1 Progress Review on Construction Projects as at 31.07.2015
Trincomalee Campus, Eastern University, Sri Lanka Progress Review on Construction Projects as at

2 Current Progress for Information Technology
Name of the Project Original / Amended TCE Implementation Period Cumulative Expenditure as at Financial Progress (%) Physical Progress (%) Allocation 2015 Estimate 2016 Projection Remarks Date of start Expected date of completion 2017 2018 Building Complex for the Information Centre, Trincomalee Campus 304.4 101.0 35% 42% 37.5 203.4 - 2nd payment has been paid

3 Current Progress for Library Building
Name of the Project Original / Amended TCE Implementation Period Cumulative Expenditure as at Financial Progress (%) Physical Progress (%) Allocation 2015 Estimate 2016 Projection Remarks Date of start Expected date of completion 2017 2018 Building Complex for the library, Trincomalee Campus 326.2 60.0 20% 25% 35.0 266.2 - Only Mobilization Advance Paid

4 Current Progress for Canteen with Recreation Facilities
Name of the Project Original / Amended TCE Implementation Period Cumulative Expenditure as at Financial Progress (%) Physical Progress (%) Allocation 2015 Estimate 2016 Projection Remarks Date of start Expected date of completion 2017 2018 Building Complex for the Canteen with Recreation Centre,Trincomalee Campus 130.4 23.0 20% 23% 20.0 107.4 - Only Mobilization Advance Paid

5 Current Progress for Five Storied Building for Faculty of Applied Science
Name of the Project Original / Amended TCE Implementation Period Cumulative Expenditure as at Financial Progress (%) Physical Progress (%) Allocation 2015 Estimate 2016 Projection Remarks Date of start Expected date of completion 2017 2018 Building Complex for the Faculty of Applied Science, Trincomalee Campus 410.0 74.0 20% 14% 40.0 336.0 - Only Mobilization Advance Paid

6 Current progress for play Ground
Name of the Project Original / Amended TCE Implementation Period Cumulative Expenditure as at Financial Progress (%) Physical Progress (%) Allocation 2015 Estimate 2016 Projection Remarks Date of start Expected date of completion 2017 2018 Constuction of play Ground at the Trincomlaee Campus 50.0 24.0 48% 70% - 26.0