Presentation is loading. Please wait.

Presentation is loading. Please wait.

LHC CMS Detector Upgrade Project US CMS Trigger Upgrade Proposal Wesley Smith, U. Wisconsin Fermilab Directors’ Review 16 July 2013 Fermilab Director's.

Similar presentations


Presentation on theme: "LHC CMS Detector Upgrade Project US CMS Trigger Upgrade Proposal Wesley Smith, U. Wisconsin Fermilab Directors’ Review 16 July 2013 Fermilab Director's."— Presentation transcript:

1 LHC CMS Detector Upgrade Project US CMS Trigger Upgrade Proposal Wesley Smith, U. Wisconsin Fermilab Directors’ Review 16 July 2013 Fermilab Director's Review -- US CMS Trigger Upgrade 1Wesley Smith, 16 July 2013

2 LHC CMS Detector Upgrade Project Wesley Smith, 16 July 2013 Fermilab Director's Review -- US CMS Trigger Upgrade 2 L1 Trigger Upgrades: Detectors Electromagnetic Calorimeter Electromagnetic Calorimeter Hadron Calorimeter Hadron Calorimeter Muon Detectors Muon Detectors 401.04

3 LHC CMS Detector Upgrade Project  Trigger TDR Status, Overall Goals  Overview of Trigger Upgrade Design  Muon Trigger Upgrade  Calorimeter Trigger Upgrade  Overview of Cost & Schedule Wesley Smith, 16 July 2013 Fermilab Director's Review -- US CMS Trigger Upgrade 3 Outline

4 LHC CMS Detector Upgrade Project L1 Upgrade TDR  Final presentation to LHCC was Tuesday June 11th  Public version of the TDR here: https://cds.cern.ch/record/1 556311  Given approval, although still awaiting final formal LHCC write-up Wesley Smith, 16 July 2013 Fermilab Director's Review -- US CMS Trigger Upgrade 4

5 LHC CMS Detector Upgrade Project  Trigger rates are driven by the increase in luminosity, the center- of-mass energy, & by higher Pile-Up  Detector readout systems limit Level-1 trigger output rate to 100 kHz, latency to 4 μsec. LHC beams collide every 25 ns.  Mitigate by improving e/γ isolation, τ id, μ p T resolution, μ isolation, jets with PU subtraction & L1 menu sophistication  Increase system flexibility with high bandwidth optical links and large FPGAs, and standardize on μTCA telecom standard  Build and commission upgrade in parallel with current trigger system to safeguard physics, decouple from LHC schedule  Overall design:  Two-layer calorimeter trigger with tower-level precision and PU subtraction  Integrated muon trigger combining all CSC, DT & RPC systems in track-finding Fermilab Director's Review -- US CMS Trigger Upgrade 5 L1 Trigger Upgrade – overview Wesley Smith, 16 July 2013

6 LHC CMS Detector Upgrade Project Final Overall Upgrade Scheme Fermilab Director's Review -- US CMS Trigger Upgrade 6Wesley Smith, 16 July 2013

7 LHC CMS Detector Upgrade Project Muon Trigger Transition Wesley Smith, 16 July 2013 Fermilab Director's Review -- US CMS Trigger Upgrade 7  Install fully parallel and higher bandwidth optical path for CSC  New CSC MPC mezzanine cards installed in cavern during LS1  Alleviates bottleneck and send all segments from each CSC (robustness to PU and collimated signals)  Build up new Track Finder in 2015 and commission in parallel, ready by 2016  Endcap hardware design is proposed by CMS to be used for all muon regions: endcap, barrel, and overlap Old systemNew system

8 LHC CMS Detector Upgrade Project Muon Trigger WBS Detail Wesley Smith, 16 July 2013 Fermilab Director's Review -- US CMS Trigger Upgrade 8 → Calorimeter Trigger

