ATEC BRAC Update 12 May 11 81 Days Remain To BRAC End-Date 15 Sep 126 Days Remain To ATEC Ready Date 1 Aug (T) Provide our employees with BRAC execution.

Similar presentations


Presentation on theme: "ATEC BRAC Update 12 May 11 81 Days Remain To BRAC End-Date 15 Sep 126 Days Remain To ATEC Ready Date 1 Aug (T) Provide our employees with BRAC execution."— Presentation transcript:

1 ATEC BRAC Update 12 May 11 81 Days Remain To BRAC End-Date 15 Sep 126 Days Remain To ATEC Ready Date 1 Aug (T) Provide our employees with BRAC execution & planning update (P) To keep all informed of ongoing actions so that we remain synchronized with minimal impact to mission.

2 ATEC BRAC Status 287 Civilian Positions/221 ToF Letters 136 Completed ToFs 31 pending moves –May: 2 –June: 5 –July: 7 –August: 13 –September: 4 5 personnel w/overseas rights 68 Departures –15 PPP placements –44 accepted another position –9 retired 47 Declinations –29 registered –1 pending registration –1 pending resignation –16 pending retirements 2 2

3 HQ ATEC & AEC BRAC Results 3 3 Changes from Last Week Farley Jones departed; PPP position Report date for Linda Terres extended to 1 Sep 11 TotalHQAEC Accept3616%2419%1213% Decline4721%3225%1516% NCR Civ8337%5643%2729% Accepted Another Job4320%2116%2325% PPP Placed157%119%44% Retired94%22%78% Departures6731%3426%3437% ToF Completed7132%3930%3234% Total221100%129100%93100%

4 New HQs Build Update  Glass Atrium Installed  Interior Atrium Stairs & Crosswalk Installed  1 st & 2nd Floor Dry-Wall Complete  Staircase Installed  All Dry Wall / Paint Complete  Freight Elevator Complete  Furniture /Flooring Installation Current Construction Status Working Change in Beneficial Occupancy Date ACSIM Tracking – 19 Day Slip Furniture Contract Awarded-install 4 May-29 June Case – Goods on schedule ACSIM Tracking – Ready Date Implications IT-Security Synchronization Contracts (e.g. IT Vendor, ADT) As of 7 Mar 11 ATEC Ready Date: 1 Aug 11

5 Summary ATEC HQs Bldg 93% complete, TRD is 1 August 11 Furniture being installed ( 4 May -29 June 11) As of 4 April majority of ATEC - Alexandria Workforce at APG: 30 personnel remain in Alexandria Two-Phase Move : Phase 1: Oct 10 through 4 April 11(Move to APG) Phase 2: 5 April through 15 Sep 11 (Move to Hqs Bldg) Weekly Planning/Coordination/Execution Meetings NCR OPS Cell - close out IMP/PCIV; APG Team - APG 5 5


Download ppt "ATEC BRAC Update 12 May 11 81 Days Remain To BRAC End-Date 15 Sep 126 Days Remain To ATEC Ready Date 1 Aug (T) Provide our employees with BRAC execution."