PRAC Project Phase II: Sour Service Evaluation of ISO TR 10400 FAD Equation API Production Research Advisory Committee Pete Moore – API PRAC Chairman Anand.

Similar presentations


Presentation on theme: "PRAC Project Phase II: Sour Service Evaluation of ISO TR 10400 FAD Equation API Production Research Advisory Committee Pete Moore – API PRAC Chairman Anand."— Presentation transcript:

1 PRAC Project Phase II: Sour Service Evaluation of ISO TR 10400 FAD Equation API Production Research Advisory Committee Pete Moore – API PRAC Chairman Anand Venkatesh, Peter Ellis – Program Managers Jan 23, 2012 Final Report Technical Session I – 3:45pm

2 Mini-Pipe Testing (4) Tensile NACE A DCB & HRC CTOD Characterization Testing Full Size Pipe (1) ALL TESTING IS COMPLETE FEA Report Complete Committee Report complete ALL TESTING IS COMPLETE FEA Report Complete Committee Report complete

3 API PRAC PROJECT 2006-102475 Final Report (123 pages) API PRAC PROJECT 2006-102475 Final Report (123 pages)

4 API PRAC PROJECT 2006-102475 Final Report (123 pages) API PRAC PROJECT 2006-102475 Final Report (123 pages) http://mycommittees.api.org/standards/ecs/sc5/Technical%20Papers/Forms/AllItems.aspx Will be posted soon to the API Website Will be posted soon to the API Website

5 PRAC Project Phase III: Sour Service Evaluation of ISO TR 10400 FAD Equation API Production Research Advisory Committee Pete Moore – API PRAC Chairman Anand Venkatesh – Program Manager January 23, 2012

6 PRAC III C110 Test Pipe Were Donated and Shipped to Honeywell by Tenaris Detailed Mill Test Report Documenting the Pipe Characterization Attributes

7 7 PRAC III – Phase 3 Details Testing Details:  NACE Standard TM0177 Method A – Tensile tests complete  NACE Standard TM0177 Method D – DCB tests complete  Mini/Tiny-Pipe SSC Tests – Machining Complete – EDM Notch cutting to start in February – Testing to begin late April  Full Scale Tests with Man-made OD Surface Imperfections ID/OD and OD only or ID only H 2 S Exposure – Pressurized ID environment and OD exposure with replenishment/purging of 7% H2S in solution held in annular volume between plastic sleeve and OD of sample. – Testing to begin late 2012

8 Machining of Tiny Pipe Complete EDM Notching to start in February EDM OD Notch ~ 4 inches

9 Testing of Full Size Pipe late 2012


Download ppt "PRAC Project Phase II: Sour Service Evaluation of ISO TR 10400 FAD Equation API Production Research Advisory Committee Pete Moore – API PRAC Chairman Anand."