Presentation is loading. Please wait.

Presentation is loading. Please wait.

R. A. Barlow, LIU-PSB review, 20 Nov 20151. BI.DIS Pulse generators controls R.A.Barlow, LIU-PSB review, 20 Nov 2015 2.

Similar presentations


Presentation on theme: "R. A. Barlow, LIU-PSB review, 20 Nov 20151. BI.DIS Pulse generators controls R.A.Barlow, LIU-PSB review, 20 Nov 2015 2."— Presentation transcript:

1 R. A. Barlow, LIU-PSB review, 20 Nov 20151

2 BI.DIS Pulse generators controls R.A.Barlow, LIU-PSB review, 20 Nov 2015 2

3 Contents -BI.DIS System description -Layout -Controls (Prototype) -Power supply -Fast interlocks -Documentation -Status and planning -Spending profiles -Conclusions 3

4 BI.DIS system function R. A. Barlow, LIU-PSB review, 20 Nov 20154 ParameterUnitValue Kick flat-top durationµsDIS0: 20 DIS1: 170 DIS2: 320 DIS3: 470 DIS4: 620 ~ 150µs The 160 MeV beam from the Linac4 transfer line will be distributed to the four levels of the PSB by a sequence of a vertical bending magnet (BI.DVT30), a system of five pulsed kicker magnets, the so called proton distributor (BI.DIS), a vertical bending magnet (BI.DVT40), three septum magnets (BI.SMV) and another three vertical bending magnets (BI.BVT). The Head and Tail dump both receive the beginning and end of the proton beam provided by Linac4 whilst the portions of beams injected into each PSB ring are respectively proportional to the length of each PFN pulse the create the adequate orbit deflection into the PSB. BI.DIS magnets 5 of

5 System and pulse generator description R. A. Barlow, LIU-PSB review, 20 Nov 20155  5 Pulse Forming Networks 6.25 Ω (one per magnet) + 1 spare  PFN voltage up to 10 kV ( ~ 6.25 kV nominal with H - operation)  IGBT switch (2 × 6.5 kV device in series)  fixed duration (different for each PFN, max 620 µs)  short-circuited magnet  recuperation of a large fraction ( > 50 %) of the PFN stored energy (1270 J) ≤2µs

6 BI.DIS controls principles R. A. Barlow, LIU-PSB review, 20 Nov 20156

7 BI.DIS prototype controls R. A. Barlow, LIU-PSB review, 20 Nov 20157 PLC TECHNOLOGY CHOICE  Siemens PLC processors, series 1500  SCADA, TIA portal  New generation of SCADA screen  EDS and AUL controller, with Siemens Safety technology  Slow control finite state machine management Finite State Machine

8 Pulse power prototype JURA6 – B867 R. A. Barlow, LIU-PSB review, 20 Nov 2015 8  FSU job TEABTECFSU-1379 for PFN and cablingTEABTECFSU-1379  HV dividers testing (PCB version, DC and AC response)  Problems with feedthrough connector, MULTI-CONTACT PFN housing Series IGBT’s mounted onto cassette system PFN patch panel for controls interconnects

9 BI.DIS prototype controls – Power Supply R. A. Barlow, LIU-PSB review, 20 Nov 2015 9 Specifications: Output Voltage, 10kV Charging Current, 1A Average Power, 5kJ/s Peak Power, 10kW Quantity, 8 of Special feature, Analogue interface & Profibus Visit to the firm, Paris, 12 th May 2015, mid-term engineering review and visit on 22 th October 2015 for HV reception with tests. Pre-series HV testing at TECHNIX LOC/REM analogue, Profibus funct. tests O/C test, (15.min) S/C test, max. power, (1.hour) R load test, 10K, max power Thermal analysis inside PS C load, 77uf, (spec. 65uf) Reproducibility, < ±0.1%, is < ±0.01% Voltage ripple, < ±0.05 % p-p Long term stability test and T coefficient done PS is certified !

10 BI.DIS controls FSC R. A. Barlow, LIU-PSB review, 20 Nov 2015 10  Functionalities studies completed  Deliverables understood  Flow diagram/VHDL (Objective early 2016)  Choice of definitive H/W scheme to be decided?  New type of FMC carrier to be developed, No VME bus ElementInterlock Magnet No Imag MagnetS/C MagnetWrong Pulse Length IGBTVbal not correct IGBTNo Iout IGBTDrivers missing 15V IGBTDriver status not correct IGBTFaulty_Shot Freewheel diodeI_diode_F missing Dump diodeI_diode_D missing

11 BI.DIS controls racks description R. A. Barlow, LIU-PSB review, 20 Nov 2015 11 BI.DIS generators location in B361 (BCER) PFN racks Control racks Dummy load rack  5 generator racks + spare  1 electrical distribution  1 racks for signal acquisitions/timing  1 rack for SCADA, BIS and OASIS  3 PFN racks (2 PFN per rack)  1 dummy load rack  DIC for final installation (Dec 2015)

12 BI.DIS system controls documentation R. A. Barlow, LIU-PSB review, 20 Nov 201512  Technical Specification for 10kV, 1 A Capacitor Charging Power Supplies for the PS Booster Distributor Kicker System, DO-28787/TE/ABT  Functional Specification, BI.DIS, CONTROLS, EDMS-1266475  Engineering Specification, BI.DIS CONTROLS, EDMS-1520605 (On-going)  Functional Specification BI.DIS FAST INTERLOCKS, EDMS-1537992 (Engineering spec on-going)  ‘Beam Interlock specification for Booster BI.DIS’ with Linac4 in draft…

13 Present status and planning until end 2015 STATUS TODAY  One full PFN built in B.867  One generator rack controls implemented  Lab. test on a prototype PFN halted till all cabling finished.  Tests with full pulse length (620 µs) and nominal required current (1000 A) performed but to be repeated for thermal aspects. (with new power supply) NEXT STEPS  After FSU cabling, system to be restarted (with Fug power supply, 12kV, 800mA.  Check thermal performance  Integrate new power supply then on-going IGBT/PFN testing R. A.Barlow, LIU-PSB review, 20 Nov 201513

14 Present Status and Planning until end 2016 R. A. Barlow, LIU-PSB review, 20 Nov 201514

15 BI.DIS spending profile, electronics and control R. A. Barlow, LIU-PSB review, 20 Nov 201515

16 Conclusion The new BI.DIS generators is now close to enter in their production phase in parallel with the completion of the design and prototype phase. Big production effort starting 2016. The aim is to have hardware ready by end 2016 Technical aspects still to be checked on full size PFN:  Thermal behaviour  Rise time Full working prototype in 867 by end 2015 and the goal of having the full system ready for installation end of 2016 should “almost” be met providing the manpower is made available. R. A. Barlow, LIU-PSB review, 10 September 201416

17 THANK YOU FOR YOUR ATTENTION! R. A. Barlow, LIU-PSB review, 20 Nov 201517


Download ppt "R. A. Barlow, LIU-PSB review, 20 Nov 20151. BI.DIS Pulse generators controls R.A.Barlow, LIU-PSB review, 20 Nov 2015 2."

Similar presentations


Ads by Google