Progress Review On Ongoing Construction Projects aimed at Budget - 2016 Professor Ranjith Premalal De Silva Vice Chancellor Uva Wellassa University, Sri.

Similar presentations


Presentation on theme: "Progress Review On Ongoing Construction Projects aimed at Budget - 2016 Professor Ranjith Premalal De Silva Vice Chancellor Uva Wellassa University, Sri."— Presentation transcript:

1 Progress Review On Ongoing Construction Projects aimed at Budget - 2016 Professor Ranjith Premalal De Silva Vice Chancellor Uva Wellassa University, Sri Lanka Dr. Gamani Chandrasena Vice Chancellor Uva Wellassa University, Sri Lanka

2 Construction (Capital) Projects of Uva Wellassa 1.Phase I 2.Phase II Phase I i.Administration Building Block ii.Lecture Hall + Lab (Block A) iii.Lecture Hall + Lab (Block B) iv.Lecture Hall + Lab (Block C) Total Cost Estimated (Amended TCE) => Rs. 350 Million Actual Expenditure incurred to 30.06.2015 => Rs. 348 Million Future Commitment (Final Bill to be Settled) => Rs 10 Million Physical Process: 100% Financial Progress: 99% Administration Building Block Awarding On: 03 rd Aug 2005 Completed On: 16 th Oct 2006 25 August 2015

3 Lecture Hall + Lab (Block B) Awarding On: 03 rd Aug 2005 Completed On: 11 th Oct 2006 Lecture Hall + Lab (Block C) Awarding On: 03 rd Aug 2005 Completed On: 11 th Oct 2006 Lecture Hall + Lab (Block A) Awarding On: 03 rd Aug 2005 Completed On: 01 st Nov 2006 25 August 2015

4 Hostel Block No. 2 Awarding On: 01 st Sep 2006 Completed On: 26 Jun 2008 Physical Progress : 100% Financial Progress : 87% Hostel Block No. 3 Awarding On: 01 st Aug 2006 Completed On: 04 th Dec 2008 Physical Progress : 100% Financial Progress : 87% Hostel Block No. 1 Awarding On : 01 st Jul 2006 Completed On : 30 th Jul 2007 Physical Progress : 100% Financial Progress : 87% 25 August 2015 Phase II

5 Dinning & Study Hall Kitchen for Dinning & Study Hall Awarding On : 15 th May 2006 Completed On : 30 th Jun 2006 Physical Progress : 100% Financial Progress : 87% Water Sump & Pump House Awarding On: 01 st Sep 2006 Completed On: 16 Jun 2008 Physical Progress : 100% Financial Progress : 73% Hostel Block No. 4 Awarding On: 01 st Nov 2006 Completed On: 25 th Jul 2008 Physical Progress : 100% Financial Progress : 87% 25 August 2015 TCE: 457 Million

6 Name Board and Developments at entrance Awarding On: 01 st Jul 2007 Completed On: 19 th Jan 2008 Physical Progress : 100% Financial Progress : 35% Temporary Sports Court Awarding On: 15 th Jan 2007 Completed On: 27 th Feb 2006 Physical Progress : 100% Financial Progress : 70% Landscaping - Phase - 1 Area Awarding On: 01 st Jan 2007 Completed On: 19 th Jan 2008 Physical Progress : 100% Financial Progress : 70% 25 August 2015

7 Fiber Network (IT back-born at Phase 1 buildings) Awarding On: 01 st Dec 2007 Completed On: 31 st Dec 2008 Physical Progress : 100% Financial Progress : 97% Vice Chancellor's Bungalow Awarding On: 08 th Sep 2008 Completed On: 09 th Mar 2010 Physical Progress : 100% Financial Progress : 98% Play Ground (For 200m track) Awarding On: 01 st Apr 2007 Completed On: 13 th Sep 2009 Physical Progress : 100% Financial Progress: 63%

8 25 August 2015 Internal Road Network (A,B & D) Awarding On: 01 st Mar 2007 Completed On: 30 th Mar 2009 Physical Progress : 100% Financial Progress: 66% Lecture Hall + Lab (Block E) Awarding On: 05 th Sep 2008 Completed On: 15 th Mar 2011 Physical Progress : 100% Financial Progress : 65% Lecture Hall + Lab (Block F - I) Awarding On: 01 st Jan 2009 Completed On: 08 th Mar 2010 Physical Progress : 100% Financial Progress: 65%

9 25 August 2015 Lecture Hall + Lab (Block F - II) Awarding On: 27 th Apr 2010 Completed On: 26 Jul 2011 Physical Progress: 100% Financial Progress: 65% Lecture Hall + Lab (Block D) Awarding On: 27 th Apr 2010 Completed On: 26 th Aug 2011 Physical Progress: 100% Financial Progress:65% Storm Water Drainage System Awarding On: 30 th Dec 2009 Physical Progress: 65% Financial Progress: 17% Ongoing

10 25 August 2015 Quarters for Deans/ Registrar/ Bursar & Course Directors Awarding On: 01 st Dec 2011 Completed On: 15 th Feb 2013 Physical Progress: 100% Financial Progress : 77% Staff Quarters (Studio Apartments) Awarding On: 25 th Nov 2012 Completed On: 05 th Mar 2013 Physical Progress: 100% Financial Progress: 50% Roads and Landscaping at Phase II Area Awarding On:17 th Dec 2009 Physical Progress: 50% Financial Progress : 41% Ongoing

11 25 August 2015 Sports Center & Gymnasium Awarding On : 30 th Dec 2014 Physical Progress : 25% Financial Progress : 25% Pavilion Awarding On:06 th Aug 2015 Physical Progress: 5% Financial Progress : 5% (Mobilization Advance) Ongoing Cafeteria and Toilets Awarding On: 27 th Aug 2012 Completed On: 26 th Aug 2013 Physical Progress: 100% Financial Progress: 100%

12 25 August 2015 Maintenance section Awarding On: 08 th Jan 2014 Completed On: 08 th Oct 2014 Physical Progress: 100% Financial Progress: 66% Senate Building Awarding On: 20 th Mar 2013 Physical Progress: 95% Financial Progress: 85% Ongoing Balance work Roads & Landscaping Awarding On: 22 nd Mar 2014 Awarding On: 22 nd Mar 2014 Physical Progress: 65% Financial Progress: 44% Ongoing

13 Waste water drainage & treatment works (Job 01 & Job 02) Awarding On:14 th Oct 2010 / 17 th May 2013 Physical Progress: 85% Financial Progress: 36% University Guest House Awarding On: 05 th Nov 2012 Completed On: 17 th Aug 2013 Physical Progress: 100% Financial Progress: 96% 25 August 2015 Ongoing University Guest House Awarding On: 05 th Sep 2011 Completed On: 20 th Oct 2012 Physical Progress: 100% Financial Progress: 64%


Download ppt "Progress Review On Ongoing Construction Projects aimed at Budget - 2016 Professor Ranjith Premalal De Silva Vice Chancellor Uva Wellassa University, Sri."