Presentation is loading. Please wait.

Presentation is loading. Please wait.

Copyright © 2008 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin Chapter 5 Activity-Based Costing.

Similar presentations


Presentation on theme: "Copyright © 2008 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin Chapter 5 Activity-Based Costing."— Presentation transcript:

1 Copyright © 2008 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin Chapter 5 Activity-Based Costing

2 Copyright © 2008 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin Learning Objective 1

3 Traditional, Volume-Based Product-Costing System Aerotech produces three complex printed circuit boards referred to as Mode I, Mode II, and Mode III. The following information is obtained from company records: Aerotech produces three complex printed circuit boards referred to as Mode I, Mode II, and Mode III. The following information is obtained from company records:

4 Traditional, Volume-Based Product-Costing System Additional information includes: Manufacturing overhead is determined as follows

5 Traditional, Volume-Based Product-Costing System Budgeted manufacturing overhead $3,894,000 Budgeted direct-labor hours 118,000 = $33 per hour

6 Traditional, Volume-Based Product-Costing System With these product costs, Aerotech established target selling prices (Cost × 125%). 209.00 x 1.25

7 Copyright © 2008 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin Learning Objective 2

8 Activity Based Costing System (ABC) two- stage ABC systems follow a two- stage procedure to assign overhead costs to products. Assigning overhead to products is a difficult process. I agree!

9 Activity Based Costing System (ABC) ABC systems follow a two-stage procedure to assign overhead costs to products. Let’s begin by identifying our major activities. Stage One Identify significant activities and assign overhead costs to each activity in proportion to resources used.

10 Activity Based Costing System (ABC) Overhead assigned to activities are called “activity cost pools.” Stage Two Identify cost drivers appropriate to each activity and allocate overhead to the products. ABC systems follow a two-stage procedure to assign overhead costs to products.

11 Copyright © 2008 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin Learning Objective 3

12 Overhead Costs Total budgeted cost = $3,894,000 ActivityCostPools Machinery cost pool $1,212,600Setup $3,000Engineering $700,000Facility $507,400 Unit Level Batch Level Product- Sustaining Level Facility Level Identification of Activity Cost Pools Identification of Activity Cost Pools Activity must be done on each unit produced. Activityperformed on each batchproduced. Activities needed to support an entire product line Activity required in order for the production process to occur.

13 Receiving/Inspection cost pool $200,000 Material-Handling cost pool $600,000 Quality-Assurance cost pool $421,000 Packaging/Shipping cost pool $250,000 Machinery cost pool $1,212,600Setup $3,000Engineering $700,000Facility $507,400 Unit Level Batch Level Product- Sustaining Level Facility Level

14 Copyright © 2008 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin Learning Objective 4

15 Machinery Cost Pool Total budgeted cost = $1,212,600 Maintenance Depreciation Computer Support Lubrication Electricity Calibration Activitycostpool STAGE ONE Various overhead costs related to machinery

16 Calculate the pool rate Budgeted Machinery Costs $1,212,600 Budgeted Machine Hours 43,000 $28.20/hour $28.20/hour CostAssignment STAGE TWO = =

17 Calculation of total setup cost Setup Cost Pool Total budgeted cost = $3,000 Activitycostpool STAGE ONE

18 Calculate the pool rate Budgeted Setup Costs $3,000 Planned Production Runs 15 runs $200 per run $200 per run CostAssignment STAGE TWO = =

19 Various overhead costs related to engineering Engineering salaries Engineering supplies Engineering software Depreciation Engineering Cost Pool Total budgeted cost = $700,000Activitycostpool STAGE ONE

20 Allocate based on engineering transactions CostAssignment STAGE TWO Engineering Cost Pool Total budgeted cost = $700,000

21 Exh. 5-9 Various overhead costs related to general operations Plant depr. Plant mgmt. Plant maint. Property taxes Insurance Security Facility Cost Pool Total budgeted cost = $507,400Activitycostpool STAGE ONE

