ALICE planning meeting 24.12.2010. 24/12/10 ALICE planning meeting2 Outline ALICE Christmas break schedule –Access UX25, L3 and MNF Services interruption.

Similar presentations


Presentation on theme: "ALICE planning meeting 24.12.2010. 24/12/10 ALICE planning meeting2 Outline ALICE Christmas break schedule –Access UX25, L3 and MNF Services interruption."— Presentation transcript:

1 ALICE planning meeting 24.12.2010

2 24/12/10 ALICE planning meeting2 Outline ALICE Christmas break schedule –Access UX25, L3 and MNF Services interruption –Gas, cooling and electricity –DAQ and DCS plans Detectors activities Day-by-day schedule wks 49-4 VIP visits AOB

3 24/12/10 ALICE planning meeting3 Christmas break schedule Start on Tuesday, 7 th December. End on Friday, 18 th February Plan: –Open both L3 doors –Installation of 3 TRD and 6 EMCal modules

4 24/12/10 ALICE planning meeting4 ALICE Christmas break schedule OpenExperiment TRD EMCal CloseExperiment Open L3 doors Close L3 doors

5 24/12/10 ALICE planning meeting5 Access restrictions The reasons to restrict the access are: –Handling of shielding blocks –Lowering of heavy structures (yellow-platform, TRD and EMCal rotators and modules) –Installation of EMCal modules –Removal of L3 ventilation –Evacuation tests –… The access restrictions concern the UX25 cavern, MNF, L3 and CRs SLIMOS shifts still missing in wks 49-50 and 4-5 Indications are given (next slides) concerning the access during the whole break – more precise info will be discussed at 5 o’clock daily meetings

6 24/12/10 ALICE planning meeting6 UX25 access Rules for access restrictions: Removal/installation of shielding (restriction includes RB24 triplets) PX24 blocks: no access CR5 and UX25 PX24 beams (35t): no access CR1-5, Expo, and UX-25 All other blocks: no access to UX-25 LHC evacuation test (7/12 after 18:00 and 24/12) – no access UX25 Gas functional test (10/12 - 2 hrs) – no access UX25 and CR1-5 AUG test (20/1) (Arrêt Urgence General – General Emergency Stop) – no access UX25 DSO test (12-13/1) (Department Safety Officer) – no access UX25 No access SX2 during manipulation of blocks in SX2 (except ACR and WRs)

7 24/12/10 ALICE planning meeting7 L3 (and MNF) access EMCal No Ventilation Wks 50 and 4: access (TPC) to be coordinated with TC (transport) Wks 1-2: no access during EMCal SMs insertion inside L3 (see day-by-day) When moving from low-beta to yellow platform: no access to MNF When inserting the module: no access L3 and MNF Watcher needed in wk 49 and from wk 4 onwards Wk 6 or 7 (tbd): Kr calibration – TPC T stability (all interventions to be agreed by TC/RC) 31 Evac. No Ventilation 243 No Ventilation 13 7

8 Services interruption

9 24/12/10 ALICE planning meeting9 Maintenance gas systems Functional tests New gas monitoring 13-15/12: Stop N2, CO2, Neon, Ar (24 hours max N2, CO2 and Neon) TRD backup (N2 bottle in CR5) – HMPID backup (Ar bottle in SG2) 12/1 (during the cooling stop): Stop C2H2F4, Isobutane, CH4 and SF6 -> will affect TOF and purifiers (no Ar/H2) 13 Flowmeters

10 24/12/10 ALICE planning meeting10 Gas system status over Christmas Albin TPC: flush CO2 TRD: ON TOF: ON – stop 11-12/12 and during cooling stop (KNF pump stopped) HMPID: ON (Ar backup) PHOS: N2 flushing PMD: ON (except 11-12/12 – gas stop) Muon TRK: backup CO2 Muon TRG: backup Ar No flammable gases from 7 Dec until 25 Jan PM (after maintenance UX25, Muon TRK-TRG ventilation)

11 24/12/10 ALICE planning meeting11 Maintenance cooling units Cooling Plants and Primary Network Cooling towers Maintenance on production network. No primary water from 12/1 (PM) to 21/1 CR1-2-3, the Wiener PS and detector cooling plants affected (plants can RUN, but no cooling power). Part of DCS will be kept running Maintenance and consolidation 17 21 12 TOF/PHOS EMC HMPID SPD TPC 10 Maintenance on cooling plants. Replacement of pneumatic actuators for TOF/TRD/TPC plants + TOF/PHOS flowmeter. CP will be stopped during maintenance SSD/SDD TRD TPC RR Chill ers

12 24/12/10 ALICE planning meeting12 Maintenance ventilation units SG2 UX25, Muon TRK-TRG 17 12 UX25, Muon TRK- TRG L3

13 24/12/10 ALICE planning meeting13 Safety and electrical systems UX25 fire detect. 20 PX24 fire detect. + red phones UPS AUG UPS DSO Evacuation DSS SNIFFER mainten. Auto-transfert Evacuation Early morning/late evening (tbc) PX24 PAD LACS doors 31 Guard 8-00 – 18-00

14 24/12/10 ALICE planning meeting14 LHC evacuation tests (7/12 after 18:00 and 24/12 tbc) –no access UX25 EN/EL: interruption on auto-transfert network (9/12 from 07:00 till 07:05): –all wall outlets will be interrupted –including all non-UPS outlets in the ACR (so essentially all WRs) –including outlets SXL2, offices and barracks –non-UPS power for the detector cooling plants will be interrupted –power to all gas systems will be interrupted –the UPS powered systems will not be affected, but will run on batteries for the 2 min. interruption –the electronics racks in the cavern and CRs will not be affected. –See https://edms.cern.ch/file/1106913/1/ENNC_2010_196.pdf https://edms.cern.ch/file/1106913/1/ENNC_2010_196.pdf DSS modification (13/1) –Will stop the full DSS, trigger all interlocks, including stopping power to all racks EN/EL: AUG Test (20/1) (Arrêt Urgence General – General Emergency Stop) –Major electrical perturbation. Also ACR affected Safety and electrical systems Impact on ALICE

