1 Maintenance and Accelerator Support RHIC Start Up 12

2 Accelerator Status: EBIS, LINAC, Booster and AGS are presently setting up with beam. EBIS, LINAC, Booster and AGS are presently setting up with beam. Access to AGS and Booster scheduled around failure. Access to AGS and Booster scheduled around failure. Submit desired jobs to the job request system. Submit desired jobs to the job request system. AGS extraction setup next week AGS extraction setup next week No Access to U downstream, W, X and Y lines. No Access to U downstream, W, X and Y lines. Any access to be scheduled. Any access to be scheduled. Booster Maintenance Next Wednesday 1/18/12 0700-1200hrs Booster Maintenance Next Wednesday 1/18/12 0700-1200hrs

3 RHIC status: Tunnel and IRs on Restricted Access. Tunnel and IRs on Restricted Access. Shielding in place, awaiting inspection. Shielding in place, awaiting inspection. No Access, eves and nights starting January 20 th. No Access, eves and nights starting January 20 th. Presently ODH0 in the tunnel. Presently ODH0 in the tunnel. Berm areas of RHIC are secured, scheduled access only. Berm areas of RHIC are secured, scheduled access only. Tomorrow and Thursday : Emergency generator transfer switch tests, momentary ACS outages possible. Tomorrow and Thursday : Emergency generator transfer switch tests, momentary ACS outages possible.

4 Next week: Controlled/Radiation area postings at RHIC, ring road. Controlled/Radiation area postings at RHIC, ring road. Wednesday – Saturday (Following 4k wave): Wednesday – Saturday (Following 4k wave): Secure any normally locked/fenced areas as necessary. Secure any normally locked/fenced areas as necessary. Power supply and Cryogenic work during the day/evening. Power supply and Cryogenic work during the day/evening. Beam work evenings/nights starting 1/21 Beam work evenings/nights starting 1/21 Select areas of the ring secured during the daytime. Schedule for securing TBD. Select areas of the ring secured during the daytime. Schedule for securing TBD. When ready for beam, secure experimental areas When ready for beam, secure experimental areas

5 During the Ramp Up. Injectors will remain closed and running with beam. Injectors will remain closed and running with beam. Any RHIC access will be scheduled at daily meetings. Any RHIC access will be scheduled at daily meetings. Daily schedules will be published on the Web and displayed on the CATV system. Daily schedules will be published on the Web and displayed on the CATV system. E-lens Phase shifter tests will occur after power supply checkout is complete. E-lens Phase shifter tests will occur after power supply checkout is complete. Regular maintenance days will be scheduled after the ramp up period is completed and Physics is declared. Regular maintenance days will be scheduled after the ramp up period is completed and Physics is declared.