Presentation is loading. Please wait.

Presentation is loading. Please wait.

INOVA Fairfax Hospital South Patient Tower Falls Church, VA Senior Thesis 2012 Mike Morder Mechanical Option Advisor: Dr. William Bahnfleth.

Similar presentations


Presentation on theme: "INOVA Fairfax Hospital South Patient Tower Falls Church, VA Senior Thesis 2012 Mike Morder Mechanical Option Advisor: Dr. William Bahnfleth."— Presentation transcript:

1 INOVA Fairfax Hospital South Patient Tower Falls Church, VA Senior Thesis 2012 Mike Morder Mechanical Option Advisor: Dr. William Bahnfleth

2 INOVA South Patient Tower Introduction Depth 1: Central Chilled Water Plant Depth 2: Dedicated Heat Recovery Chiller Depth 3: Condensate Recovery Breadth 1: Two-Way Slab Reinforcing Breadth 2: Electrical Conclusion Acknowledgements Questions

3 INOVA South Patient Tower Introduction South Patient Tower Mechanical System Design Objective Depth 1: Central Chilled Water Plant Depth 2: Dedicated Heat Recovery Chiller Depth 3: Condensate Recovery Breadth 1: Two-Way Slab Reinforcing Breadth 2: Electrical Conclusion Acknowledgements Questions Building Introduction Addition to Existing Patient Bed Tower Located in Falls Church, VA 236,000 SF Overall Cost: $76 Million Completion Expected in June 2012 Site Map

4 INOVA South Patient Tower Introduction South Patient Tower Mechanical System Design Objective Depth 1: Central Chilled Water Plant Depth 2: Dedicated Heat Recovery Chiller Depth 3: Condensate Recovery Breadth 1: Two-Way Slab Reinforcing Breadth 2: Electrical Conclusion Acknowledgements Questions Project Team Architectural Aspects Owner: INOVA Health System Architect: Wilmot/Sanz, Inc. General Contractor: Turner Construction Structural Engineer: Cagley & Associates MEP Engineer: RMF Engineering, Inc. Civil Engineer: Dewberry & Davis Designed to Respect Existing Tower Natural Daylight Essential for Patient Rooms Focal Point – Atrium with Fountain at Entrance Pursuing LEED Silver

5 INOVA South Patient Tower Introduction South Patient Tower Mechanical System Design Objective Depth 1: Central Chilled Water Plant Depth 2: Dedicated Heat Recovery Chiller Depth 3: Condensate Recovery Breadth 1: Two-Way Slab Reinforcing Breadth 2: Electrical Conclusion Acknowledgements Questions Structural System Electrical System Typical 29’ x 29’ Bays Reinforced Normal Weight Concrete Two-Way Slab with Drop Panels Two 2000 kVA Transformers 600 A Bus Ducts Provide Service Throughout Building 2000 kW Emergency Generator

6 INOVA South Patient Tower Introduction South Patient Tower Mechanical System Design Objective Depth 1: Central Chilled Water Plant Depth 2: Dedicated Heat Recovery Chiller Depth 3: Condensate Recovery Breadth 1: Two-Way Slab Reinforcing Breadth 2: Electrical Conclusion Acknowledgements Questions Existing Mechanical System Connected to Existing Campus Central Plant Steam System- Domestic Hot Water Heating Heat Exchangers Provide HHW Chilled Water System- Supplies Cooling to AHUs No Booster Pumps in Building Four (4) 20,000 CFM AHU Majority of Bed Tower 10,000 CFM and 13,000 CFM AHU Supply Cafeteria and Kitchen Hoods Baseboard Radiators (Hot Water) Constant Air Volume Terminal Units Reheat Provided on Exterior Rooms

7 INOVA South Patient Tower Introduction South Patient Tower Mechanical System Design Objective Depth 1: Central Chilled Water Plant Depth 2: Dedicated Heat Recovery Chiller Depth 3: Condensate Recovery Breadth 1: Two-Way Slab Reinforcing Breadth 2: Electrical Conclusion Acknowledgements Questions Design Objective Chilled Water Plant Optimization Study Chiller Design/ Layout Centrifugal vs. Absorption Primary Secondary vs. Variable Primary Flow Dedicated Heat Recovery Chiller Air-Handler Condensate Recovery System Best Selections = Most Economical Most Energy Reduction Lowest Emissions