15 24/12/10 ALICE planning meeting15 DAQ upgrade plans 21 st Dec PM till the 04 th Jan included –The DAQ will be OFF during the CERN closure. –The ACR PCs will be left ON to give access to the DCS for the detectors teams who need it. 5 th to the 11 th of January included –DAQ restarted on the first working day for 1 week. The DAQ will be switched ON with the present version of all software. Allow a quick commissioning after the installation of new detector modules or the intervention on existing detectors. 12 th to the 23 rd Jan included –The DAQ will be OFF during the cooling interruption at P2. –DAQ renovated (see TB December) 24 th January –The DAQ will be ON again. It will run under SLC5 64 bits unless there would be an unexpected key problem. The electronic logbook will remain available during the whole period. When the DAQ will be OFF, it will be running in the DAQ lab in Meyrin. There will be a few hours of interruption to switch from P2 to Meyrin and back. Pierre/Uli

16 24/12/10 ALICE planning meeting16 DCS plans Baseline: DCS will be operational all times where technically possible –With ‘best effort’ support –With access restrictions during CERN End-of-Year closure (22/12 – 4/1) Many activities and upgrades are planned –Will be coordinated with individual detectors to minimise impact –For central systems, as much as possible in shadow of other perturbations (e.g. cooling stop) –Perturbations (e.g. for reboots etc.) cannot be excluded Detectors are invited to communicate ‘critical periods’, with services needed –Will try to cater for detector needs as much as possible Known perturbations: –Tue 7/12 10:00 – 12:00, interruptions of the GPN link to/from P2 Upgrade of router, test impact on ALICE –Wk50 (13-17/12) – major updates to all PC (many perturbations to be expected) –12/1 – 21/1 (cooling stop), only minimal central services. All detector DCS switched off, except for special requests and if cooling power allows More detailed planning at weekly and daily meetings André / Peter

17 24/12/10 ALICE planning meeting17 DCS plans (details) Wk 50 –Mon 13/12 – Fri 17/12 (daytime): SW upgrades and patches to all systems (Operating system and PVSS) Delayed/extended due to problems with automatic PVSS upgrade procedure (several manual operations needed) Systems unavailable for short (~hrs) periods, frequent reboots –Support to detectors restarting/testing their systems after upgrades Detectors shall test functionality as much as possible Wk 51 –Contingency for system upgrades –Support to detectors restarting/testing their systems after upgrades Detectors shall test functionality as much as possible –Tue 21/12 PM: Limit access to DCS cluster during end-of-year closure Register with your SRC if you require access (see message Peter 2/12/2010) Wk 52 – Wk 01 –Only ‘best effort’ support during CERN closure Wk 02 –Wed 12/01 – (cooling intervention) shutdown of detector systems except special requests, within limits of cooling power André / Peter

18 24/12/10 ALICE planning meeting18 Access request Cavern and surface You should submit an ADI and a task procedure Two persons minimum Work breakdown structure – risk associated at each step ADI https://edh.cern.ch/Document/ADI Task procedure Template EDMS 1103355 Attach task procedure

19 Detectors activities

20 24/12/10 ALICE planning meeting20 EMCal Status of modules: –6 modules in SXL2 Test station installed in SXL2 Requiring a lot of access to connect everything up, test, and debug as they commission the new SMs –Low voltage, high voltage (CR4), and DAQ operating as much as possible during the installation period in January.

21 24/12/10 ALICE planning meeting21 EMCal Surveys Zero measurement (wk 51-52), after insertion of 1 st module and after the insertion of 2 nd module: –A-side: CALframe feet and rails + modules (adaptors) –C-side (photogrammetry - 1/2 day) After insertion of 3 rd, after insertion of 4 th and after insertion of 5 th module: –A-side: points chosen depending on results previous survey –C-side: with theodolite from A-side (or full photogrammetry, depending on results previous survey) After insertion of 6 th module: –A-side: full –C-side: full

22 24/12/10 ALICE planning meeting22 PMD Wk 50: –Lift CROCUS (in order to open L3 doors) - can be done by P2 technicians –disconnect cables (after 16/12) Wk 51 (20/1): move PMD in parking position (Pieter) Wks 51-4: repair electronics chains –Need Ar/CO2 at all times Wks 5-6 (night): access to CROCUS (doors closed, use CROCUS platform) February: move PMD to final position Wk 6: survey (transfer survey network to miniframe (Antje)) Wks 1-3 SPIE: new air cooling system – major installation work in January (should be done by end January) –Nacelle HAULOTTE needed

23 24/12/10 ALICE planning meeting23 TOF/PHOS TOF: –HV hardware checks on SM13 (December) –TRM replacement (14 TRMs on the A side) (3/01 – 12/01) –Replacement DC-DC (with no LV spare channels): 16/12 (after 18:00) PHOS: (A.Vinogradow at CERN 1/12 end January) –Investigate module 2 pedestal issues –Try to understand behavior of unstable branch in Module 3 –Remake ISEG crate to connect to the hardware interlock –Maintenance crystal cooling plant (January) Gilda/Yury

24 24/12/10 ALICE planning meeting24 Muon TRG RPC Detector/gas system: –Check gas leak on few RPC detectors and repair 2 gas distribution channels. Replacement of 1 HV cable. From Monday 10/01 (afternoon) to Friday 14/01 –Upgrade Sensor gas humidity and pressure regulator (CR5, schedule to be defined with the gas team) –Replace few RPC modules with high current: under discussion –Will restart the flammable gas flow at end of January/beginning of February, to check the detectors with HV at least 15 days before the first beam injection Electronics: –Maintenance Local decision electronics (December 8 th after 18:00) –Upgrade FE threshold distributors, higher segmentation (level 4 gangway, December 8 th after 18:00) –Upgrade firmware DARC and Regional board in order to speed up MTR decision electronics configuration (wk 6, after the DAQ upgrade) Pascal/Ermanno/Paolo/Anna

