1 Rand Water Parliamentary Portfolio Committee Water Affairs & Forestry
Presentation of Annual Report

2 Snapshot Revenue - R4,119 bn (R3,672 bn~2006)
Total Assets - R 6,257 bn (R5,387 bn~2006) All Rand Water financial reports are unqualified Staff Employed Corporate ISO 9001:2000 accredited All plants ISO accredited

3 Rand Water Geographical Footprint
Consumers million Supply Area km2 Total Pipeline Length km Total Number of Reservoirs - 54

4 Performance Highlights
Profit Revenue Cash generated from operations Sales volume 25.3% 12.2% 17.8% 2.7%

5 Performance Highlights
Customer Satisfaction Index: 76% 76% Training spend (as % of Total Payroll) 7% 7% Employment equity at management level 75% 64% BEE spend % 60%

6 Corporate Social Involvement
Water related and non-water related The focus area and allocation of funds ( ~ Approx R2.5 m) Focus Area Type of Support Spent HIV/AIDS Home based care R Special needs institutions Training equipment R People with Disabilities Resource provision R Women Empowerment Shelter provision R Care of the Elderly Support to institutions R Partnerships Partnering with organisations R Health Grants to organizations R

7 Corporate Social Involvement
This is water related activities in partnership with different stakeholders Summary of Job Creation and Local Supplier Support Gender Jobs Created % Male 224 48 Female 267 52 Total 513 100 Project funds spent on local labour and suppliers Items Funds Spent % Traditional Suppliers 4 PDI Suppliers 52 Total 100

8 Corporate Social Involvement
This is water related activities in partnership with different stakeholders Project Description Area Project Value Funder Water pipeline Reinforcement Winterveldt R CT Winterveldt Sanitation R Emfuleni Leaks Repairs Bekkersdal R Emfuleni, RWF Tshwane- Leaks Repairs Mamelodi R CT, RWF DACEL-Alien Plant Removal Elandsfontein R GDACE Mogale City R KZN Donga Rehabilitation Bergville R DEAT HIV/Aids Mainstreaming National R DWAF Water Sector Monitoring R Bushbuckridge Water Supply Kumani Village BBR Rand Water Golden Gate Freestate R RW Siluma Wetland Gauteng R RWF Blesbokspruit Nigel R Sri Lanka Water Service Support Sri Lanka R TOTAL R

9 Energy Crisis Impact Request by Eskom to cut usage by 10%
Active engagement with Eskom: Cooperation but on our terms Water quality and reliability problems Active/Dynamic pumping and reservoir management – to encourage savings Essential services exemption Still finding ways of saving on electricity usage – energy efficiency programme

10 CONSULTATION SALGA: National Treasury: Use of surplus to reduce tariff
Supported Capital Programme Value chain sustainability National Treasury: Inflation target Explore feasibility of further reduction

11

12 Allocation of surplus : Project Overview
Forecast Cashflow Significant Capital Projects (R m) Jun-08 Jun-09 Jun-10 Jun-11 Jun-12 A Augment infrastructure 5720 420 439 395 470 529 B Renovation & replacement 1370 148.6 271 344 323 310 C Total 7090 569 710 739 793 839

13 Allocation of surplus Central to our operations - pipelines
Generally very old – mostly in excess of 80 years Significant amounts being spent on augmentation and refurbishment to ensure operational sustainability Increased expenditure due to escalation Reserves will be used to smooth the tariff and cater for new schemes

14 Projects plan - Process Steps
Additional water supply scheme due to development. Planned programme of renovation to existing infrastructure Analyses of latest estimates of future water demand growth patterns depending on development statistics.

15 Projects plan - Process Steps
Condition assessment of current infrastructure. Annual infrastructure recommendations combine : - extra capacity for 15 year demand growth - renovation to maintain existing capacity

16 How are costs determined
Estimates for these projects are done by escalating similar work already completed. By enquiring from the market what the current costs for the work are.

17 Water Quality Full adherence to SANS 0241 (based on a WHO standards)

18 Water Quality - Cont

19 Fit with overall DWAF Strategy
Emfuleni Sanitation Delmas involvement Western Highveld Involvement

20 Challenges : Sanitation & Environmental Pressures
85 per cent of local municipalities within Rand Water’s catchment area have challenges with meeting DWAF’s effluent management standards This increases Rand Water’s purification cost This ultimately places greater pressure on Rand Water’s tariff increments One solution is to roll out the Emfuleni Regional Sanitation Scheme