8 INOVA South Patient Tower Introduction Depth 1: Central Chilled Water Plant Design Alternatives First Costs / Energy Life-Cycle Cost Depth 2: Dedicated Heat Recovery Chiller Depth 3: Condensate Recovery Breadth 1: Two-Way Slab Reinforcing Breadth 2: Electrical Conclusion Acknowledgements Questions Introduction Location: 5 th Floor Mechanical Space Alternative 1: Purchased CHW and Steam Alternative 2: Centrifugal (Primary/Secondary) Alternative 3: Centrifugal (VPF) Alternative 4: Absorption (Primary/Secondary) Alternative 5: Absorption (VPF)

9 INOVA South Patient Tower Introduction Depth 1: Central Chilled Water Plant Design Alternatives First Costs / Energy Life-Cycle Cost Depth 2: Dedicated Heat Recovery Chiller Depth 3: Condensate Recovery Breadth 1: Two-Way Slab Reinforcing Breadth 2: Electrical Conclusion Acknowledgements Questions Alternative 3: Centrifugal (VPF) Centrifugal Chiller COP: 1.72 2280 GPM

10 INOVA South Patient Tower Introduction Depth 1: Central Chilled Water Plant Design Alternatives First Costs / Energy Life-Cycle Cost Depth 2: Dedicated Heat Recovery Chiller Depth 3: Condensate Recovery Breadth 1: Two-Way Slab Reinforcing Breadth 2: Electrical Conclusion Acknowledgements Questions Alternative 5: Absorption (VPF) Absorption Chiller COP: 1.12 3420 GPM

11 INOVA South Patient Tower Introduction Depth 1: Central Chilled Water Plant Design Alternatives First Costs / Energy Life-Cycle Cost Depth 2: Dedicated Heat Recovery Chiller Depth 3: Condensate Recovery Breadth 1: Two-Way Slab Reinforcing Breadth 2: Electrical Conclusion Acknowledgements Questions First Costs EquipmentUnit Cost Pump (7.5 HP)$ 4,070 / pump Pump (15 HP)$ 4,810 / pump Pump (30 HP)$ 8,440 / pump Cooling Towers – Induced (Axial)$ 38,220 / tower Centrifugal Chillers$ 350 / ton Absorption Chillers$ 550 / ton Schedule 40 Piping ( 8”)$ 203.15 / LF Insulation$ 25.33 / LF Unit Costs of Equipment 1325 4 RANK

12 INOVA South Patient Tower Introduction Depth 1: Central Chilled Water Plant Design Alternatives First Costs / Energy Life-Cycle Cost Depth 2: Dedicated Heat Recovery Chiller Depth 3: Condensate Recovery Breadth 1: Two-Way Slab Reinforcing Breadth 2: Electrical Conclusion Acknowledgements Questions Energy UtilityCost/Unit Electricity$ 23.45/ MMBTU Steam$ 11.40 / MMBTU Chilled Water$ 14.00 / MMBTU Water$ 2.16 / 1000 gal

13 INOVA South Patient Tower Introduction Depth 1: Central Chilled Water Plant Design Alternatives First Costs / Energy Life-Cycle Cost Depth 2: Dedicated Heat Recovery Chiller Depth 3: Condensate Recovery Breadth 1: Two-Way Slab Reinforcing Breadth 2: Electrical Conclusion Acknowledgements Questions Emissions

14 INOVA South Patient Tower Introduction Depth 1: Central Chilled Water Plant Design Alternatives First Costs / Energy Life-Cycle Cost Depth 2: Dedicated Heat Recovery Chiller Depth 3: Condensate Recovery Breadth 1: Two-Way Slab Reinforcing Breadth 2: Electrical Conclusion Acknowledgements Questions Life-Cycle Cost Analysis Alt. 1Alt. 2Alt. 3Alt. 4Alt. 5 Simple Payback BASELINE5.6 yrs.5.3 yrs.32.1 yrs.26.9 yrs. Discounted Payback BASELINE7.0 yrs.6.0 yrs.30+ yrs. Payback Summary Alternative 3: Centrifugal Chillers (VPF) Lowest Payback (Simple and Discounted) $2.4 Million Savings Compared to Current Design Lowest Energy and Emissions