9 LHC CMS Detector Upgrade Project 401.04.03 EMU Trigger Upgrade CavernCounting Room μTCA: Advanced Mezzanine Cards from Telecommunications Computing Architecture (commercial telco, see backup slide) Fermilab Director's Review -- US CMS Trigger Upgrade 9Wesley Smith, 16 July 2013 401.04.03.03 MPC-EMUTF Optical Fibers 401.04.03.02 Muon Port Card Mezzanine 401.04.03.04 Endcap Muon Track-Finder 401.04.03.05 EMUTF Infrastructure 401.04.03.06: Muon Sorter Trigger MotherBoard Data MotherBoard Clock&Control Sector Processors Clock & Control Muon Sorter

10 LHC CMS Detector Upgrade Project 401.04.03.02 Muon Port Card Upgrade (Rice) x 60 + 20 spares Fermilab Director's Review -- US CMS Trigger Upgrade 10  Use the existing MPC main board  Backplane interface to TMB remains unchanged  3 original optical links are still available  New mezzanine card with new FPGA and new links Wesley Smith, 16 July 2013 (60 needed + 15 spares + 5 test setups = 80)

11 LHC CMS Detector Upgrade Project 401.04.03.04: EMU Track-Finder Upgrade (U. Florida) Wesley Smith, 16 July 2013 Fermilab Director's Review -- US CMS Trigger Upgrade  Muon Track Finder processor: MTF7  13 needed + 4 spares + 3 test setups = 20  Optimized for maximum input from muon detectors (84 input links, 24 output links)  Dual card with large capacity for RAM (~1GB) to be used for p T assignment in track finding  Current prototype based on Virtex 6 FPGA is undergoing final tests (RLDRAM memory access)  Virtex 7 FPGA design is ~75% done, expected late 2013 Back: Core FPGA card with P T LUT mezzanine Front: Optics card 11

12 LHC CMS Detector Upgrade Project 401.04.03.05: EMUTF Infrastructure (U. Florida) Fermilab Director's Review -- US CMS Trigger Upgrade 12 Not US* *Processing the resulting tracks with RPC or CSC hits is a US responsibility Wesley Smith, 16 July 2013 401.04.02.04 Endcap Muon Track-Finder 401.04.02.06: Muon Sorter

13 LHC CMS Detector Upgrade Project  Provide immediate CSC Trigger improvement in 2015  Provide optical path to new μTCA Global Muon Trigger from old CSCTF from each endcap  Allows independent upgrade of individual endcaps  Add isolation to endcap muons from old CSCTF with a new mezzanine card on the old muon sorter to send an optical path to 2015 calorimeter trigger initial upgrade  Analogous to MPC upgrade: Wesley Smith, 16 July 2013 Fermilab Director's Review -- US CMS Trigger Upgrade 13 401.04.03.06: Intermediate Sorter Upgrade (Rice)

14 LHC CMS Detector Upgrade Project Upgrade Cal. Trig. Layer 1 & 2 Hardware US: UK: Wesley Smith, 16 July 2013 Fermilab Director's Review -- US CMS Trigger Upgrade 14 Vienna:

15 LHC CMS Detector Upgrade Project Calorimeter Trigger WBS Detail Wesley Smith, 16 July 2013 Fermilab Director's Review -- US CMS Trigger Upgrade 15 ← Muon Trigger M&S paid by CMS-France

16 LHC CMS Detector Upgrade Project  Upgraded HCAL Readout & Trigger Electronics (μHTR) is after split that sends data to old electronics (HTR)  μHTR supplies TP to upgrade cal. Trigger, HTR continues to send to present cal. Trigger  ECAL Trigger Concentrator Cards (TCC) are not upgraded, instead their mezzanines with trigger serial links are replaced (built by Lisbon):  Optical Serial Link Board oSLB replaces single copper link to current Regional Calorimeter Trigger (RCT – U. Wisc.) with two optical links (WBS 401.04.04.06)  One optical link to optical Receiver Module (oRM) on RCT (WBS 401.04.04.05) o Replaces copper Receiver Module  One optical link to input of Upgraded Calorimeter Trigger: CTP7 Card  574 oSLB’s & oRM’s with Fibers installed in 2014  French Contribution to Calorimeter Trigger (no US Upgrade Funds)  Presently oSLB & oRM in final prototype stage  oSLB:oRM: Wesley Smith, 16 July 2013 Fermilab Director's Review -- US CMS Trigger Upgrade 16 HCAL & ECAL Trigger Primitives

