GCOM-W1,AMSR-E/ADEOS-II Project Update in EORC GCOM Research Group in EORC Masato Yamanashi 29 th June 2011, NCDC,Asheville, NC.

Similar presentations


Presentation on theme: "GCOM-W1,AMSR-E/ADEOS-II Project Update in EORC GCOM Research Group in EORC Masato Yamanashi 29 th June 2011, NCDC,Asheville, NC."— Presentation transcript:

1 GCOM-W1,AMSR-E/ADEOS-II Project Update in EORC GCOM Research Group in EORC Masato Yamanashi 29 th June 2011, NCDC,Asheville, NC

2 Japanese FY * FY2009FY2010FY2011FY2012FY2013FY2014 Major Milestones RA Algorithm Homepages & Data Distribute Cal/Val RA #1 (W1)RA #3 (W1+Multi-sensor research)RA #5 Development PrototypingImplementationTesting/Optimization Keep(AMSR-E)&Preparation (sites, tools, methodologies) Operational Issue RA#3 (W1+Multi) W1 Launch V.1 GEOV.1 TB Criteria #1 ( Revise every 1.5 or 2 years after launch) Algorithm selection (standard products) PreparationOperation/Improvement EORC GCOM Group main tasks and its schedules

3 Standard Algorithms ・ 3 rd RA announced on 21 st January, 2011 and closed on 25 th March ・ Research areas(Categories): - GCOM-W1 research: algorithm development, validation, and application research - Multi-sensor research: multi-sensor algorithm development and application research Status of 3 rd RA ・ The conclusion of Selection will be announced soon, (at early August)

4 ParametersAlgorithm PI TPWKazumori CLWKazumori PRRAonashi SSTShibata SSWShibata SICJ.Comiso (led by Cho) SMCKoike SNDR.Kelly GCOM-W1 L2 Standard algorithms for the first data release. Standard Algorithms ・ Decided at the last PI WorkShop in Tokyo, on December 2010

5 EORC Homepages EORC Home Pages structure (plan now) InformationDetailsContents Top GCOM-W1 Introduction Mission outline Explanation on mission outline Operation information Schedules of maneuver, Loss of data etc Data Product & Algorithms Sort of products and its developer Calibration & Validation Calibration,Validation plan Validation data Provide validation data Tools Product access tools(AMTK)and so on Organization (after 3 rd RA) ATBD Documents of Algorithms Topics Press Release Image Grally Today’s best shot

6 Top page of Data Distribute System Developed by GCOM project Group Data Distribution System

7 Select the data from the following choices – Data Categories, the sort of physical parameters( like SST,SSW and so on) – Satellite or Sensors, etc Using shopping trolley icons, more user-friendly Format exchange functions AMSR/AMSR-E are HDF4,AMSR2 is HDF5, provided by these original format basically. – GeoTIFF,TIFF – netCDF(netCDF 4 classic model,CF-1.4) – HDF5(for AMSR-E/AMSR only) Features of this system

8 Data Distribution System We will provide standard products through Data Distribution System( using online,http,sftp) – Start to provide AMSR-E/AMSR2 soon (plan) – RA research and cooperate organizations Start to provide after initial checkout( 3month after the launch) – Other users Start to provide after the calibration/validation phase ( 1 year after the launch) Provide plan

9 LevelContents Level-1A Swath data with geolocation information Scene counts ½ orbit starting from northern/southern-most latitudes Level-1B Swath data with geolocation information Brightness temperatures ½ orbit starting from northern/southern-most latitudes Level-1R Swath data with geolocation information Spatial-resolution matched brightness temperatures 4 resolution sets (6,10,23,36GHz) and raw swath for 89GHz A/B Level-2 Swath data with geolocation information Geophysical parameters (8 parameters) ½ orbit starting from northern/southern-most latitudes Leve-3 Grid data with 0.1/0.25 degrees (10/25km) resolution Brightness temperatures and geophysical parameters Daily and monthly temporal average Equidistant Cylindrical and Polar Stereo Projection All products are in HDF5 format. GCOM-W1 Processing Levels

10 Calibration/Validation Validation by utilizing the existing observation networks: – Radiosondes and GPS networks, SST and sea surface wind speed from various buoy system, Ground-based precipitation radar networks, Snow depth and other surface measurements by meteorological agencies, etc. Specific field campaigns/monitorings – Soil moisture test sites such as Mongolia, Thailand, and CEOP sites including Australia Murray-Darling Basin, and Snow depth test site in Yakutsuk. Potential interaction with other missions – SMOS and SMAP for soil moisture, GPM GV collaboration for precipitation.

11 -New AWS testing in Metrological Institute since the beginning of June, untill September - After test, will install to Murry Darling Basin, north-west part of Melbourne, in Australia Calibration/Validation (new tool)

12 Next PI meeting ・ Plan Around December or January in Tokyo, together with other project,GCOM-C, TRMM/GPM, EarthCARE, setting crosscutting discussion like the last year, (only plan, not discussed enoungh, not approved) choices are - Just after 3 rd RA selection, around September or October, 3 rd RA researhers only, introducing work plans each other. -Place ( Tokyo, or western part of Japan because of problems of reactors and radiation.)

13 AMSR-E HW Recent Trend (as of 21 st,June) Amplitude are a little bigger than before (pink) (Light blue) (yellow) (light green)

14 The following problem are because of aging - The antenna torque has been unstable than before - 89GHz-B Detector’s output voltage will reach upper limit soon ( expected, around this December) To make life longer - The operation to make the dynamic range of Tb a little narrow => details are reported EOC/MELCO AMSR-E HW information