15 INOVA South Patient Tower Introduction Depth 1: Central Chilled Water Plant Design Alternatives First Costs / Energy Life-Cycle Cost Depth 2: Dedicated Heat Recovery Chiller Depth 3: Condensate Recovery Breadth 1: Two-Way Slab Reinforcing Breadth 2: Electrical Conclusion Acknowledgements Questions Life-Cycle Cost Analysis

16 INOVA South Patient Tower Introduction Depth 1: Central Chilled Water Plant Design Alternatives First Costs / Energy Life-Cycle Cost Depth 2: Dedicated Heat Recovery Chiller Depth 3: Condensate Recovery Breadth 1: Two-Way Slab Reinforcing Breadth 2: Electrical Conclusion Acknowledgements Questions Life-Cycle Cost Analysis

17 INOVA South Patient Tower Introduction Depth 1: Central Chilled Water Plant Depth 2: Dedicated Heat Recovery Chiller Design/ Comparison Depth 3: Condensate Recovery Breadth 1: Two-Way Slab Reinforcing Breadth 2: Electrical Conclusion Acknowledgements Questions Dedicated Heat Recovery Chiller Module Chilled WaterHeat Rejection Cooling EER Heatin g COP EWT (F)LWT (F)EWT (F)LWT (F) 25 ton58421501703.72.1 32 ton58421501703.82.1 Cost / Unit Heat Recovery Chiller $ 600 / ton Heat Recovery Chiller Operating Conditions Unit Cost

18 INOVA South Patient Tower Introduction Depth 1: Central Chilled Water Plant Depth 2: Dedicated Heat Recovery Chiller Design/ Comparison Depth 3: Condensate Recovery Breadth 1: Two-Way Slab Reinforcing Breadth 2: Electrical Conclusion Acknowledgements Questions Dedicated Heat Recovery Chiller

19 INOVA South Patient Tower Introduction Depth 1: Central Chilled Water Plant Depth 2: Dedicated Heat Recovery Chiller Design/ Comparison Depth 3: Condensate Recovery Breadth 1: Two-Way Slab Reinforcing Breadth 2: Electrical Conclusion Acknowledgements Questions Dedicated Heat Recovery Chiller

20 INOVA South Patient Tower Introduction Depth 1: Central Chilled Water Plant Depth 2: Dedicated Heat Recovery Chiller Depth 3: Condensate Recovery Design Breadth 1: Two-Way Slab Reinforcing Breadth 2: Electrical Conclusion Acknowledgements Questions Condensate Recovery System Where: CFM = Airflow over Coil ρ air = density of air Δw = difference in humidity ratios across cooling coil JanuaryFebruaryMarchAprilMayJune Condensate (1000 gal.) 1.10.88.67.553.9128.0 JulyAugustSeptemberOctoberNovemberDecember Condensate (1000 gal.) 203.9161.186.44.76.81.8 Example Monthly Calculation (July)

21 INOVA South Patient Tower Introduction Depth 1: Central Chilled Water Plant Depth 2: Dedicated Heat Recovery Chiller Depth 3: Condensate Recovery Design Breadth 1: Two-Way Slab Reinforcing Breadth 2: Electrical Conclusion Acknowledgements Questions Condensate Recovery System Amount (1000 gal.)Annual Cost Water (Make-Up)4,891$ 10,565 Reduced Make-Up4,226$ 9,129 Savings14 %

22 INOVA South Patient Tower Introduction Depth 1: Central Chilled Water Plant Depth 2: Dedicated Heat Recovery Chiller Depth 3: Condensate Recovery Design Breadth 1: Two-Way Slab Reinforcing Breadth 2: Electrical Conclusion Acknowledgements Questions Depth Conclusions SPB: BASE5.35.25.1

23 INOVA South Patient Tower Introduction Depth 1: Central Chilled Water Plant Depth 2: Dedicated Heat Recovery Chiller Depth 3: Condensate Recovery Breadth 1: Two-Way Slab Reinforcing Analysis Breadth 2: Electrical Conclusion Acknowledgements Questions Structural Breadth Assuming #6 Bars Middle StripColumn Strip Neg. Moment Pos. Moment Neg. Moment Pos. Moment Moment (M U )-194.3+ 167.4-583.1+251.2 Width Column Strip174” Effective Depth9.375” 14.25”9.375” M N = M U / φ-215.94+186-647.9+279.1 R = (Mn x 12000) / bd 2 169.4145.95220.04219 ρ (Table A-3)*0.0033 0.0039 A s = ρbd5.383 in 2 9.67 in 2 6.362 in 2 A smin = 0.0018bt3.289 in 2 N = (larger 7 or 8) / 0.4413 2215 N min = width / (2t)9999 EquipmentAmountWeight/UnitTotal Weight (lbs) Centrifugal Chillers322,173 lb /each66,519 Heat Recovery Chiller42,000 lb / 25 ton8,000 Pumps9200 lbs / each1,800 Piping300 ft36.32 lb / ft10,896 Water-19.66 lb / ft Steel Pipe (8”)-16.66 lb / ft Total 87,215 Distributed LoadArea =3,364 ft 2 25.9 lb / ft 2

