Presentation is loading. Please wait.

Presentation is loading. Please wait.

2006 Project Management Workshop External Independent Reviews Catherine Santana November 14, 2006.

Similar presentations


Presentation on theme: "2006 Project Management Workshop External Independent Reviews Catherine Santana November 14, 2006."— Presentation transcript:

1 2006 Project Management Workshop External Independent Reviews Catherine Santana November 14, 2006

2 2006ProjectManagementWorkshop 2 Improving the EIR Process EIRs Should Not be “One Size Fits All” Develop Risk Based EIR Plans Match Team Expertise to Review Requirements Increase Review Team Resources Strive to Shorten Review Period Develop Consistent Processes and Criteria

3 2006ProjectManagementWorkshop 3 Goals Add Value to the Department, Programs and Projects Help to Improve Projects’ Success in Executing to the Established Baseline Increase EIR and Project Credibility Reduce EIR Costs Work Collaboratively While Remaining Objective and Independent

4 2006ProjectManagementWorkshop 4 “One Size Fits All” Same Level of Effort and Same Costs, Regardless of Complexity and Scope of Project Tailoring Considerations - Project Risk and Complexity - Project Tailoring Strategy - Breadth and Depth of the Review - Lines of Inquiry - Paper Review/Site Review Just as you Tailor the Project so Shall we Tailor the Review

5 2006ProjectManagementWorkshop 5 Consistent Results Quality - Report - Findings and Recommendations Interpretation of DOE O 413.3A and DOE M 413.3-1 Level of Program/Project Knowledge Collaborative Approach

6 2006ProjectManagementWorkshop 6 Next Steps Revamp the EIR Process - Conduct Facilitated Process Reviews - Capture Lessons Learned - Evaluate Existing Contract - Develop Contractor Performance Measures Develop EIR Statistics - Costs - Time to Validate - Baseline Cost and Schedule Impacts - Common Findings/Recommendations

7 2006ProjectManagementWorkshop 7 What Have We Learned? Major Findings and Other Findings are Often Significant Baselines Cannot be Validated with the Initial Review Corrective Action Plans are “Often” Almost “Always” Required Satisfactorily Resolving Findings Extends the EIR Timeline

8 2006ProjectManagementWorkshop 8 Common Findings Funding Profiles do not Support the Project Baselines Cost and Schedule Contingencies are Under Estimated Critical Paths are Often Obscured by Level of Effort Activities Risk Management Plans are Deficient Assumptions are Invalid or Too Optimistic Management Reserve is not Defined or Included …Often Identify Inadequate Project Management Infrastructures Necessary to Execute the Baseline

9 2006ProjectManagementWorkshop 9 Risk Management Plans Many common risk events that are normally associated with … projects are not included in the risk management plan The risk register does not indicate the probability and consequence rankings for each risk… Mitigation strategies are not specifically shown as discrete activities in the project schedule… The risk/contingency analysis is not risk based… Lack of quantitative contingency analysis…to address the occurrence of risk events.

10 2006ProjectManagementWorkshop 10 Impact Can Be Significant Faulty Assumptions Incomplete Risk Management Plans Inadequate Management Reserve and Contingency Under Estimated Baselines


Download ppt "2006 Project Management Workshop External Independent Reviews Catherine Santana November 14, 2006."

Similar presentations


Ads by Google