1 Criminal Justice System SITA briefing to the Portfolio Committee of the Police by Dr Setumo Mohapi 10 June 2015.

Similar presentations


Presentation on theme: "1 Criminal Justice System SITA briefing to the Portfolio Committee of the Police by Dr Setumo Mohapi 10 June 2015."— Presentation transcript:

1 1 Criminal Justice System SITA briefing to the Portfolio Committee of the Police by Dr Setumo Mohapi 10 June 2015

2 2 1.Modernisation of the Criminal Justice System a)Identity and Access Management( IDAM) b)National Photo Image System(NPIS) c)Property Control and Exhibit Management (PCEM) 2.Facial Compilation 3.Criminal Record Identification Management System (CRIM) 4.Investigate Case and Docket Management System (ICDMS) 5.Docket Scanning Solution (ECM) 6.Automated Vehicle Tracking System (AVL) 7.National Network upgrade Program (NNUP) 8.Network Video Conferencing (VC) 9.Integrated Justice System (IJS) 10.DNA ACT (Criminal Law amendment Act 37 of 2013) a)Labware b)Forensic Science Laboratory Admin System (FSL Admin) c)DNA Solution architecture CONTENT

3 3 PROJECTSSITA’S ROLESTATUSTIMEOUTSTANDING Identity and Access Management (IDAM) SITA ISS initiated a Business Impact Analysis (BIA) to confirm scope of bid. Draft document sent to SAPS for review and comment. Presentation and summary discussion were conducted between SITA & SAPS on the 4 th June 2015. May 2015 - 2016 Business Impact Analysis assessment completed by SITA ISS. The existing bid is complex and the BIA will assist in clarifying the scope. Background: SAPS signed an Information Security SLA with SITA in 2014-2015 and the security assessment forms part of the service delivery. At present SAPS have no IDAM solution. SAPS have compiled a bid specification and expected to go out on tender for a solution in the 1st quarter this year. SAPS requested that SITA advise on the IDAM bid and then further participation in the proposed bid with the expectation for SITA to manage, configure and support the IDAM solution upon procurement and implementation. IDENTITY & ACCESS MANAGEMENT (IDAM)

4 4 PROJECTSsSITA’S ROLESTATUSTIMEOUTSTANDING National Photo Identification system (NPIS) SITA’s role is to maintain and enhance the NPIS within maintenance service delivery. Development of the ICAO NPIS interface. SITA completed the redevelopment of the legacy NPIS to cater for current technology to enable the interfacing required with the integrated into Documentum. After delivery of ICAO software it will take one month for developing the integration and testing. Completion of the integration between NPIS and ICAO is currently dependant on provision of ICAO software to SITA. SAPS Procurement of Muvoni’s (ICAO) software program could only be done in the new financial year and is still in process. Background: SITA performs all the Maintenance and Enhancement activities related to the National Photo Image System and Identity System. This support all the digital photos received from the SAPS. The hardware (webcams) have been acquired by the SAPS and are in the process of being deployed. NATIONAL PHOTO IMAGE SYSTEM (NPIS)

5 5 PROJECTSSITA’S ROLESTATUSTIMEOUTSTANDING Property Control and Exhibit Management (PCEM) SITA delivered a proposal to the SAPS for the maintenance / rewrite of the PCEM 1.X. SAPS submitted the current PCEM solution to the CSIR to do an investigation on the total solution and provide a way forward to SAPS. SAPS deliverable.Currently the SAPS do not have a maintenance contract in place for the solution in production. Background: The PCEM contract was signed between SAPS and an external service provider. This contract expired. At present there are 2 systems available for the management of property items and exhibits known as PCEM Version 1.1 and PCEM 1.x. The PCEM Version 1.1 was developed to manage the Forensic Science Laboratories (FSL) and is presently deployed at 4 Main SAPS Forensic Science Laboratories. The PCEM Version 1.x was developed to manage the SAPS 13 Stores needs for Visible Policing (Vispol) and at present has not been deployed. PROPERTY CONTROL & EXHIBIT MANAGEMENT