24 INOVA South Patient Tower Introduction Depth 1: Central Chilled Water Plant Depth 2: Dedicated Heat Recovery Chiller Depth 3: Condensate Recovery Breadth 1: Two-Way Slab Reinforcing Analysis Breadth 2: Electrical Conclusion Acknowledgements Questions Structural Breadth Column Strip: Negative Moment:0 bars (Design OK) Positive Moment:(10) #6 bars / bay Middle Strip: Negative Moment:(6) #5 bars / bay Positive Moment:(8) #5 bars / bay Sizelb/ftAmountLength (ft)Total Weight (lb.) # 6 1.5024014.5871.2 # 5 1.0435614.5846.9 TOTAL 1718.1 Structural Additional Cost: $ 0.76 / lb X 1718.1 lb = $ 1,305.76

25 INOVA South Patient Tower Introduction Depth 1: Central Chilled Water Plant Depth 2: Dedicated Heat Recovery Chiller Depth 3: Condensate Recovery Breadth 1: Two-Way Slab Reinforcing Breadth 2: Electrical Equipment Sizing Conclusion Acknowledgements Questions Electrical Breadth Electrical Additional Cost: $ 73,489 EquipmentCost 1600 A Switchboard$ 3,450 225 A Panelboard$ 1,090 Motor Starters$ 5,751 Wire$ 17,650 Conduit$ 7,501 Circuit Breakers$ 38,047

26 INOVA South Patient Tower Introduction Depth 1: Central Chilled Water Plant Depth 2: Dedicated Heat Recovery Chiller Depth 3: Condensate Recovery Breadth 1: Two-Way Slab Reinforcing Breadth 2: Electrical Conclusion Acknowledgements Questions Conclusion Centrifugal Chillers with VPF Dedicated Heat Recovery Chiller Condensate Recovery Savings: $ 2.729 million over 30 year life Simple Payback: 5.1 years Additional Structural / Electrical Costs Included Savings: $ 2.655 million over 30 year life Simple Payback: 5.6 years MAE Course Relation AE 557- Centralized Cooling Chilled Water Plant Design / Study AE 558- Centralized Heating Life-Cycle Cost Analysis Utility Costs

27 INOVA South Patient Tower Introduction Depth 1: Central Chilled Water Plant Depth 2: Dedicated Heat Recovery Chiller Depth 3: Condensate Recovery Breadth 1: Two-Way Slab Reinforcing Breadth 2: Electrical Conclusion Acknowledgements Questions Dr. William BahnflethFaculty Advisor, Penn State University Joseph KranzProject Executive, Turner Construction Tessa TeodoroProject Engineer, Turner Construction Andrew RhodesDesign Engineer, Southland Industries Kevin SmithEnergy Engineer, Southland Industries Raj VoraDirector, Life Sciences, Southland Industries Joe MulliganSales Engineer, Boland TRANE Tony McGheeAccount Executive, Johnson Controls Inc. Acknowledgements THANKS ALL OF YOU! All my fellow AE peers, friends and family for their support throughout the thesis process.

28 INOVA South Patient Tower Introduction Depth 1: Central Chilled Water Plant Depth 2: Dedicated Heat Recovery Chiller Depth 3: Condensate Recovery Breadth 1: Two-Way Slab Reinforcing Breadth 2: Electrical Conclusion Acknowledgements Questions THANK YOU QUESTIONS?

29 INOVA South Patient Tower

30


Download ppt "INOVA Fairfax Hospital South Patient Tower Falls Church, VA Senior Thesis 2012 Mike Morder Mechanical Option Advisor: Dr. William Bahnfleth."

Similar presentations


Ads by Google