Vision for Power Sector: To Ensure reliable & quality power supply to all citizens by 2021 at an affordable price. Vision 2021: To be a Middle-Income.

Similar presentations


Presentation on theme: "Vision for Power Sector: To Ensure reliable & quality power supply to all citizens by 2021 at an affordable price. Vision 2021: To be a Middle-Income."— Presentation transcript:

1

2 Vision for Power Sector: To Ensure reliable & quality power supply to all citizens by 2021 at an affordable price. Vision 2021: To be a Middle-Income Country 2 Vision

3 3 Power Sector At a glance Electricity Growth: 9 % Generation Capacity: 14,077 MW Total Consumers: 17.8 Million Transmission Line: 9,695 Ckt. km Distribution Line: 3,41,000 km Distribution Loss: 11.36 % Per Capita Generation: 371 kWh Access to Electricity: 74%

4 Success story: Last Six years Success story: Last Six years 20092015Achievement Power Plants (No) 27100 (+) 73 Generation Capacity (MW) 4,94214,077 (+) 9,135 Highest Generation 3,2688,177 (+) 4,909 Per Capita Generation (KWh) 220371 (+) 151 Access to Electricity (%) 4774 (+) 27 Consumers (lakh) 108178 (+) 70 Transmission Line (Ckt Km) 8,0009,695 (+) 1,695 Distribution Line (Km) 2,60,0003,41,000 (+) 81,000 System Loss (%) 18.4513.55 (-) 4.9 4

5 Present Generation: Fuel Mix Present Generation: Fuel Mix 5

6 Power Generation Addition From Jan’09 to Oct’15 6

7 Up Coming Generation Projects 7 SlDescriptionProjects (Number) Capacity (MW) 01Under Construction256082 02In the Process of Tendering207848 03Under Planning Process74685 Total5218615

8 Year-wise Power Generation Plan for 2015 - 2021 YEAR2015201620172018201920202021 TOTAL (MW) Public Sector (MW) 8488852,0201,3971,6111,0001,9009661 Private Sector (MW) 1,110428630 1,1521,8111,9127,673 Total (MW)1,9581,3132,6502,0272,7632,8113,81217,334 8

9 Power System Master Plan (PSMP) 2010 (PSMP) 2010 Year Target (MW) 201616,000 202124,000 203040,000 According to the PSMP-2010 Power generation Capacity targets up to 2030: 9

10 Bangladesh Transmission System at a Glance 10 Transmission Line: 400kV:165 Circuit Km 230 kV:3172 Circuit Km 132 kV:6359 Circuit Km Substations : 23818 MVA HVDC BtB:01 (500MW) 230/132 kV: 16 (8775 MVA) + 2 Nos. Switching 230/132 kV (BPDB & APSCL):2 (550 MVA) 132/33 kV:89 (11568 MVA) 132/33 kV (BPDB, DPDC, DESCO & Others) :20 (2425 MVA)

11 Power Transmission: Future Plan Power Transmission: Future Plan 11 Voltage (kV)Length (Ckt-km) 13210,297 2305,081 4003,711 800180 Total19, 269 Voltage (kV)Capacity (MVA) 13232,000 23037,225 40014,970 Total84, 195

12 Power Distribution: Future Plan Power Distribution: Future Plan 12 Parameters 2015 (At present) 20212030 Consumers (Mill.)17.824.236.3 Line Constr (Thou KM)341481641 Sub-Station (MVA)24,72035,70066,500 Peak Demand (MW)8,17718,80033,700 Distribution System Loss11.36 %9.50 %8.70 %

13 Prepaid Metering System 13 Objectives:  Upfront payment  Decreased non-technical losses  Tamper protection  Non-allowance of over sanctioned load  Better customer services  Automated record keeping  Create power saving attitude to the consumers Progress:  Already 98,000 prepaid meter installed  Under pipelines( tendering Process) : 11 lacs  Under planning stages: 121 lacs.

14 ICT Activities 14  Project Monitoring System  Monthly Meeting Report System  E-filing system  Setting Up Video Conferencing System  On-line Recruitment System  Personnel Information Management System  Audit Management System

15 ICT Activities 15  Online Application for Electricity Connection  Bill Payment Through Mobile Phone  Bill Pay Through Online  Meter Reading Through Snap Shot  Bill Payment Through Union Information & Service Centre (UISC)  Contact Centre/ Customer Complaint Management System (Under Process )

16 Renewable Energy At a glance 16 Policy adopted Dedicated institute created Set targets 185 Mega Watt installed 4.0 Million Solar Home System 10% population coverage 3100 Planned by 2021 Wind Resource Assessment at 13 sites 80,000 Bio gas plants installed 5 million ICS sold Going to set Bench Mark Tariff

17 Energy Savings 17  Use sun light and free air as much as possible  Switch off before leaving your room  Turn off your electronic device after use  Do not use AC, electric iron, water pump during peak hours  Use of LED, CFL bulb  Avoid un-necessary lighting in the room  Limited use of Air Conditioners keeping temperature 25°C & above  Use of energy efficient appliances