25 24/12/10 ALICE planning meeting25 Muon TRK plans December: CROCUS firmware upgrade (protection against spurious busy reset signal): –Access to Crocus, Dipole and FASS. Need nacelle wk 49 High occupancy bus patches: –Remove one "bad" slat (and replace by one spare) to test it in lab Done –Access to Dipole and to muon side with nacelle in December Done –Depending on the results, fix all remaining “bad” slats in January Planning to be sorted out January (from wk 2): replacement 2 quadrants ST2 with faulty wires: –Test spare quadrants in lab (December) –Work scheduled during January 6 - 27, 2011 (access to FASS) –Crane needed on 11th and 18th January –Discussion on 6th January Ermanno/Herve

26 24/12/10 ALICE planning meeting26 ZDC plans Check platform displacement with survey –One week – depending on surveyors availability Paolo

27 24/12/10 ALICE planning meeting27 SPD cooling plans Wk 49 (8/12 after 18:00): cut pipes in order to open the doors Wks 2-3 (during cooling stop): wash 4 bad sectors (machine installed on I-side, close to HMPID pump). Access to the outer side of MNF (side I) to work on the heater of sector 0 (nacelle or scaffolding needed) Wks 3-4 (as soon as the door is closed): reconnect temporarily pipes and test with dummy sector inside MNF (in parallel with shielding in wk 4)

28 24/12/10 ALICE planning meeting28 SSD/SDD SSD: Ton: remove a cooling pipe from SSD corrosion test setup (week 2) Replacement CAEN module (C-side) + repair bad temperature signal at the C-side (week 2) SDD: Calibration of 78 pressure sensors in L3 and on miniframe (January 12 to 14)

29 24/12/10 ALICE planning meeting29 T0 Activities planned from 7-19 December (after 18:00): –Check/repair the amplifiers from A and C side (inside L3) –Check the signal cables from A-side –Check/repair fast electronics modules (racks O18-19) –Need possibility to do standalone runs in parallel

30 24/12/10 ALICE planning meeting30 TRD installation - weeks 51, 52 4 modules at P2 (SM2, SM11, SM 15 and SM16) Installation sequence: 16 → 15 → 11 (or 16 → 11 → 15) 2 technicians (Philippe and Didier) + Survey (Nail from 6/12) + TC permanently at P2 Connection done right after installation Survey: –Space-frame deformations and displacement of beampipe (flange), miniframe and TPC feet. Before-after each insertion –Modules (2 points/SM on 4/7 SM) in wk 50 –Modules (3 points/SM on 10/10 SM) after EMCal (wk 3)

31 24/12/10 ALICE planning meeting31 TRD Week 49: –LV Wiener ~70 PSU Back-Plane modifications (to improve mechanical stability, same as TPC applied already) –Netgear switches replacements (1 day) –LV line fixation: installation of improved patch panels on front of module (C-side) and replacing cables Repair pretrigger (A-side, below PMD) – after 20/12 Week 1: –Finalizing connections, start commissioning Week 2: –Stable running with cosmics 3 to 4 weeks in January or February: –Stable running with cosmics for alignment and with Krypton for gain calibrations (to be still discussed)

32 24/12/10 ALICE planning meeting32 TPC Recover all water inside cooling plant (week 50) Replacement of 15 damaged FECs (equally distributed A-C sides) –~3 days per FEC. Therefore, we would like to use all available time slots where access to the L3 is possible –At the end of this activity we will need a period of about 2 weeks where all aforesaid systems are available for final verification, and access to the TPC in case something is not working correctly. Kr data taking at the end of the shutdown (1 week)

33 24/12/10 ALICE planning meeting33 TPC Replacement of the laser Start the dismantling of the Spectron laser (week 50, Th-Sat after 18:00): –dismount back wall of laser hut (help of P2 technician) –stop cooling water (help of P2 technician) –prepare new water connection (electrical power should be OK) Install new Ekspla laser (week 1): –remove old laser and install new (use crane to transport laser) –connect cooling water (help of P2 technician) –reinstall back wall (maybe after cutting a hole in it) Testing and alignment of new laser (week 2): –possibility to run laser behind closed doors (inside hut) –maybe install laser tube temporarily and shoot into TPC whenever –compatible with other installation work Possible further testing and adjustment (week 3) Borge

34 24/12/10 ALICE planning meeting34 ACORDE Check some ACORDE modules (PMTs optical conections, connectors, etc) above the magnet The plan is to start this activities after the second week of January 2011

35 24/12/10 ALICE planning meeting35 Other activities SPIE + CV: refurbishment ITS dehumidifier in CR – February –New unit at P2 in January –Repair leak (replace leaking part – transport needed) –Recirculation air –Add flowmeter (connect to ELMB: Frederick) EN-EL (T.Bourrel): motorize L3-Dipole-Miniframe circuit breaker. –VIC 16/12 10:30 SPIE: cabling UX25-CR4 – 17/1 New magnet emergency buttons + flashing lights L3 and dipole Frederick: humidity sensor L3 ventilation (extraction) + redo CTP connectors Intervention on cavern lift –One day stop – no access to UX25. To be scheduled

36 24/12/10 ALICE planning meeting36 Other activities Google propose to produce a custom Streetview application for CERN showing both outside and underground areas –Visit Tuesday 21 December at 16:15 Philippe: replace rack filters during cooling stop. Install temporary line PHOS cooling (PS rack and crystal cooling plant)

37 24/12/10 ALICE planning meeting37 Magnet control upgrade Wk 49: nous devons intervenir dans la MCR pour: –changement des alimentations 24V et 48 V des systèmes MSS et MCR (préventif) –changement des modules convertisseurs PT100 des hots points du Solénoïde (correctif suite à deux incidents ayant entrainés l'arrêt du Solénoïde) et en UX25, comme Philippe Bouvier l'a déjà signalé: –recâblage des AU du dipôle et du Solénoïde –signalisation du champ magnétique du dipôle et du Solénoïde Nous étudions toujours une solution pour le monitoring des températures du Solénoïde. L'arrêt de fin d'année va permettre de faire une meilleure approche de ce qui est existant en UX25. En ce qui concerne l'alimentation électrique de la MCR, nous dépendons actuellement d'une seule source de courant sous UPS avec secours diesel. Afin d'établir une redondance pour l'alimentation de la MCR je souhaiterais installer une seconde source d'alimentation sous UPS. Je sais qu'une étude est faite à ALICE pour augmenter la puissance des UPS existants en 2012. Je souhaiterais que cette demande soit incluse pour le calcul de puissance des nouveaux UPS (besoin pour la MCR: 16A en monophasé) Pascal

