1 Run II PMG 1/19/06 Pushpa Bhat 1 Run II Upgrades Status January 2006 Pushpa Bhat

2 Run II PMG 1/19/06 Pushpa Bhat 2 Outline Technical Progress Project Status Status Report for December ‘05

3 Run II PMG 1/19/06 Pushpa Bhat 3 Technical Progress AP2, DB studies  Dave’s talk Li Lens  One each of PT-1 and PT-2 lenses will be filled and the PT-2 will be tested on the test stand. PT-2 should be ready for beam in June. Rapid Transfers  Many elements of the upgrade are in place (ramping power supplies, BPMs) providing benefits to operations in various modes  Transfers without reverse proton tune-up tried many times last week with good results

4 Run II PMG 1/19/06 Pushpa Bhat 4 Technical Progress (contd.) 2.5 MHz pbar acceleration in MI  Results from 2 pbar study periods promising: 86- 93% eff while tuning,  ~ 30% Shows 100% efficiency and ~10% emittance growth in proton studies for relevant intensities and emittance May save 15% pbars now being lost in MI during acceleration and coalescing –current scheme acc+ coalescing eff. ~85%,   80% better beam quality, hence expect lower losses in Tev and gain in luminosity due to smaller long. Emittance Overall expect >20% gain in peak luminosity Contention on how to proceed. There was a recent review held by McGinnis/Kourbanis. McGinnis report: Potential for 5-10% in  L.dt now We should try a few shots before shutdown  Far less risky and far less complicated than trying to recover and recycle pbars!  Compare with many projects in pbar source each <10% gain

5 Run II PMG 1/19/06 Pushpa Bhat 5 MI BPM upgrade  Most of the hardware designed, ordered or delivered  First test system almost ready; will be installed in MI40 next week, replacing the old system  Full upgrade during and immediately after shutdown BLM upgrades  Prototype system running at MI60 for ~ 3 months, with PC instead of local control card. Control card + software under test  Production to be completed by 4/15, a month of testing followed by installation Technical Progress (Contd.)

6 Run II PMG 1/19/06 Pushpa Bhat 6 IPM, OTR detectors  One each installed in the Tevatron during the Dec. shutdown. Now fixing some problems. Might have some data after the current shutdown Tevatron Electron Lens  Good progress  TEL-1 upgraded with new SEFT e-gun  TEL-2 essentially ready for installation Tev ES separators  Install in SD’06, 2 new separators and swap 3 existing separators (these were sparking at higher voltages when larger collision helix were tried last Fall.) Technical Progress (Contd.)

7 Run II PMG 1/19/06 Pushpa Bhat 7 Project Highlights: Projects 100% complete  1. Luminosity Upgrades  1.1 Protons on Target 1.1.1 Slip Stacking 1.1.2.1, 1.1.2.2 pbar Target & Beam Sweeping (initial) 1.1.3.1 MI dampers 1.1.4 Booster Cogging 1.1.5 Optical Transition Radiation Detectors 1.1.6 Operational Improvements to Slip Stacking  1.2 Antiproton Acceptance 1.2.1.1 Modifications to existing lens 1.2.1.3 General Lens R&D 1.2.1.4 New Lens (prototype-1) operational (Milestone) 1.2.2.3.1.1, 1.2.2.3.2.2 AP2 & Debuncher BPM Upgrade 1.2.2.10 Initial AP2/Debuncher Aperture Improvements Complete (Milestone)  1.3 Antiproton Stacking & Cooling 1.3.1 Stacking & Cooling Integration Task Force 1.3.2 Debuncher Cooling 1.3.3.2 Stacktail Betatron Cooling 1.3.4 Recycler Stacking & Cooling 1.3.5 Electron Cooling R&D, Installation & Commissioning  1.4 Tevatron High Luminosity 1.4.3.1.1, 1.4.3.1.2, 1.4.3.1.3, 1.4.3.1.9 Design and implement new helix with existing and new installed separators in the Tevatron 1.4.3.2 Polarity switches for separators 1.4.5 Improved Control Diagnostics: BPM system upgrade, IPM, Tune tracker, abort gap monitor, 1.7 GHz Schottky, Dampers, Head-tail Monitor  2. Maintenance & Reliability Upgrades  2.1 2003 White Paper & Vulnerability Report 2.1.1 LINAC 7835 Amplifier Tubes 2.1.2 Orbit Bump Magnets 2.1.3, 2.1.4, 2.1.5 Booster RF 2.1.6, 2.1.7 MI: PS transformers, Kicker vacuum tubes 2.1.8, 2.1.9 Tevatron low beta power supply, centrifugal cold compressors 2.1.13 Harmonic Filter Damping Resistors  2.2 Maintenance Improvements 2.2.2 Booster Collimator 2.2.3 Tevatron Abort Improvements (Initial) 2.2.5 General Alignment

8 Run II PMG 1/19/06 Pushpa Bhat 8 Possible Additions Chromatic Compensation in the Tev Lattice  The mom. spread combined with chromatic error in the optics lead to poorer beam lifetimes. Correct the chromatic errors by implementing new circuits using existing sextupole magnets  Benefits: Improves beam lifetime leading to 5-10%  L.dt gain Allows Tev to be operated at a new working point near ½ integer resonance. This in turn allows more intense proton bunches to be used in Tev stores. Can lead to another 10% gain in  L.dt  A review was held in Dec., 2005  Three versions of the hardware implementation and cost estimates presented with cost estimates of $620K (v1) (whole ring), $220K (v2) and $107K (v3). Since v3 seems to provide optimal benefit and the most cost effective, we would like to pursue v3.

9 Run II PMG 1/19/06 Pushpa Bhat 9 Possible Gains (Peak Luminosity) Pbar stack rate + aperture up by another 30% ? 2.5 MHz pbar acceleration  10-20% More protons 230E9 ppb  20% Chromatic Compensation  10%

10 Run II PMG 1/19/06 Pushpa Bhat 10 Near term Reviews/Decisions (Contd.) Beam-beam effects in Tev  Jan. 26, ’06 Tev alignment SD’06 work  Feb. ’06 Pbar aperture SD’06 work  Aperture: band-4 cooling tank arrays + DB extraction kicker magnet (+ DB extraction kicker motorized stand)  <7% gain expected; Lot of effort, Risky? Review late February 2.1 Reliability Upgrades  Infrastructure: 345-KV switchgear spares for KRS, MMS

11 Run II PMG 1/19/06 Pushpa Bhat 11 December ’05 Status

12 Run II PMG 1/19/06 Pushpa Bhat 12 Milestones Baseline Finish Date Actual Finish Date Forecast Date 100% complete?

13 Run II PMG 1/19/06 Pushpa Bhat 13 Progress as of December 31, 2005 % Complete

14 Run II PMG 1/19/06 Pushpa Bhat 14 M&S Spending through Dec. ‘05

15 Run II PMG 1/19/06 Pushpa Bhat 15 Effort for December 2005

16 Run II PMG 1/19/06 Pushpa Bhat 16 Project Highlights Project Status  V4 of the plan issued in December  Changes documented  Project 82% complete as of Jan. 1, 2006 Costs:  M&S estimate now (v4) = $18,607K  Jan ’05 status (DOE review) : $17,587K  $15.2 M spent; ~$3.45M to complete; Contingency: $550K ($1,791 K taken away in the past year)