17 LHC CMS Detector Upgrade Project Calo. Trigger Upgrade in Parallel: Split inputs from ECAL & HCAL HCAL Energy (HTR) ECAL Energy (TCC) Regional Calo Trigger Global Calo Trigger EM candidates Region energies HF Energy (μHTR) HCAL Energy (μHTR) Layer 1 Calo Trigger Layer 2 Calo Trigger Current L1 Trigger System Upgrade L1 Trigger System oSLB oRM  Install optical SLB and optical RM mezzanines during LS1  Install HCAL optical splitters during LS1 or YETS  Install HCAL backend μHTR cards for input to new trigger  Install HCAL frontend electronics after LS2 (finer long. segmentation) Wesley Smith, 16 July 2013 Fermilab Director's Review -- US CMS Trigger Upgrade 17 US UK US UK HCAL Optical Splitters Stage HCAL uHTR & assoc. Cal. Trigger Cards

18 LHC CMS Detector Upgrade Project 401.04.04.02: Calorimeter Trigger Processor Virtex-6 Prototype Board (CTP-6) – U. Wisconsin Back End FPGA XC6VHX250T/ XC6VHX380T Front End FPGA XC6VHX250T/ XC6VHX380T Avago AFBR- 810B Tx Module 4X Avago AFBR-820B Rx Module MMC Circuitry JTAG/USB Console Interface Mezzanine Power Modules Dual SDRAM for dedicated DAQ and TCP/IP buffering 12x Multi Gig Backplane Connections Wesley Smith, 16 July 2013 Fermilab Director's Review -- US CMS Trigger Upgrade 18 36 total + 8 spares + 2 test setups = 46

19 LHC CMS Detector Upgrade Project 401.04.04.02: Calorimeter Trigger Processor Final Version: Virtex-7 (CTP-7) – U. Wisconsin Replace 2 Virtex-6s with a Virtex 7 for processing+ZYNQ for embedded TCP/IP endpoint 30A, 1V power module for FPGA logic core 3x CXP Pluggable modules for 36 Tx + 36 Rx 10G optical links 2x AFBR-820 modules for 24 Rx 10G optical links Simpler design to execute than the CTP-6 36 total + 8 spares + 2 test setups = 46 Virtex-7 VX690T FPGA ZYNQ XC7Z03 0 EPP 1.5V Supply 2.5V Supply 3.3V Supply 1V 30A Supply CXP Module 12Tx + 12 Rx CXP Module 12Tx + 12Rx CXP Module 12Tx + 12 Rx 12X Rx 12X Rx (CTP-6 CAD View) Wesley Smith, 16 July 2013 Fermilab Director's Review -- US CMS Trigger Upgrade 19

20 LHC CMS Detector Upgrade Project 401.04.04.03: Crosspoint IO Card: provides crate interconnections – U. Wisconsin Controller (MMC and link mgmt) 4X Avago AFBR-79EQDZ QSFP+ Module Positions 4x4 Lane Bidirection al Multi Gig Backplane Connectio ns Backplane Rx/Tx Redriver ICs (top and bottom sides) Wesley Smith, 16 July 2013 Fermilab Director's Review -- US CMS Trigger Upgrade 20 (2/crate x 3 crates = 6 + spares)