38 Day-by-day schedule UX25 and MNF - Wk 49

39 24/12/10 ALICE planning meeting39 18:00: end HI program –Ramp down both magnets. !!! Emergency dump !!! 18:00 – 22:00: access system test. No access UX25 22:00: RPE survey (Jiri + 2 nd person) –Then go to restricted mode Week 49 - 6/12 Monday Program

40 24/12/10 ALICE planning meeting40 Activities in UX25 - Week 49 - 6/12 Monday No access UX-25 - possibility of access from 22:00 ITECO HAULOTTE TRD team at CERN: 6 to 10/12

41 24/12/10 ALICE planning meeting41 8:00 - 18:00: UX25 cavern in Restricted mode –No access UX25 (except Transport, VAC, TC and RP) 8:30 - 9:30: RP liquid (and gas) sampling (Adeline, Pierre) –Collect RP samples (Fernando, Philippe) –Survey L3 and Dipole 18:00 - 21:00: evacuation test – No access UX25 From 21:00 - Cavern in General mode 14:00 - 15:00: Portuguese Press visit. 10 persons Week 49 - 7/12 Tuesday Program

42 24/12/10 ALICE planning meeting42 ALTEAD: PX24 shielding blocks – top layer removed –8:00 to 18:00: no access CR5 Reinstall crane electronics - Problems (ongoing) 14:00 to 15:00: put SM16 into the rotator - Ongoing VAC: Neon injection preparation - Started –Transport needed (EDH 4472100) – Rack moved by hand –Remove “green fence” (P2 technician) - Done Stop flammable gases i-C4H10 and CH4 (Ar/H2 on 10/12) - Done 8:30: Lock L3+Dipole power converter + compensator magnet - Done Test transmission of alarm lift to FB - Done 8:30: inspection PHOS cooling plant (Arturo, Dominique, Philippe, Sasha) – Done (will install temporary line) 15:15: VIC SPD – Done + Gas VIC DCS: 10:00 – 12:00, interruptions of the GPN link to/from P2 – Done. DCS got stuck. Investigating why MCR (Magnet Control Room): HW modifications (Pascal B.) – Started TRD (after 21:00): Wiener PS back-plane modification and LV consolidation (L3) Week 49 - 7/12 Tuesday Activities

43 24/12/10 ALICE planning meeting43 Activities in UX25 - Week 49 - 7/12 Tuesday VAC RP samples PX24 shielding: blocks TRD Wiener PS

44 24/12/10 ALICE planning meeting44 8:00 - 18:00: UX25 cavern in Restricted mode –No access UX25 (except Transport, VAC, TC and RP) From 18:00 - Cavern in General mode 18:00: Confined Space Training –Tour in L3 at the end of the course Week 49 - 8/12 Wednesday Program

45 24/12/10 ALICE planning meeting45 ALTEAD: PX24 shielding beams (35t) - Done –8:00 to 16:30: no access CR1-5 and Expo –Move ITECO C-side - Ongoing EN-HE: Reinstall crane electronics – Done. Crane operational VAC: Neon injection – injection table prepared. Neon injected tomorrow afternoon –Annular ion pump (PI.45.1L2.X) switched off Activities after 16:30: EN-CV: empty TPC tank - Ongoing TPC: replacement of damaged FECs (C-side) - Ongoing TRD: pretrigger PS work done. Wiener PS back-plane modification (SXL2, almost done). Start re-installing Wieners tonight. SPD: cut inox pipes - Done Muon TRK: CROCUS firmware upgrade Muon TRG: Maintenance Local decision electronics and upgrade FE threshold distributors – Done T0: investigation broken amplifier (MNF and L4-rack) - Ongoing Week 49 - 8/12 Wednesday Activities

46 24/12/10 ALICE planning meeting46 Activities in UX25 - Week 49 - 8/12 Wednesday PX24 shielding: beams (35t) VAC Move TRD Wiener PS Cut SPD pipes Muon TRG TPC FEC and TRD LV TPC cooling Muon TRK: CROCUS firmware upgrade T0

47 24/12/10 ALICE planning meeting47 Activities in MNF - Week 49 - 8/12 Wednesday T0

48 24/12/10 ALICE planning meeting48 8:00 - 18:00: UX25 cavern in Restricted mode –No access UX25 (except Transport, VAC and TC) From 18:00 - Cavern in General mode Interruption on auto-transfert network (from 07:00 till 07:05). No access underground –all wall outlets will be interrupted –including all non-UPS outlets in the ACR (so essentially all WRs) –including outlets SXL2, offices and barracks –non-UPS power for the detector cooling plants will be interrupted –power to all gas systems will be interrupted –the UPS powered systems will not be affected, but will run on batteries for the 2 min. interruption –the electronics racks in the cavern and CRs will not be affected. –See https://edms.cern.ch/file/1106913/1/ENNC_2010_196.pdf https://edms.cern.ch/file/1106913/1/ENNC_2010_196.pdf Week 49 - 9/12 Thursday Program

49 24/12/10 ALICE planning meeting49 ALTEAD: MNF shielding – 2/4 “T” blocks removed –8:00 to 18:00: No access CR1-5 during lifting up of 5 big beams –Stabilizers (after 18:00) - OK –Move ITECO I-side VAC: Neon injection – Beampipe under Neon RAMSES: removal of Data Acquisition modules CR5 - Done EMCal team at CERN: fit rollers on all SMs (SXL2). Start 13:30 - OK Dipole-Solenoid cooling stopped (Philippe) Purge TRD cooling flexibles + replace o-rings (Philippe + Frederick) - Done Activities after 18:00: TPC: replacement of damaged FECs (C-side) TRD: Wiener PS back-plane modification and LV consolidation (SXL2) Muon TRK: CROCUS firmware upgrade T0: investigation broken amplifier (MNF and L4-rack) Week 49 - 9/12 Thursday Activities

