Presentation is loading. Please wait.

Presentation is loading. Please wait.

Estimating PS&E – Plans, specifications and estimate 1.

Similar presentations


Presentation on theme: "Estimating PS&E – Plans, specifications and estimate 1."— Presentation transcript:

1 Estimating PS&E – Plans, specifications and estimate 1

2 Types of Estimates Ball-Park (Planning phase) Preliminary (Design Report/EIS) Detailed (PS&E---Detailed Design) 2

3 Estimate Quality Good book-keeping Accurate backup of quantities Familiarity w/ project Experience 3

4 4

5 Estimating Procedure List all item numbers-plans and similar plans Estimate quantities and prepare a backup for each item # Assign prices to each item (WAIPR) Lump sum price analysis Summary of quantities Add contingency Summarize final costs 5

6 Item Numbers Referenced to spec book Examples: ◦ 201.07 Clearing and Grubbing ◦ 203.xxxx Grade and Reshape Ditches ◦ 304.xx Subbase ◦ 610.0203 Establish Turf ◦ 634.01 Survey and Stakeout *Special specifications—General or Special (must be approved) 6

7 Units Unit abbreviationsDefinition LSLump Sum EAEach CYCubic Yard SYSquare Yard LFLinear Feet TNTon MOMonth 7

8 Units-Metric Unit abbreviationsDefinition CMCubic Meters SQMSquare meters MTMetric Ton KGKilograms MMeters 8

9 Specifications https://www.dot.ny.gov/main/business- center/engineering/specifications https://www.dot.ny.gov/main/business- center/engineering/specifications 9

10 Pay Item Catalog https://www.dot.ny.gov/pic 10

11 Weighted Average Item Price Report (WAIPR) https://www.dot.ny.gov/divisions/engineering/design/dqab/waipr 11

12 Special Spec Repository https://www.dot.ny.gov/spec-repository-us/ 12

13 Contingency Added to estimate to account for unknowns Usually a percentage of final cost 13

14 Cost Estimate Example Item #DescriptionUnitQTYPriceSubtotal 201.0601Clear & GrubLS1.0$12,500.00 203.0100Earth Cut & EmbCY14,545.0$12.00$174,540.00 10209.0100Bale DikesLF42.0$7.50$315.00 403.1100Asph Base CourseTN6392.0$38.00$242,896.00 603.730324” RCP End SecEA4.0$700.00$2,800.00 637.0701OfficeMO6$1,000.00$6,000.00 645.2140Traffic SignEA8$170.00$1,360.00 14

15 Backup for Estimate Example ITEM 640.0102 (White Paint Reflective Paint Stripes) 2 Shoulder Stripes Sta 26+44 to Sta 30+92 2*448’ = 896’ Say 900’ 15

16 Asphalt – English Tons.06865 Tons per Cubic Foot (Base).07525 Tons per Cubic Foot (Binder).07265 Tons per Cubic Foot (Top-6F) Old Marshall Design New Superpave????? 16

17 Lump Sum Price Analysis Estimate for items paid as a “Lump Sum” Includes: ◦ Labor ◦ Materials ◦ Equipment ◦ Rental costs ◦ Profit and Overhead Typical lump sum items: ◦ Clearing and Grubbing ◦ Survey and Stakeout ◦ Temporary Traffic Signals 17

18 Lump Sum Analysis Example Item 619.13 (Temporary Traffic Signal) Labor Costs ◦ Backhoe Operator-$30.05/hr ◦ Electrician-$32.99/hr ◦ Laborer-$22.95/hr Prevailing Wages http://wpp.labor.state.ny.us/wpp/publicViewPWChanges.do?method=showIt http://wpp.labor.state.ny.us/wpp/publicViewPWChanges.do?method=showIt Installation and Removal of Temp. Poles ◦ 1 Backhoe Operator $30.05/hr * 16 hours = ◦ 2 Laborers @ $22.95/hr * 16 hours = Installation and Removal of Temp. Signal Heads ◦ 1 Electrician @ $32.99/hr * 16 hours = ◦ 2 Laborer@ $22.95/hr * 16 hours = Installation and Removal of Controller ◦ 1 Electrician @ $32.99 * 16 hours = ◦ 1 Laborer @ $22.95 * 16 hours = 18

19 Lump Sum Analysis Example-Cont. Item 619.13 (Temporary Traffic Signal) Materials ◦ Temporary Poles 4 @ $1,300.00 each ◦ Temporary Signal Heads 4 @ $250.00 each ◦ Controller, Fixed Time 1@ $1,000.00 ◦ Misc. Hardwire and Wire $1,000.00 Equipment (Installation and Removal) ◦ 1 Bucket Truck @ $18.00/hr * 24 hours ◦ 1 Backhoe @ $35.00/hr * 24 hours Profit and Overhead (20%) 19

20 Estimate Shares Highway Bridge Utilities Different Counties 20

21 Engineer’s Estimate Quantities included in plans Engineer’s estimate not given to contractor Prices not available to contractor—each contractor provides their own bid Lowest bidder gets the contract 21

22 22

23 23


Download ppt "Estimating PS&E – Plans, specifications and estimate 1."

Similar presentations


Ads by Google