6 6 PROJECTSSITA’S ROLESTATUSTIMEOUTSTANDING Facial CompilationSITA’s role is to support the SAPS in the procurement process Technical evaluation finalized and currently at price evaluation stage. Proposed adjudication date - 17 June 2015. N/A Background: SITA assists the SAPS in the Facial compilation tender specification through the procurement process. FACIAL COMPILATION

7 7 PROJECTSSITA’S ROLESTATUSTIMEOUTSTANDING Criminal Record and Information Management System (CRIM) Maintenance and enhancement of the system and the development of interfaces. Assist SAPS in the procurement of AFIS. DNA ACT: Development for manual capturing and reports to display buccal numbers completed. Si-Bus development of between CRIM and ICDMS completed. AFIS: On the procurement of AFIS, SITA SCM must be notified by the 5 June 2015 if all specification issues are clarified. The AFIS publication is planned for 12 June 2015 The tender contained inconsistent evaluation criteria and a letter in this regard has been issued to SAPS. The evaluation criteria is fundamental to the evaluation of any bid. Background: SITA has maintained the CRIM system for the past 15 years. It is one of the SAPS legacy systems for supporting the Criminal Record Centre and the system interfaces with the Automated Fingerprint Identification System(AFIS) CRIMINAL RECORD & INFORMATION MANAGEMENT SYSTEM

8 8 PROJECTSSITA’S ROLESTATUSTIMEOUTSTANDING ICDMS - Administer Case (Phase 1) Development of a criminal case registration process based on Service Orientated Architecture (SOA) approach. *SITA development has been completed. ICDMS has been deployed to 665 Police Stations *Investigate performance issues with the ICDMS solution Development was completed by 31 March 2015 *Investigation will run until the 30 th June 2015 100% delivery *The performance (slow system) of the ICDMS solution is not meeting the expectations of our SAPS clients. Background: In November 2009 SITA received an order for the development of the ICDMS Administer Case that will deliver an end to end business process, application, ICT and Integrations required to manage and administer criminal cases, inquests and enquiries from the time an incident is reported until the case is archived. The project consists of two phases: The first phase -Administer Case which has been completed; and The second phase - Investigate Case for which SITA delivered a Project Charter to SAPS INVESTIGATE CASE DOCKET MANAGEMENT SYSTEM

9 9 PROJECTSSITA’S ROLESTATUSTIMEOUTSTANDING Docket scanning solution SITA maintain, integrate and enhance the Documentum ECM for SAPS. This includes the support of the scanning of documents into Documentum. Decentralisation of JuDISS Rustenburg LCRC completed. Vereeniging LCRC completed. Polokwane servers completed. Deployment to Polokwane in progress. Sites to be deployed over the next two months: Eastern Cape – Mount Road LCRC Western Cape – Cape Town Central LCRC Kwa-Zulu Natal – Durban Central LCRC The replacement of the Scanman by the Captiva was tested in the SAPS Technology centre of excellence laboratory (TCOE lab) and the national deployment challenge was resolved. Background: The purpose of the Document Scanning Solution system is to store records in the Electronic Content Document Management System (ECDMS). Image capturing and processing – EMC Document repository – Documentum DOCKET SCANNING SOLUTION

10 10 PROJECTSSITA’S ROLESTATUSTIMEOUTSTANDING AVLProcurementThis was recommended for cancellation on the 23 January 2015 as none of the Bid responses met the minimum threshold of 80% as per the requirements. Awaiting SAPS feedback on way forward to re- publish tender SAPS to advise on re-advertisement of the previously cancelled bid. Background: Tracking devices are installed into the SAPS vehicles to track and trace the vehicle movement. This is done by a 3 rd party supplier through an agreement between SAPS and the supplier. This contract expired and SAPS requested SITA to publish a tender for support of AVL. AUTOMATED VEHICLE LOCATION SERVICE (AVL)