50 24/12/10 ALICE planning meeting50 Activities in UX25 - Week 49 - 9/12 Thursday VAC MNF shielding TRD Wiener PS Stabilizers No access CR1-5 during lifting up of 5 big beams TPC FEC and TRD LV Muon TRK: CROCUS firmware upgrade T0 Stabilizers Move

51 24/12/10 ALICE planning meeting51 Activities in MNF - Week 49 - 9/12 Thursday T0

52 24/12/10 ALICE planning meeting52 8:00 - 17:00: UX25 cavern in Restricted mode –No access UX25 (except Transport and TC) From 17:00 - Cavern in General mode 9:00 – 12:30: functional test gas systems –9:00 – 11:00: No access UX25 and CR1-5 –All gas systems will be stopped-started several times –Stop Ar/H2 at end of test Week 49 - 10/12 Friday Program

53 24/12/10 ALICE planning meeting53 ALTEAD: MNF shielding: I-side wall EMCal: fit rollers on all SMs Maintenance PX24 MAD (transparent) Activities after 18:00: TPC: replacement of damaged FECs (C-side) TRD: Wiener PS back-plane modification and LV consolidation (L3) Muon TRK: CROCUS firmware upgrade T0: investigation broken amplifier (MNF and L4-rack) Week 49 - 10/12 Friday Activities

54 24/12/10 ALICE planning meeting54 Activities in UX25 - Week 49 - 10/12 Friday LV156 TRD Wiener PS TPC FEC and TRD LV MNF shielding

55 24/12/10 ALICE planning meeting55 Activities in MNF - Week 49 - 10/12 Friday

56 24/12/10 ALICE planning meeting56 8:00 - 17:00: UX25 cavern in Restricted mode –No access UX25 (except Transport and TC) From 17:00 - Cavern in General mode 18 KV Autotransfert tests from 8h00 to 20h00 –Frequent power cuts will occur on the Meyrin site. The group EN-EL recommends that you turn off all your critical equipment, computers and computer equipment. –For any further information please refer to the "note de coupure": –https://edms.cern.ch/file/1107011/1/ENNC_2010_203.pdfhttps://edms.cern.ch/file/1107011/1/ENNC_2010_203.pdf Week 49 - 11/12 Saturday Program

57 24/12/10 ALICE planning meeting57 ALTEAD: MNF shielding: I-side wall Activities after 17:00: TRD: Wiener PS back-plane modification and LV consolidation (L3) Week 49 - 11/12 Saturday Activities

58 24/12/10 ALICE planning meeting58 Activities in UX25 - Week 49 - 11/12 Saturday TRD Wiener PS TRD LV LV156 MNF shielding

59 24/12/10 ALICE planning meeting59 Activities in MNF - Week 49 - 11/12 Saturday

60 24/12/10 ALICE planning meeting60 Activities in UX25 - Week 49 - 12/12 Sunday Access in general mode

61 24/12/10 ALICE planning meeting61 Activities in MNF - Week 49 - 12/12 Sunday Access in general mode

62 Day-by-day schedule UX25 and MNF - Wk 50

63 24/12/10 ALICE planning meeting63 Access status: 8:00 - 18:00: UX25 cavern in Restricted mode –No access UX25 (except Transport and TC) From 18:00 - Cavern in General mode No access L3 (no ventilation) Activities: ALTEAD: MNF shielding: O-side wall Lift PMD CROCUS SPIE: removal L3 ventilation Philippe: cut SPD pipe (chillers) Activities after 18:00: TRD: access to L4 racks T0: investigation broken chains Week 50 - 13/12 Monday

64 24/12/10 ALICE planning meeting64 Activities in UX25 - Week 50 - 13/12 Monday LV156 No access L3 (no ventilation) L3 ventilation LV156 MNF shielding

65 24/12/10 ALICE planning meeting65 Activities in MNF - Week 50 - 13/12 Monday No access L3 (no ventilation)

66 24/12/10 ALICE planning meeting66 Access status: 8:00 - 18:00: UX25 cavern in Restricted mode –No access UX25 (except Transport and TC) From 18:00 - Cavern in General mode No access L3 (no ventilation) Activities: ALTEAD: MNF shielding: O-side wall Opening I-side door done Gas upgrade (SG2): stop all gas systems Ar, CO2, N2 and Neon done. The others must be done on January 11!!! –Evacuation all Ar/H2 bottles (Fayet, morning) –X-ray at night SPIE: new PMD ventilation (removal filter) –VIC at 10:00 Activities after 18:00: T0: investigation broken chains Week 50 - 14/12 Tuesday

67 24/12/10 ALICE planning meeting67 Activities in UX25 - Week 50 - 14/12 Tuesday Open I-side door No access L3 (no ventilation) LV156 MNF shielding (green bridges) PMD ventilation Visit 13:30 (Karel) T0

68 24/12/10 ALICE planning meeting68 Activities in MNF - Week 50 - 14/12 Tuesday No access L3 (no ventilation) T0

69 24/12/10 ALICE planning meeting69 Access status: Cavern in General mode Activities: ALTEAD: yellow-platform rails. Put YP on rails. Removal MNF staircase. Shielding on O-side gone TRD: test LV inside magnet TPC: replacement FE cards (C-side) Release all TOF crates supports (Yannick-Samuel) Gas upgrade (SG2): restart gas systems EN-CV: maintenance TRD cooling unit TPC laser: dismount back wall of laser hut + start removal laser TOF: removal DC/DC converters VIP visit: Finance and Council Delegates – 16:45 (1hour) Week 50 - 15/12 Wednesday

70 24/12/10 ALICE planning meeting70 Activities in UX25 - Week 50 - 15/12 Wednesday Access in general mode TRD cooling TPC/TRD YP rails Release all TOF crates supports (Yannick- Samuel) + TOF DC/DC Laser EMC

