GLAST LAT ProjectMarch 24, 2003 6C Tracker Peer Review, WBS 4.1.4 1 GLAST Large Area Telescope: Tracker Subsystem WBS 4.1.4 6C: Ladder Fabrication A. Brez.

Similar presentations


Presentation on theme: "GLAST LAT ProjectMarch 24, 2003 6C Tracker Peer Review, WBS 4.1.4 1 GLAST Large Area Telescope: Tracker Subsystem WBS 4.1.4 6C: Ladder Fabrication A. Brez."— Presentation transcript:

1 GLAST LAT ProjectMarch 24, 2003 6C Tracker Peer Review, WBS 4.1.4 1 GLAST Large Area Telescope: Tracker Subsystem WBS 4.1.4 6C: Ladder Fabrication A. Brez I.N.F.N. Pisa Brez@pi.infn.it Gamma-ray Large Area Space Telescope

2 GLAST LAT ProjectMarch 24, 2003 6C Tracker Peer Review, WBS 4.1.4 2 Ladder construction flow down LAT ladder construction follows the block diagram (see LAT-PS- 00635 and LAT-PS-00831 for details) Assembly in G&A Engineering (251 flight ladder produced) Assembly in Mipot staring up (PRR in April)

3 GLAST LAT ProjectMarch 24, 2003 6C Tracker Peer Review, WBS 4.1.4 3 SSD edge bonding Manual fast AND precise method 24 ladder assembly tools used in parallel Very good ladder alignment obtained Ladder assembly tool

4 GLAST LAT ProjectMarch 24, 2003 6C Tracker Peer Review, WBS 4.1.4 4 Encapsulation Dam & Fill encapsulation Dam Nusil 1142 Fill Nusil 15-2500 Requirements: 1.Height <0.5mm 2.Lateral overflow <0.05mm 3.Coverage of all the bondings and pads Fast system to check encapsulation height

5 GLAST LAT ProjectMarch 24, 2003 6C Tracker Peer Review, WBS 4.1.4 5 Ladder electrical test: methods 2 PA200 probe stations with modified chucks to accept ladders are in activity (G&A and Mipot) Tests: IV curve (ladder leakage current from 0V to 200V) CV curve (ladder total capacity and depletion voltage) Single channel AC test: 100 V voltage step to measure AC insulation and AC capacity  o Connected strips  o Interrupted strips I(5  )>10nA AC short IV,CV test scheme AC strips test scheme

6 GLAST LAT ProjectMarch 24, 2003 6C Tracker Peer Review, WBS 4.1.4 6 Electrical Tests: Results Electrical test results: 1.Ladder tested251 2.Accepted243 (97%) 3.Broken edge 4 4.Probe accident 1 5.Not understood 3 The causes of problems 3 and 4 have been corrected, foreseen rejection rate ∼ 1% Bad channels caused by bonding (coupling shorts)=0.016% (accepted limit 1%) No broken or bad bondings

7 GLAST LAT ProjectMarch 24, 2003 6C Tracker Peer Review, WBS 4.1.4 7 Database A Access database system installed in the two assembly centers, collects all the relevant data of the ladders: SSDs alignment IV curve CV curve Bad channels (AC insulation test) Not bonded channels The database allows a fast and accurate monitoring of the ladder production. This database adds to the traveler systems installed in the assembly company (ISO9001) which ensure the whole traceability of materials, instruments, procedures.

8 GLAST LAT ProjectMarch 24, 2003 6C Tracker Peer Review, WBS 4.1.4 8 Conclusions The ladder construction successfully started (9% of the ladders have been produced with a 97% yield, possible increase of the yield to 99%). Electrical and dimensional ladders characteristics well within specifications Production rate > 10 ladders/day in both assembly centers that will work in parallel (G&A Engineering and Mipot), so there are no schedule problems with this item