22 Exh. 5-9 Budgeted Facilities Cost $507,400 Budgeted Direct-Labor Hours 118,000 $4.30/hour $4.30/hour CostAssignment STAGE TWO = = Calculate the pool rate

23 Other Overhead Costs

24 $14.82

25 Product Cost from ABC These are the new product costs when Aerotech uses ABC.

26 Copyright © 2008 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin Learning Objective 5

27 Distorted Product Costs Both original and ABC target selling prices are based on (Cost × 125%). [$209.00 × 1.25][$183.44 × 1.25] The selling price of Mode I and II are reduced and the selling price for Mode III is increased.

28 Can you identify any problems Aerotech is likely to face as a result of this distortion? Traditional costing understates the cost of complex, low volume products. Distorted Product Costs

29 Two Key Points A large proportion of non- unit-level activities A unit-level cost driver, such as direct labor, machine hours, or throughput, will not be able to assign the costs of non-unit-level activities accurately. A large proportion of non- unit-level activities A unit-level cost driver, such as direct labor, machine hours, or throughput, will not be able to assign the costs of non-unit-level activities accurately. Product diversity When the consumption ratios differ widely between activities, no single cost driver will accurately assign the resulting overhead costs. Product diversity When the consumption ratios differ widely between activities, no single cost driver will accurately assign the resulting overhead costs.

30 Copyright © 2008 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin Learning Objective 6

31 Cost Drivers A characteristic of an event or activity that results in the incurrence of costs.

32 Cost Drivers A characteristic of an event or activity that results in the incurrence of costs. In selecting a cost driver, we must consider... Degree of Correlation

33 Cost Drivers A characteristic of an event or activity that results in the incurrence of costs. In selecting a cost driver, we must consider... Degree of Correlation Cost of Measurement

34 Cost Drivers A characteristic of an event or activity that results in the incurrence of costs. In selecting a cost driver, we must consider... Degree of Correlation Cost of Measurement BehavioralEffects

35 Copyright © 2008 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin Learning Objective 7

36 Interviewing and Paper Trails The information for ABC systems initially comes from interviews with employees in the support departments and a review of each department’s records.

37 Storyboarding A procedure used to develop a detailed process flow chart, which visually represents activities and the relationships among activities. Step 1 Step 1 Step 2 Step 2 Step 3 Step 3 Step 4 Step 4 These are the steps we follow to build a memory board. These are the steps we follow to build a memory board.

38 Direct versus Indirect Costs Volume-Based Costing All production costs except direct materials and direct labor are lumped together in one overhead cost pool. Volume-Based Costing All production costs except direct materials and direct labor are lumped together in one overhead cost pool. Activity-Based Costing An effort is made to account for as many costs as possible as direct costs of production. Activity-Based Costing An effort is made to account for as many costs as possible as direct costs of production. IndirectCosts

39 Indicators of Need for ABC Line managers do not believe the product costs reports Line managers do not believe the product costs reports Marketing does not use costs reports for pricing decisions Marketing does not use costs reports for pricing decisions Product-line profit margins are hard to explain Product-line profit margins are hard to explain Sales are increasing, but profits are declining. Sales are increasing, but profits are declining. Some products that have reported high profit margins are not sold by competitors Some products that have reported high profit margins are not sold by competitors Direct labor is a small percentage of total costs Direct labor is a small percentage of total costs

40 Optimal Product-Costing System High High Low Low Cost InformationSystemAccuracy Optimalsystem Total Cost Design, implementation and maintenance costs Cost of inferiordecisionsresultingfrominaccurateinformation. Exh. 5-13

41 Copyright © 2008 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin Learning Objective 8

42 ABC in the Service Industry Objectives

43 End of Chapter 5 This is my kind of cost pool!


Download ppt "Copyright © 2008 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin Chapter 5 Activity-Based Costing."

Similar presentations


Ads by Google