Presentation is loading. Please wait.

Presentation is loading. Please wait.

Roman Pot Engineering Design Review CERN, 14 February 2006 M.Oriunno, CERN PH-TOT Installation, Commissioning and Schedule.

Similar presentations


Presentation on theme: "Roman Pot Engineering Design Review CERN, 14 February 2006 M.Oriunno, CERN PH-TOT Installation, Commissioning and Schedule."— Presentation transcript:

1 http://totem.web.cern.ch/Totem/ Roman Pot Engineering Design Review CERN, 14 February 2006 M.Oriunno, CERN PH-TOT Installation, Commissioning and Schedule Marco Oriunno CERN, PH TOT TOTEM Collaboration http://totem.web.cern.ch/Totem / ROMAN POT Engineering Design Review, CERN 14 February 2006

2 http://totem.web.cern.ch/Totem/ Roman Pot Engineering Design Review CERN, 14 February 2006 M.Oriunno, CERN PH-TOT

3 http://totem.web.cern.ch/Totem/ Roman Pot Engineering Design Review CERN, 14 February 2006 M.Oriunno, CERN PH-TOT TOTEM Geography @ LSS5 220 m, C6.L5 145 m, C4.L5 220 m, C6.R5 145 m, C4.R5

4 http://totem.web.cern.ch/Totem/ Roman Pot Engineering Design Review CERN, 14 February 2006 M.Oriunno, CERN PH-TOT Integration of services Trigger latency critical for the station at 220 m Optimized cable routing of the trigger cable to the CMS counting room

5 http://totem.web.cern.ch/Totem/ Roman Pot Engineering Design Review CERN, 14 February 2006 M.Oriunno, CERN PH-TOT 2 Racks in the USC55Tunnel Motors and Controls cabling Accessible area with circulating beam Not Accessible area with circulating beam

6 http://totem.web.cern.ch/Totem/ Roman Pot Engineering Design Review CERN, 14 February 2006 M.Oriunno, CERN PH-TOT The installation procedure

7 http://totem.web.cern.ch/Totem/ Roman Pot Engineering Design Review CERN, 14 February 2006 M.Oriunno, CERN PH-TOT Deliverables from previous tasks : Roman pot stations installed and aligned, cooling plant installed, cables and patch panels electrically tested and connected Infrastructures : In addition to the permanent specified services, Power supply 220V/50Hz for test equipments, Internet connection Access requirements: Standard access mode to the tunnel, since no dangerous materials or tests are foreseen. Access granted to a team of ~4 people minimum plus tools per sub-system to be commissioned 1 st assumption -> The Roman Pot are vacuum equipments of the LSSs. They must be included in the planning of the vacuum commissioning of the LSS, namely: Sectorization valves, bake out, NEGs activation, pure gas filling if required. 2 nd assumption -> At the commissioning the pots are under secondary vacuum, but without the detectors. 1.Motors & controls commissioning 2.Cooling System Commissioning 3.Interlocks & Signals Commissioning 4.Detectors connectivity and cooling Commissioning of the Roman Pot (Discussed at the LHC Hardware Commissioning Working Group, 3 march 2005) https://edms.cern.ch/document/566502/1

8 http://totem.web.cern.ch/Totem/ Roman Pot Engineering Design Review CERN, 14 February 2006 M.Oriunno, CERN PH-TOT Tasks: Movements sequence of each independent motor Garage position->Data taking position->Garage position Validation of Encoders reading Validation of LVDTs reading Beam Position Monitor calibration Crew : 1 Sub –system supervisor 1 technicians in the tunnel 1 technicians in the counting room 1 operator in the control room Timing: 24 pot & motors to be checked ~ 8 hours for 1 crew FTE Remarks: The primary vacuum is required Motors & controls commissioning sequences

9 http://totem.web.cern.ch/Totem/ Roman Pot Engineering Design Review CERN, 14 February 2006 M.Oriunno, CERN PH-TOT Tasks :Check the logic of the interlocks signals with the Control Room To be included in the interlock commissioning of the machine Crew : 1 Sub –system supervisor 1 technician in the tunnel 1 operator in the Control room Timing: ~ 4 hours for 1 crew FTE Remarks : Non need of the machine vacuum Interlocks & Signals Commissioning sequences

10 http://totem.web.cern.ch/Totem/ Roman Pot Engineering Design Review CERN, 14 February 2006 M.Oriunno, CERN PH-TOT Tasks : Electrical connection of a test assembly detector (warm system) Checking of:readout system low voltage bias voltage temperatures Crew : 1 Sub –system supervisor 1 technicians in the tunnel 1 technicians in the counting room Timing: 24 detector assemblies to check ~ 12 hours for 1 crew FTE Remarks : Non need of the machine vacuum Detectors connectivity

11 http://totem.web.cern.ch/Totem/ Roman Pot Engineering Design Review CERN, 14 February 2006 M.Oriunno, CERN PH-TOT High population density in the region between the TAN and D2 (C4.R5 & C4.L5) : Roman Pot, BI, Collimators, Vacuum components -> conflicts during the commissioning of the different items Possible interferences :

12 http://totem.web.cern.ch/Totem/ Roman Pot Engineering Design Review CERN, 14 February 2006 M.Oriunno, CERN PH-TOT Preparation on Surface January-October 2006 1.Roman Pot equipment assembled on surface without detector 2.UHV Test of the system 3.Commissioning of the full system on surface (detectors, cooling, vacuum) 4.Relative alignment by metrology of the moving components Calibration of motors and encoders 5.Test beam on a fixed target (only for one or two units) Underground access through the PM56 shaftOctober-February 2007 1.Installation of the cooling system 2.Installation at the defined locations along the tunnel 3.Check of the cabling (motors, controls interlocks) 4.Vacuum Chambers connection 5.Alignment on the beam Roman Pot Commissioning After the LHC commissioning and just before the pilot runs 1.Installation of the detectors assembly in the pots 2.Connection to the patch panels and to the cooling plant Installation phases break down

13 http://totem.web.cern.ch/Totem/ Roman Pot Engineering Design Review CERN, 14 February 2006 M.Oriunno, CERN PH-TOT Installation vs. the LHC machine


Download ppt "Roman Pot Engineering Design Review CERN, 14 February 2006 M.Oriunno, CERN PH-TOT Installation, Commissioning and Schedule."

Similar presentations


Ads by Google