71 24/12/10 ALICE planning meeting71 Activities in MNF - Week 50 15/12 Wednesday Access in general mode Removal MNF staircase (access with ladder)

72 24/12/10 ALICE planning meeting72 Access status: Cavern in General mode Arrival PMD team Visit (W.Riegler). 14:30 Activities: ALTEAD: yellow-platform rails Open O-side door – by afternoon SPIE: PMD ventilation Survey: baby-frame zero-measurement + TRD EN-EL: motorize L3-Dipole-Miniframe circuit breaker (T.Bourrel, VIC at 10:30) TRD: test LV inside magnet TPC: replacement FE cards (C-side) Release all TOF crates supports (Yannick-Samuel) Re-arrange TPC cooling pipes (MNF, Yannick) EN-CV: maintenance TRD cooling unit TPC laser: removal laser + take out laser-hut back door. Take out old power supply EMCal: installation HV PS (CR4) and LV PS (L4-O-side) Done Week 50 - 16/12 Thursday

73 24/12/10 ALICE planning meeting73 Activities in UX25 - Week 50 - 16/12 Thursday Laser TRD cooling TPC/TRD EN-EL Release all TOF crates supports (Yannick- Samuel) PMD ventilation Open O-side door LV156 Access in general mode Survey

74 24/12/10 ALICE planning meeting74 Activities in MNF - Week 50 - 16/12 Thursday Access in general mode TPC cooling pipes (Yannick)

75 24/12/10 ALICE planning meeting75 Access status: Cavern in General mode Visit (C-E.Sala) DAQ: the experiment logbook and data taking will be unavailable from 10:00 to 12:00 for a maintenance operation Arrival 2 (last) EMCal modules from Grenoble. Unload in SXL2 Activities: ALTEAD: lower TRD 16. No access low-beta platform SPIE: PMD ventilation Survey: baby-frame zero-measurement + TRD TRD: test LV inside magnet TPC: replacement FE cards (C-side, and A-side (tbc)) Decoupling TPC-Space-Frame (Yannick-Samuel) EMC: investigate a part of the EMCal readout that was noisy (~16 channels on one "T-card") (L3) PMD: disconnect services EN-CV: maintenance TRD cooling unit Week 50 - 17/12 Friday

76 24/12/10 ALICE planning meeting76 Activities in UX25 - Week 50 - 17/12 Friday Decoupling TPC-Space- Frame (Yannick- Samuel) & EMC TPC FEC Access in general mode Survey PMD ventilation TPC FEC TRD cooling

77 24/12/10 ALICE planning meeting77 Activities in MNF - Week 50 - 17/12 Friday Disconnect PMD services Access in general mode

78 24/12/10 ALICE planning meeting78 Activities in UX25 - Week 50 - 18/12 Saturday Decoupling TPC- Space-Frame (Yannick-Samuel) Access in general mode Survey

79 24/12/10 ALICE planning meeting79 Activities in MNF - Week 50 - 18/12 Saturday Access in general mode

80 24/12/10 ALICE planning meeting80 Activities in UX25 - Week 50 - 19/12 Sunday Access in general mode TRD team at CERN: 19 (PM) to 23/12

81 24/12/10 ALICE planning meeting81 Activities in MNF - Week 50 - 19/12 Sunday Access in general mode

82 Day-by-day schedule UX25 and MNF - Wk 52

83 24/12/10 ALICE planning meeting83 Activities in UX25 - Week 52 - 27/12 Monday Connect TRD 15 Prepare TRD 11 installation Including installation BBF rails SR11 TRD Survey Diego at CERN (noon) PMD ventilation

84 24/12/10 ALICE planning meeting84 Activities in MNF - Week 52 - 27/12 Monday PMD: replacement electronics chains

85 24/12/10 ALICE planning meeting85 Activities in UX25 - Week 52 - 28/12 Tuesday Prepare TRD 11 installation PMD ventilation

86 24/12/10 ALICE planning meeting86 Activities in MNF - Week 52 - 28/12 Tuesday PMD: replacement electronics chains

87 24/12/10 ALICE planning meeting87 Activities in UX25 - Week 52 - 29/12 Wednesday Install TRD 11 TRD Survey PMD ventilation

88 24/12/10 ALICE planning meeting88 Activities in MNF - Week 52 29/12 Wednesday PMD: replacement electronics chains

89 24/12/10 ALICE planning meeting89 Activities in UX25 - Week 52 - 30/12 Thursday Connect TRD 11 TRD Survey EMCal infrastructure Move EMCal rotator + SM5 onto low beta platform, and perform handling test

90 24/12/10 ALICE planning meeting90 Activities in MNF - Week 52 - 30/12 Thursday PMD: replacement electronics chains

91 24/12/10 ALICE planning meeting91 Activities in UX25 - Week 52 - 31/12 Friday EMCal infrastructure

92 24/12/10 ALICE planning meeting92 Activities in MNF - Week 52 - 31/12 Friday PMD: replacement electronics chains

93 24/12/10 ALICE planning meeting93 Activities in UX25 - Week 52 - 1/1/2011 Saturday New Year day

94 24/12/10 ALICE planning meeting94 Activities in MNF - Week 52 - 1/1/2011 Saturday New Year day

95 24/12/10 ALICE planning meeting95 Activities in UX25 - Week 52 - 2/1 Sunday

96 24/12/10 ALICE planning meeting96 Activities in MNF - Week 52 - 2/1 Sunday

97 Day-by-day schedule UX25 and MNF - Wk 1 - 2011

98 24/12/10 ALICE planning meeting98 Activities in UX25 - Week 1 - 3/1 Monday Connect TRD 11 PMD ventilation Install EMCal 40deg-C (PM) Lower SM6 onto low beta platform SM5 TOF TRM Move HAULOTTE Laser Install new Ekspla laser Reconnect PMD cooling

99 24/12/10 ALICE planning meeting99 Activities in MNF - Week 1 - 3/1 Monday PMD: replacement electronics chains