21 LHC CMS Detector Upgrade Project 401.04.04: CTP Infrastructure: Vadatech VT894 Crate Test Setup BU AMC13 Vadatech MCH UW CTP-6 TTC Downlink UW Aux Wesley Smith, 16 July 2013 Fermilab Director's Review -- US CMS Trigger Upgrade 21 (Final system: 3 crates w/ 12 CTP7 ea. + 2 test setups + spare = 6) U. Wisconsin designed backplane with dense card interconnects manufactured & installed in commercial Vadatech VT892 Crate available in Vadatech Catalog

22 LHC CMS Detector Upgrade Project  Goal (Original):  Provide readout of original RCT descoped during construction project  Present readout through GCT input buffer not workable with trigger evolution  Uses connection to a single CTP6 prototype or CTP7 card for DAQ readout  optical Receiver Summary Card (oRSC) paid by DOE Nuclear  VME Slave Interface Card  Fits in current RCT Crates (1 per crate)  18 Cards in 2015 System  Receives RCT Jet Sum Card Output to GCT on Copper “SCSI” Data Cables  Provides direct optical input to GCT o Bypassing old optical conversion cards  Planned use for Heavy Ion Triggers  Prototype under test   Multiple optical outputs provide:  Inputs for upgrade calorimeter trigger & parallel operation of old & new trigger wherever ECAL & HCAL electronics not available in 2015 Wesley Smith, 16 July 2013 Fermilab Director's Review -- US CMS Trigger Upgrade 22 Calorimeter Trigger Risk Mitigation

23 LHC CMS Detector Upgrade Project Evolution: Partial Upgrade in 2015 Wesley Smith, 16 July 2013 Fermilab Director's Review -- US CMS Trigger Upgrade 23 Layer 2 Calo Trigger HCAL energy Regional Calo Trigger Global Calo Trigger HF energy oRSC Layer 2 Calo Trigger oRM ECAL energy Layer 1 Processors oSLB ECAL & HF Clusters Half-tower position 4x4 E+H Clusters 2x1 E+H Clusters 2-bit region ID Layer 2 Processors Muon Jets & Sums eGammaTau Heavy Ion Spare RCT RO + Testing GCT fallback and Minimal Stage-1 fallback remains available With just a fraction of final cards or even prototypes, derive many benefits of full upgrade, incl. muon isolation Uses reprogrammed RCT clusters with improved algorithms in Layer-2 Also, brings in all the power of finer grain HF using “Slice Test” of Layer-1 & 2 Improved PU subtraction, Isolation Calculation (e/γ/τ/μ) & Half-tower Position Resolution US Items: oRSCs, oSLB/oRM commissioning CTP Layer 1 Processors RCT RO+Testing CTP UK Items: MP7 Layer 2 Processors 36  HTRs 2 CTP7s  9 CTP7s Add to bring in finer grain EM clusters 2 CTP7s 4 MP7s

24 LHC CMS Detector Upgrade Project  CTP7 M&S: no HB/HE Backend until 2016  Delay purchase of 34 CTP7 cards until FY15  Use 12 CTP7 Cards w/prototypes as additional spares & for test setups.  Connected as shown on previous slide  EMU CSCTF M&S: one endcap in 2015 & other in 2016  Commission & test one endcap thoroughly so 2 nd can be integrated quickly  Delay spares & use prototypes for spares, test setups  Compatible with Global Muon Trigger using different Endcap inputs  Stages and Content: Wesley Smith, 16 July 2013 Fermilab Director's Review -- US CMS Trigger Upgrade 24 Trigger Staging

25 LHC CMS Detector Upgrade Project  Working prototypes for all major cards exist & have passed tests  Production quotes exist for all critical parts with confirmed delivery upon order  Upgrade is based upon common μTCA hardware platform also used by HCAL & other CMS systems  Common hardware components across subsystems: Virtex-7 FPGA, multi-gigabit optical links  Many handles to facilitate testing – test-pattern injection, spy-buffer readout as well as test stands  Upgrade trigger project replaces existing trigger hardware built by the same team → interfaces well understood  Same team wrote software & firmware for existing trigger system → scope & requirements well understood  Requirements are frozen in approved Trigger TDR  System is commissioned & operated in parallel with existing trigger Wesley Smith, 16 July 2013 Fermilab Director's Review -- US CMS Trigger Upgrade 25 Technical Feasibility