11 11 PROJECTSSITA’S ROLESTATUSTIMEOUTSTANDING Upgrade of WAN and LAN network infrastructure at all SAPS sites *Management and implementing Program. *The establishment of procurement contracts for Cabling and Equipment. * SAPS decided to do direct tasking via SITA contracts to suppliers, as from January 2015. *A total of 1,498 SAPS sites were upgraded, countrywide June 2015*SITA tenders (1221 Equipment and 1189 Cabling) evaluated and await Board final award. Background: The objective of the program focuses on the upgrading of the SAPS absolute Technology Infrastructure. This includes renewal of data and voice cabling, network equipment, consolidation of servers, data carriers and voice over IP NATIONAL NETWORK UPDRADE PROGRAMME

12 12 PROJECTSSITA’S ROLESTATUSTIMEOUTSTANDING Establishment of VC Contracts for (i) maintenance of current equipment and (ii) Contract for procurement of additional equipment SITA SCM to establish SAPS (i) Contracts for Maintenance & Support and (ii) Contract for Procurement of additional equipment. *Maintenance & Support Contract established *Procurement Contract in Process of evaluation * Contract with Dimension Data effective since 1 March 2015 for maintenance & support. Tender for the procurement of additional equipment - evaluation commenced from 25 May 2015. Adjudication scheduled 15 July Background: SAPS directly, prior to 2010, acquired VC equipment through SITA Transversal Contract 431 which did not include maintenance and support. SAPS therefore requires maintenance on existing equipment and a procurement contract to replace and expand NETWORKS VIDEO CONFERENCE (VC)

13 13 PROJECTSSITA’S ROLESTATUSTIMEOUTSTANDING IJS SITA Transversal Developme nt Capability Development and maintenance of integration endpoints and interfaces between systems and departments. Completed: SAPS Decision Docket Ready, NPA Decision Docket Outcome Notification and Integration, First Enrolment and Court Appearance Notification, Postponement Notification, Plea and Verdict Notification Accused Update Case Transfer & Case Merge Notification Total of 20 high level integrations completed between systems and numerous in 2014-2015 All development is on track. N/A Background: SITA develop the integration endpoints and interfaces as per the specifications compiled and approved by the IJS transversal team. A team has been established in SITA to focus on integrations required across systems and departments. IJS SITA TRANSVERSAL DEVELOPMENT CAPABILITY

14 14 PROJECTSSITA’S ROLESTATUSTIMEOUTSTANDING NFDDSITA team has completed the development on the consolidated DNA database as part of STRlab solution with the associated indices to accommodate all the DNA profiles on a national basis. NFDD Functional Design Specification has been completed and in process of final signatures. NFDD Technical Design Specification 95% completed. Development of the NFDD modules will commence once the TDS is signed off with the consolidated DNA database as an interim solution. SAPS await the final internal instruction on the implementation of CODIS. Background: SITA appointed a team to assist the SAPS in the implementation of the NFDD (CODIS) solution. The team has started the preparation of the environment from where the system will operate. NATIONAL FORENSIC DNA DATABASE (NFDD)

15 15 PROJECTSSITA’S ROLESTATUSTIMEOUTSTANDING LABWAREThe skill transfer from the service provider to SITA over the course of the project to ensure that SITA can maintain and support the software going forward. 5 SITAzens were trained on LABWARE to work with the SAPS service provider in the configuration of the software. Managed by SAPSSAPS to manage the delivery of the Service provider. Background: A software solution procured by SAPS directly, which manages workflow of all specimen in the forensic LAB LABWARE

16 16 PROJECTSSITA’S ROLESTATUSTIMEOUTSTANDING Forensic Science Laboratory Administrative System (FSL Admin) In relation to the DNA Act SITA is responsible for the maintenance and enhancement of FSL Admin. Integration development between FSL Admin and STRLab system were completed. Integration development between CAS / ICDMS and FSL Admin were completed. Deliverables completed on time. N/A ArchitectureSITA is responsible for the DNA Solution Architecture Solution Architecture completed and GAP analysis completed mapped to the ACT and associated regulations. SITA await final signoff. Deliverables completed on time. Background: Administration system behind the forensic science laboratory FORENSIC SCIENCE LABORATORY ADMIN SYSTEM

17 17 Thank You