How to Build Test Inventory Test inventory is built and updated as the software project moves from phase to phase –Start with Requirements List the actual.

Similar presentations


Presentation on theme: "How to Build Test Inventory Test inventory is built and updated as the software project moves from phase to phase –Start with Requirements List the actual."— Presentation transcript:

1 How to Build Test Inventory Test inventory is built and updated as the software project moves from phase to phase –Start with Requirements List the actual and “budgeted” requirements Analyze which of these requirements are “testable” – “reviewable” –For each of the “testable” requirement, consider if there are more than one item that is testable. (e.g. data, flow, systems, performance, etc.) For each of the testable requirements –Describe the test flow or scenario –Describe each of the testable items –describe the expected results for each testable item

2 An Initial Test List-Inventory Example Req. # Req. Description Test flow/ scenario Testable items Expected Result for Each testable item #3 Query must Complete in 1 to 2 secs Populate the Employee Data base and query On all Employees younger than 25 and are managers 1.Create 100 employee Entries in DB with one 24 yrs manager 2. Set up a query and record response time and answer DB table with Employee data Response time Less than 2 Seconds with one entry

3 Prioritize the Test Scenarios Just as not all requirements have the same priority, not all test scenarios have the same priority - - - prioritize the test scenarios by risks –Cost of failure –Users’ usage pattern –Chance of error from past experience (e.g. error prone areas, error prone development team, new areas, etc.) add a column to the Test List-Inventory

4 An Initial Test List-Inventory Example Req. # Req. Description Test flow/ scenario Testable items Expected Result for Each testable item #3 Query must Complete in 1 to 2 secs Populate the Employee Data base and query On all Employees younger than 25 and are managers 1.Create 100 employee Entries in DB with one 24 yrs manager 2. Set up a query and record response time and answer DB table with Employee data Response time Less than 2 Seconds with one entry Prio- rity Med.

5 Add More Test Information The example can not be tested without real code and the data base system. So it is closer to component or system test. –Add a column stating the test type: Req. review/inspection Design review/inspection Unit test Functional test Component test System test

6 Add More Details to Test List-Inventory Required Test environment –System and system interfaces –UI –Data formats (date, numeric, alphanumeric, etc.) –Other factors: performance, reliability, security, etc. ( any equipment/tool needed) If more information is needed to build and/or complete the test inventory, conduct “interviews” much like requirements gathering

7 Two Levels of Interviews for Test Info. High Level ( appr. 15 minutes ) to get general information - - - include managers Detailed Level (appr. 30 min – 1 hr.) to get more explanation. Read page 167( Hutcheson) – “Expendable Tester Ploy”--- a touch of realism

8 Goals of High Level Test Interviews Identify: –Project deliverables (which need to be tested?) –Owners of deliverables (where to get them?) –Project dependencies (sources of potential flaws?) Other project Shared DB/network/tools Passing data or control with another on-going project Get “opinions” on constraints and preferences: –Priorities of requirements and other project items –Schedule constraints –View on testing versus development versus support –Any specific goal behind this project Beat competition in the market Improve customer satisfaction Cut support cost Etc.

9 Goals of Detail Test Interviews Update business flow/logic flow Gain insight into views on testing and project –Definition and views on quality –Past test information How long? How much? # of people and level of experiences What were tested and what were usually left out –Test tools used and needed –Test process and fix process used

10 Some Guidance on Test Interviews Be prepared with questions Be quick and professional on the questions/answers Listen carefully --- especially for “volunteered” information Review the answers with the participants to confirm the answers Do not offer solutions when there are discrepancies among the answers - - - ask for clarifications

11 Update your Test Inventory Priority Dependencies and integration needs Tools needed Order of testing Systems interfaces Etc.

12 Product Integration and Build for Test Functional Test –module dependencies –Other subsystem dependencies (DB or Network) Component Test –Functional dependencies System Test –Component dependencies


Download ppt "How to Build Test Inventory Test inventory is built and updated as the software project moves from phase to phase –Start with Requirements List the actual."