26 LHC CMS Detector Upgrade Project Trigger L2 Manager: Wesley Smith Deputies: Darin Acosta, Sergo Jindariani Muon Trigger L3 Manager: Darin Acosta Muon Port Card & Sorter: Paul Padley Muon Track-Finder: Ivan Furic Calorimeter Trigger L3 Manager: Sridhara Dasu CERN Integration: Pam Klabbers Wesley Smith, 16 July 2013 Fermilab Director's Review -- US CMS Trigger Upgrade 26 Trigger Project Organization

27 LHC CMS Detector Upgrade Project  W.S. (U. Wisconsin)  CMS Trigger Project Manager 1994-2007,  Trigger Coordinator 2007 – 2012  US CMS L2 Trigger Project Manager 1998 – present  Darin Acosta (U. Florida)  CMS Trigger Project Manager 2012-13  EMU Track-Finder, US CMS Trigger, 1998- present  Sridhara Dasu (U. Wisconsin)  US CMS L3 Manager for Calorimeter Trigger, 1998 – present  Author of original & upgrade cal. trig. Algorithms 1994 – present  Pam Klabbers (U. Wisconsin)  CMS Regional Calorimeter Trigger Operations Manager (more than a decade on RCT project)  CMS Deputy Trigger Technical Coordinator  Ivan Furic (U. Florida)  CMS CSC muon trigger maintenance & operations 2010-11  CMS CSCTF Upgrade leader  Paul Padley (Rice U.)  US CMS EMU Project Manager 2006-2012  EMU Port Card, Clock Card, Sorter, 1998 – present Wesley Smith, 16 July 2013 Fermilab Director's Review -- US CMS Trigger Upgrade 27 Trigger Management CMS Experience

28 LHC CMS Detector Upgrade Project  Tom Gorski (U. Wisconsin) – Calorimeter Trigger  Over a decade of engineering on the CMS Calorimeter Trigger  Alex Madorsky (U. Florida) – Muon Track-Finder  Over a decade of engineering on CMS Trigger, EMU, CSCTF  Mike Matveev (Rice U.) – Muon Port Cards & Sorter  Over a decade of engineering on CMS Trigger, EMU, Port Cards, Sorter  Mathias Blake (U. Wisconsin) – Cal. Trig. Firmware  New to project  5 years Applications Engineer at Xilinx, 2 years FPGA Engineer at DRS Technologies, 3 years FPGA Design Engineer at Dolby Labs Wesley Smith, 16 July 2013 Fermilab Director's Review -- US CMS Trigger Upgrade 28 CMS Trigger Engineering Experience

29 LHC CMS Detector Upgrade Project  M&S:  Parts based on quotes & prototype purchases  Ordering times based on experience with prototype orders  Board cost & delivery times based on prototype boards  Assembly cost & delivery times based on prototype boards  EDIA:  Labor Hours based on experience with corresponding tasks done for prototypes and on experience in delivering the original CMS trigger system (done by the same people & groups).  Labor costs based on actual labor rates of all of the individuals who are now working on the project  Contingency:  Follows US CMS Contingency rules Wesley Smith, 16 July 2013 Fermilab Director's Review -- US CMS Trigger Upgrade 29 C&S Methodology

30 LHC CMS Detector Upgrade Project Fermilab Director's Review -- US CMS Trigger Upgrade Base Cost & Contingency in AY K$ 30Wesley Smith, 16 July 2013 401.04 Cost Estimate with Contingency