100 24/12/10 ALICE planning meeting100 Activities in UX25 - Week 1 - 4/1 Tuesday PMD ventilation EMC Survey EMC Survey (AM) Install EMCal 40deg-A (PM) SM6 TOF TRM Laser

101 24/12/10 ALICE planning meeting101 Activities in MNF - Week 1 - 4/1 Tuesday PMD: replacement electronics chains

102 24/12/10 ALICE planning meeting102 Activities in UX25 - Week 1 - 5/1 Wednesday TPC RR cooling RAMSES: reinstallation of Data Acquisition modules CR5 Maintenance UPS ESS307/2X (transparent) GS/ASE: PX24 fire detection maintenance PMD ventilation EMC Survey Lower SM7 onto low beta platform TOF TRM Laser TPC FEC EN-CV: maintenance chillers (transparent)

103 24/12/10 ALICE planning meeting103 Activities in MNF - Week 1 - 5/1 Wednesday PMD: replacement electronics chains

104 24/12/10 ALICE planning meeting104 Activities in UX25 - Week 1 - 6/1 Thursday TPC cooling PMD ventilation Install EMCal 60deg-C SM7 Lower SM8 onto low beta platform EMC Survey TOF TRM Laser GS/ASE: PX24 fire detection + red phones maintenance TPC FEC EN-CV: maintenance chillers (transparent)

105 24/12/10 ALICE planning meeting105 Activities in MNF - Week 1 - 6/1 Thursday PMD: replacement electronics chains

106 24/12/10 ALICE planning meeting106 Activities in UX25 - Week 1 - 7/1 Friday TPC cooling PMD ventilation Install EMCal 60deg-A SM8 EMC Survey TOF TRM Laser GS/ASE: PX24 fire detection + red phones maintenance TPC FEC EN-CV: maintenance chillers (transparent)

107 24/12/10 ALICE planning meeting107 Activities in MNF - Week 1 - 7/1 Friday PMD: replacement electronics chains

108 24/12/10 ALICE planning meeting108 Activities in UX25 - Week 1 - 8/1 Saturday Laser

109 24/12/10 ALICE planning meeting109 Activities in MNF - Week 1 - 8/1 Saturday

110 24/12/10 ALICE planning meeting110 Activities in UX25 - Week 1 - 9/1 Sunday

111 24/12/10 ALICE planning meeting111 Activities in MNF - Week 1 - 9/1 Sunday

112 Day-by-day schedule UX25 and MNF - Wk 2

113 24/12/10 ALICE planning meeting113 Activities in UX25 - Week 2 - 10/1 Monday PMD ventilation TPC cooling VIP visit (Mr Herman Josef Lamberti, Deutschen Bank). From 15:30 Lower SM9 onto low beta platform Muon TRG: RPC (PM) Check gas tightness on few RPC detectors (need both nacelles) SDD/ SSD Laser Testing and alignment of new laser HAULOTTE needed 1 day (whenever possible) SDD: calibration of 78 pressure sensors (10-12/1) SSD: replacement CAEN module (C-side) + repair bad temperature signal (C-side) TOF TRM TPC FEC

114 24/12/10 ALICE planning meeting114 Activities in MNF - Week 2 - 10/1 Monday PMD: replacement electronics chains

115 24/12/10 ALICE planning meeting115 Activities in UX25 - Week 2 – 11/1 Tuesday PMD ventilation TPC cooling SSD/SDD cooling Visit (30 students. Peter Glaessel and Kai Schweda) Muon TRG: RPC SPD cooling Wash 4 bad sectors + repair heater (nacelle) Laser TOF TRM TPC FEC

116 24/12/10 ALICE planning meeting116 Activities in MNF - Week 2 - 11/1 Tuesday PMD: replacement electronics chains

117 24/12/10 ALICE planning meeting117 Activities in UX25 - Week 2 - 12/1 Wednesday PMD ventilation Cooling towers maintenance (start 14:00) (No primary water) SNIFFER maintenance Install EMCal 80deg-C SM9 Lower SM10 onto low beta platform EMC Survey Muon TRG: RPC SPD cooling SDD/ SSD Laser SSD: removal of cooling pipe from corrosion test setup Cleaning rack filters (Philippe) Maintenance UPS EBS106/2X and EBS128/2X (transparent) PH-DT: new gas monitoring: Stop C2H2F4, Isobutane, CH4 and SF6 TPC FEC

118 24/12/10 ALICE planning meeting118 Activities in MNF - Week 2 - 12/1 Wednesday PMD: replacement electronics chains

119 24/12/10 ALICE planning meeting119 Activities in UX25 - Week 2 - 13/1 Thursday PMD ventilation Cooling towers maintenance (No primary water) HMPID cooling RAMSES: radiation source tests EN/CV: maintenance SG2 ventilation DSS modification. Will stop the full DSS, trigger all interlocks, including stopping power to all racks SNIFFER maintenance Install EMCal 80deg-A SM10 EMC Survey SPD cooling SDD Visit: Danish high school class (C. Søgaard) TPC FEC Muon TRG: RPC

120 24/12/10 ALICE planning meeting120 Activities in MNF - Week 2 - 13/1 Thursday PMD: replacement electronics chains

121 24/12/10 ALICE planning meeting121 Activities in UX25 - Week 2 - 14/1 Friday PMD ventilation Cooling towers maintenance (No primary water) SPD cooling SNIFFER maintenance EN/CV: maintenance SG2 ventilation RAMSES: radiation source tests VAC Start pumping out EMC Survey SPD cooling SDD LACS: revision UX25 access doors Removal EMCal infrastructure TPC FEC Muon TRG: RPC

122 24/12/10 ALICE planning meeting122 Activities in MNF - Week 2 - 14/1 Friday PMD: replacement electronics chains

123 24/12/10 ALICE planning meeting123 Activities in UX25 - Week 2 - 15/1 Saturday Cooling towers maintenance (No primary water) PHOS: maintenance crystal cooling plant PHOS cooling

