing scale and style determined at this stage  Master schedule  Public outreach and incentivized pricing for customer recruitment  Identified built-out system for planning period  Backed into the Phase I project based on anticipated customers  Conducted hydraulic modeling to ensure proper function of Phase I and built-out systems

18 Design  Master schedule  Multiple design teams  Project implementation manual  Weekly production team coordination meetings  Weekly owner PM updates/coordination  Accelerated design development of certain components  State Property Office (2 crossings of NE Cape Fear River)  NCDOT (I-40 Crossing)  Early communication with reviewers  Minimized required easements  Continued proactive communication with USDA

19 Summary  PCU is committed to providing potable water to citizens wherever feasible  Sometimes project timelines are legitimately compressed  Project planning must be sound at early stages to ensure success  The plan is only as good as the team carrying it out  Owner  Consultants  Funding agency  Regulatory agencies

20 Progress update  USDA funding committed  Project bidding schedule  Project construction schedule

21 Time is money. Use yours wisely. Bryan McCabe, PE PCU J. Ray Cox, PE HIGHFILL DISCUSSION