31 LHC CMS Detector Upgrade Project Fermilab Director's Review -- US CMS Trigger Upgrade 31 Schedule/Milestones Wesley Smith, 16 July 2013  The project completes at the end of FY16  FY14:  Launch production of trigger electronics 1QFY14  Deliver on-detector muon trigger electronics to CERN: 3QFY14  Deliver Stage 1 calorimeter layer 1 & muon track-finder electronics to CERN: 4QFY14  FY15:  Test operation of trigger calorimeter and muon trigger electronics*: 2QFY15 (*except muon sorter)  Deliver Stage 2 calorimeter layer 1 & muon track-finder electronics to CERN: 2QFY15  Deliver Muon Sorter electronics to CERN: 3QFY15  Test Operation of Muon Sorter electronics: 4QFY15  FY16:  Test high luminosity capability of endcap muon trigger electronics: 4QFY16  Test high luminosity capability of calorimeter trigger electronics: 4QFY16

32 LHC CMS Detector Upgrade Project Fermilab Director's Review -- US CMS Trigger Upgrade 32 Base Cost = AY $K (No Contingency) Wesley Smith, 16 July 2013 401.04: Trigger Resource Profile

33 LHC CMS Detector Upgrade Project  Senior Engineer becomes unavailable  Hire new engineer, subcontract to consulting firm, use FNAL engineer  Funding is delayed  Commission with prototypes and/or fewer production boards  Software or Firmware does not meet requirements  Hire extra expert effort to recover schedule and help personnel  Boards are delayed (design, manufacture or testing)  Hire extra effort to speed up testing schedule  Vendor non-performance  Acquire spending authority to use alternative vendors (while original funds are being unencumbered).  Input or output electronics (non-trigger) delayed  Built in capabilities of trigger electronics provide signals for their own inputs & outputs  Overall Risk Mitigation Strategy:  Continue to provide fully operational current trigger system in parallel with upgrade commissioning  Partial operation of the upgrade systems provide tangible benefits from 2015 onwards Wesley Smith, 16 July 2013 Fermilab Director's Review -- US CMS Trigger Upgrade 33 Overall Trigger Risks

34 LHC CMS Detector Upgrade Project  Safety: follows procedures in CMS-doc-11587, FESHM  L2 Manager (W.S.) responsible for applying ISM to trigger upgrade. o Under direction of US CMS Project Management  Fermilab employees and CMS collaborators working at Fermilab & CERN receive training in accordance with Fermilab & CERN policies. Personnel conducting work at collaborating institutions are trained in accordance with the policies of those institutions.  Regular US CMS Upgrade Mgm’t meetings review work activity, schedule, costs, hazards, risks and controls.  Quality Assurance: follows procedures in CMS-doc-11584  Regularly evaluate achievement relative to performance requirements & appropriately validate or update performance requirements & expectations to ensure quality.  QA: Equipment inspections & verifications; Software code inspections, verifications, & validations; Design reviews; Baseline change reviews; Work planning; and Self-assessments.  Graded Approach:  Apply appropriate level of analysis, controls, and documentation commensurate with the potential to have an environmental, safety, health, radiological, or quality impact.  Four ESH&Q Risk levels are defined & documented in CMS-doc-11584. Wesley Smith, 16 July 2013 Fermilab Director's Review -- US CMS Trigger Upgrade 34 Trigger ESH&Q

35 LHC CMS Detector Upgrade Project  C&S understood since prototypes for all major cards have been built & have passed tests  C&S based on experience of the same team that built original CMS calorimeter & muon trigger systems  Hardware is based upon common μTCA hardware platform also used by HCAL & other CMS systems  Same team wrote software & firmware for existing trigger system → scope & requirements well understood  Requirements are frozen in approved Trigger TDR  Schedule is robust because it always provides a working trigger at each stage with parallel operation of old & new trigger systems, commissioning & testing of new system during data- taking (with data) & evolution to final system while providing immediate availability of improved trigger in 2015 Wesley Smith, 16 July 2013 Fermilab Director's Review -- US CMS Trigger Upgrade 35 Cost & Schedule Understanding