124 24/12/10 ALICE planning meeting124 Activities in MNF - Week 2 - 15/1 Saturday

125 24/12/10 ALICE planning meeting125 Activities in UX25 - Week 2 - 16/1 Sunday Cooling towers maintenance (No primary water) PHOS cooling

126 24/12/10 ALICE planning meeting126 Activities in MNF - Week 2 - 16/1 Sunday

127 Day-by-day schedule UX25 and MNF - Wk 3

128 24/12/10 ALICE planning meeting128 Activities in UX25 - Week 3 - 17/1 Monday TOF/PHOS/ EMC cooling Cooling towers maintenance (No primary water) Maintenance UX25, Muon TRK-TRG ventilation SPD cooling SPIE: cabling UX25-CR4 TRD/EMC Survey PMD ventilation Removal EMCal infrastructure TPC FEC PHOS cooling Maintenance ITECO (9:00 to 11:00)

129 24/12/10 ALICE planning meeting129 Activities in MNF - Week 3 - 17/1 Monday PMD: replacement electronics chains

130 24/12/10 ALICE planning meeting130 Activities in UX25 - Week 3 – 18/1 Tuesday Cooling towers maintenance (No primary water) Maintenance UX25, Muon TRK-TRG ventilation SPD cooling TRD/EMC Survey TPC FEC TOF/PHOS/ EMC cooling PHOS cooling

131 24/12/10 ALICE planning meeting131 Activities in MNF - Week 3 - 18/1 Tuesday PMD ventilation PMD: replacement electronics chains

132 24/12/10 ALICE planning meeting132 Activities in UX25 - Week 3 - 19/1 Wednesday Cooling towers maintenance (No primary water) Maintenance UX25, Muon TRK-TRG ventilation Maintenance harmonic filter (EOF128/2X) TRD/EMC Survey PMD ventilation TPC FEC TOF/PHOS/ EMC cooling PHOS cooling

133 24/12/10 ALICE planning meeting133 Activities in MNF - Week 3 - 19/1 Wednesday PMD: replacement electronics chains

134 24/12/10 ALICE planning meeting134 Activities in UX25 - Week 3 - 20/1 Thursday Cooling towers maintenance (No primary water) Maintenance L3, UX25, Muon TRK-TRG ventilation AUG test. No access UX25

135 24/12/10 ALICE planning meeting135 Activities in MNF - Week 3 - 20/1 Thursday

136 24/12/10 ALICE planning meeting136 Activities in UX25 - Week 3 - 21/1 Friday Restart primary water Maintenance L3, UX25, Muon TRK-TRG ventilation Close doors No access L3 (no ventilation)

137 24/12/10 ALICE planning meeting137 Activities in MNF - Week 3 - 21/1 Friday PMD: replacement electronics chains No access L3 (no ventilation)

138 24/12/10 ALICE planning meeting138 Activities in UX25 - Week 3 - 22/1 Saturday No access L3 (no ventilation) Close doors

139 24/12/10 ALICE planning meeting139 Activities in MNF - Week 3 - 22/1 Saturday No access L3 (no ventilation)

140 24/12/10 ALICE planning meeting140 Activities in UX25 - Week 3 - 23/1 Sunday No access L3 (no ventilation)

141 24/12/10 ALICE planning meeting141 Activities in MNF - Week 3 - 23/1 Sunday No access L3 (no ventilation)

142 Day-by-day schedule UX25 and MNF - Wk 4

143 24/12/10 ALICE planning meeting143 Activities in UX25 - Week 4 - 24/1 Monday No access L3 (no ventilation) L3 and PMD ventilation Maintenance UX25, Muon TRK-TRG ventilation SPD cooling Reconnect pipes

144 24/12/10 ALICE planning meeting144 Activities in MNF - Week 4 - 24/1 Monday PMD: replacement electronics chains No access L3 (no ventilation) PMD ventilation SPD cooling SPD: test with dummy sector

145 24/12/10 ALICE planning meeting145 Activities in UX25 - Week 4 – 25/1 Tuesday L3 and PMD ventilation No access L3 (no ventilation) Maintenance UX25, Muon TRK-TRG ventilation

146 24/12/10 ALICE planning meeting146 Activities in MNF - Week 4 - 25/1 Tuesday PMD: replacement electronics chains SPD cooling PMD ventilation No access L3 (no ventilation)

147 24/12/10 ALICE planning meeting147 Activities in UX25 - Week 4 - 26/1 Wednesday Green bridge TPC FEC

148 24/12/10 ALICE planning meeting148 Activities in MNF - Week 4 - 26/1 Wednesday PMD: replacement electronics chains SPD cooling

149 24/12/10 ALICE planning meeting149 Activities in UX25 - Week 4 - 27/1 Thursday Green bridge TPC FEC

150 24/12/10 ALICE planning meeting150 Activities in MNF - Week 4 - 27/1 Thursday SPD cooling

151 24/12/10 ALICE planning meeting151 Activities in UX25 - Week 4 - 28/1 Friday MNF wall TPC FEC

152 24/12/10 ALICE planning meeting152 Activities in MNF - Week 4 - 28/1 Friday PMD: replacement electronics chains SPD cooling

153 24/12/10 ALICE planning meeting153 Activities in UX25 - Week 4 - 29/1 Saturday MNF wall

154 24/12/10 ALICE planning meeting154 Activities in MNF - Week 4 - 29/1 Saturday

155 24/12/10 ALICE planning meeting155 Activities in UX25 - Week 4 - 30/1 Sunday

156 24/12/10 ALICE planning meeting156 Activities in MNF - Week 4 - 30/1 Sunday

157 24/12/10 ALICE planning meeting157 VIP visits 7/12 14:00 to 15:00: portuguese press visit to CERN. 10 persons.F.Baltasar 15/12 16:30: finance and Council Delegates 22/12: RIKEN RIBF Accelerator technical coordination group. Ken Oyama 10/1 (16:15): Mr Herman Josef Lamberti, Deutsche Bank, Germany

158 24/12/10 ALICE planning meeting158 AOB Peter Ginter: wk 4