1 -Classification: Internal 2011-01-19 Gullfakslandsbyen 2011 Knut.

Similar presentations


Presentation on theme: "1 -Classification: Internal 2011-01-19 Gullfakslandsbyen 2011 Knut."— Presentation transcript:

1 1 -Classification: Internal 2011-01-19 Gullfakslandsbyen 2011 Knut

2 2 -Classification: Internal 2011-01-19 Challenge 2. Drilling of a long reach water injector A new water injection well to the Beta ridge is being planned from the Gullfaks B platform. Planning the well is ongoing. A good well project is often “drilled on the paper” before initiated offshore. Describe a possible route from “drilling the well on paper”. The drilling industry has the last 5 years established remote expert team onshore. Describe how the Statoil should perform the expert team solution. Make a recommendation about which measures Statoil need to take in order to be able to drill these wells to Gullfaks Sør Statfjord. Statoil advisor: Johan Eck-Olsen

3 3 -Classification: Internal 2011-01-19 Specific requirements to planning Organizing the detailed planning phase Work process description Project schedule Peer Assist and Peer Review Detailed 15 minutes plan Decision and task log Risk Assessment Check list Decision trees and contingency plan Detailed drilling and well program Best Practice

4 4 -Classification: Internal 2011-01-19 Evaluated in Peer Assist and Peer Review Project plans Statoil relevant governing documentation Authorities rules and regulations Budget, based on uncertainty simulations Score board Programs Procedures Risk identification log Decission trees Pros and cons for different scenarioes and cases

5 5 -Classification: Internal 2011-01-19 DWB WIB - Well Interventions Bergen Well Interventions Manager DWB WIB Torstein Haugland Bergen Gullfaks 1 DWB WIB WG1 Knut Müller Bergen Gullfaks 2 DWB WIB WG2 Njål Grønnerød Bergen Oseberg DWB WIB WOO Hans Morten Koldal Bergen North Sea 1 DWB WIB NS Gunnar Halle Daae Bergen North Sea 2 DWB WIB NS2 Stephen Stragiotti Bergen DWB WIB PI Well Interv. Plan Dep. Jens M. Wennesland Bergen

6 6 -Classification: Internal 2011-01-19 D&W DWB WIB, Activity 2010 pr 31.12 Operations: 65 Operations: 20 Operations: 31Operations: 32

7 7 -Classification: Internal 2011-01-19

8 8 -Classification: Internal 2011-01-19

9 9 -Classification: Internal 2011-01-19 Coiled Tubing

10 10 -Classification: Internal 2011-01-19 Stimulation Vessel

11 11 -Classification: Internal 2011-01-19 Mechanical WL/ Electrical WL/Traktor

12 12 -Classification: Internal 2011-01-19 Challenge 3a. PLT in Gulltopp Gulltopp is a 10 km well drilled from Gullfaks A platform. The well had water breakthrough after two years of production and it is now desirable to find out from which zone the water is coming. Explain the PLT technology and how a Production logging tool (PLT) can improve the oil recovery at Gulltopp. Plan a detailed PLT job for Gulltopp. (This includes simulations and detailed PLT procedure) Make a cost estimate based on information from vendors, and show economics before tax including Net Present Value. Statoil advisor: Knut Müller

13 13 -Classification: Internal 2011-01-19

14 14 -Classification: Internal 2011-01-19 Challenge 3b. WL operations bellow the rig on GF. The three Gullfaks platforms have two shafts with wells. Well operations and drilling can then work independent. When production wells has to be shut in due to barrier problems on the same shaft as drilling is doing their work, it would be beneficial to secure this well properly without stopping drilling operation. Explain equipment for rigging up WL bellow the rig. What are the main issues for running WL bellow the rig? What are the financial benefits of running WL bellow the rig? Statoil advisor: Knut Müller.

15 15 -Classification: Internal 2011-01-19 Wells on GFA

16 16 -Classification: Internal 2011-01-19

17 17 -Classification: Internal 2011-01-19 Presentation title Presenters name Presenters title E-mail address, tel: +00 00 00 00 www.statoil.com Thank you