DEA IT CONSULTING THE TEAM: DAVID CLARKE EMMANUEL CAUBALEJO ADAM WHEATON CIITS Server Infrastructure Optimization.

Similar presentations


Presentation on theme: "DEA IT CONSULTING THE TEAM: DAVID CLARKE EMMANUEL CAUBALEJO ADAM WHEATON CIITS Server Infrastructure Optimization."— Presentation transcript:

1 DEA IT CONSULTING THE TEAM: DAVID CLARKE EMMANUEL CAUBALEJO ADAM WHEATON CIITS Server Infrastructure Optimization

2 Agenda Project Background Accomplishments Budget Conclusion

3 Project Background Who? What? When? Where? How?

4 Accomplishments Project management process experience Learned how to deal with deadlines Learned how to manage multiple scope changes Modern operating system knowledge growth

5 Budget Projected Costs  Hardware total cost: $3,734.99  Operating Costs: $37,440 Actual Costs  Hardware total costs: $3,839.98  Operating Costs: $10,200 Variance: $27,135.01

6 Conclusion  Great work with CIITS lab  Great learning experience  Budget:  Estimated Cost: $41,174.99  Actual Cost: $14,039.98  Variance: $27,135.01

7 Special Thanks Ben Reed CIITS Lab Jason Fisher Colin Chamberlain Joe Petermann SAIT institution and our fantastic teachers