36 LHC CMS Detector Upgrade Project  Develop a plan prior to the CD-1 review for procurement of components that need to be installed prior to the end of LS1.  These components are the Muon Port Card Mezzanines and MPC- EMUTF Optical Fibers that must be installed in the collision hall during LS1.  These components are being moved to the operations program so they can be purchased in 2013.  Incorporate the missing information identified within comment section into the CDR prior to the CD-1 review.  This has been done and the CDR has been revised Wesley Smith, 16 July 2013 Fermilab Director's Review -- US CMS Trigger Upgrade 36 Response to Recommendations from May Review

37 LHC CMS Detector Upgrade Project  Trigger Upgrade is technically feasible since based on working prototypes, & built by the same team that built original CMS Calorimeter & Muon triggers.  Trigger Upgrade can be accomplished within Cost & Schedule since based on working prototypes and experience in building the original CMS Calorimeter & Muon triggers.  Risks are understood and familiar due to team experience – risk is mitigated by parallel operation of existing and upgraded calorimeter systems  Plan to complete prototyping and begin production when approved. Wesley Smith, 16 July 2013 Fermilab Director's Review -- US CMS Trigger Upgrade 37 Conclusions

38 LHC CMS Detector Upgrade Project BACKUP Wesley Smith, 16 July 2013 Fermilab Director's Review -- US CMS Trigger Upgrade 38

39 LHC CMS Detector Upgrade Project Calorimeter Trigger Components Wesley Smith, 16 July 2013 Fermilab Director's Review -- US CMS Trigger Upgrade 39 TypeNamePurpose TCCTrigger Concentrator CardExisting ECAL trigger primitives (TP) (FR) oSLBOptical Serial Link BoardTransmit ECAL TPs to RCT & CTP (PT)  HTR HCAL Trigger & DAQ BoardCreate and transmit HCAL TPs RCTRegional Calorimeter TriggerExisting trigger system oRMOptical Receiver ModulesReceive ECAL TPs on RCT oRSCOptical Regional Summary CardConvert and transmit RCT output CTPCompact Trigger ProcessorLarge FPGA w/ optical & backplane CIOXCompact IO cross-point switchIntra-crate sharing switch MP7Multipurpose ProcessorLarge FPGA w/ only optical links (UK)

40 LHC CMS Detector Upgrade Project TMT Calorimeter Trigger Upgrade Wesley Smith, 16 July 2013 Fermilab Director's Review -- US CMS Trigger Upgrade 40 Time-multiplexed architecture, calo data from an entire event processed by a single processor

41 LHC CMS Detector Upgrade Project Crate G Up to 12 Trigger Path Modules Trig Path 1 (MP7) 2x288-fiber patch panel (2x24×12-fiber optical ribbons in & out) Crate BCrate C CTP CIO-U CIO-L 6 x 8-fiber ribbons for Lateral Network (@ 4.8 Gbps) Trig Path 2 (MP7) Trig Path 3 (MP7) Trig Path 4 (MP7) Trig Path 5 (MP7) Trig Path 6 (MP7) HCALECALHCALECALHCALECAL Each 1 st -Level CTP7 Drives 2 fibers out to 6-12 Trigger Paths @ 9.6 Gbps Each Trigger Path MP7 rcvs 48 total 1 st -Level fibers @ 9.6 Gbps (2/region) To GT CTP CIO-L CTP CIO-U CIO-L CIO-U Crate A  Crate G Pipelined Calorimeter Trigger Upgrade Calorimeter Trigger Processor (CTP) Card Crosspoint I/O (CIO) Card Wesley Smith, 16 July 2013 Fermilab Director's Review -- US CMS Trigger Upgrade 41 Each Layer 2 processor calculates suite of trigger paths Layer 1 sends dedicated clusters to Layer 2


Download ppt "LHC CMS Detector Upgrade Project US CMS Trigger Upgrade Proposal Wesley Smith, U. Wisconsin Fermilab Directors’ Review 16 July 2013 Fermilab Director's."

Similar presentations


Ads by Google