1 ALICE planning meeting 17.12.2010

2 17/12/10 ALICE planning meeting2 Outline ALICE Christmas break schedule –Access UX25, L3 and MNF Services interruption –Gas, cooling and electricity –DAQ and DCS plans Detectors activities Day-by-day schedule wks 51-4 VIP visits AOB

3 17/12/10 ALICE planning meeting3 Christmas break schedule Start on Tuesday, 7 th December. End on Friday, 18 th February Plan: –Open both L3 doors –Installation of 3 TRD and 6 EMCal modules

4 17/12/10 ALICE planning meeting4 ALICE Christmas break schedule OpenExperiment TRD EMCal CloseExperiment Open L3 doors Close L3 doors

5 17/12/10 ALICE planning meeting5 Access restrictions The reasons to restrict the access are: –Handling of shielding blocks –Lowering of heavy structures (yellow-platform, TRD and EMCal rotators and modules) –Installation of EMCal modules –Removal of L3 ventilation –Evacuation tests –… The access restrictions concern the UX25 cavern, MNF, L3 and CRs SLIMOS shifts still missing in wks 49-50 and 4-5 Indications are given (next slides) concerning the access during the whole break – more precise info will be discussed at 5 o’clock daily meetings

6 17/12/10 ALICE planning meeting6 UX25 access Rules for access restrictions: Removal/installation of shielding (restriction includes RB24 triplets) PX24 blocks: no access CR5 and UX25 PX24 beams (35t): no access CR1-5, Expo, and UX-25 All other blocks: no access to UX-25 LHC evacuation test (7/12 after 18:00 and 24/12 tbc) – no access UX25 Gas functional test (10/12 - 2 hrs) – no access UX25 and CR1-5 AUG test (20/1) (Arrêt Urgence General – General Emergency Stop) – no access UX25 DSO test (12-13/1) (Department Safety Officer) – no access UX25 No access SX2 during manipulation of blocks in SX2 (except ACR and WRs)

7 17/12/10 ALICE planning meeting7 L3 (and MNF) access EMCal No Ventilation Wks 50 and 4: access (TPC) to be coordinated with TC (transport) Wks 1-2: no access during EMCal SMs insertion inside L3 (see day-by-day) When moving from low-beta to yellow platform: no access to MNF When inserting the module: no access L3 and MNF Watcher needed in wk 49 and from wk 4 onwards Wk 6 or 7 (tbd): Kr calibration – TPC T stability (all interventions to be agreed by TC/RC) 31 Evac. No Ventilation 243 No Ventilation 13 7

8 Services interruption

9 17/12/10 ALICE planning meeting9 Maintenance gas systems Functional tests New gas monitoring 13-15/12: Stop N2, CO2, Neon, Ar (24 hours max N2, CO2 and Neon) TRD backup (N2 bottle in CR5) – HMPID backup (Ar bottle in SG2) 11/1 (tbc, date must fall in the cooling stop): Stop C2H2F4, Isobutane, CH4 and SF6 -> will affect TOF and purifiers (no Ar/H2) 13 Flowmeters

10 17/12/10 ALICE planning meeting10 Gas system status over Christmas Albin TPC: flush CO2 TRD: ON TOF: ON – stop 11-12/12 and during cooling stop (KNF pump stopped) HMPID: ON (Ar backup) PHOS: N2 flushing PMD: ON (except 11-12/12 – gas stop) Muon TRK: backup CO2 Muon TRG: backup Ar No flammable gases from 7 Dec until 21 Jan PM (after maintenance L3 ventilation)

11 17/12/10 ALICE planning meeting11 Maintenance cooling units Cooling Plants and Primary Network Cooling towers Maintenance on production network. No primary water from 12/1 (PM) to 21/1 CR1-2-3, the Wiener PS and detector cooling plants affected (plants can RUN, but no cooling power). Part of DCS will be kept running Maintenance and consolidation 17 21 12 TOF/PHOS EMC HMPID SPD TPC 10 Maintenance on cooling plants. Replacement of pneumatic actuators for TOF/TRD/TPC plants + TOF/PHOS flowmeter. CP will be stopped during maintenance SSD/SDD TRD TPC RR

12 17/12/10 ALICE planning meeting12 Maintenance ventilation units SG2 UX25, Muon TRK-TRG 17 12 UX25, Muon TRK- TRG L3

13 17/12/10 ALICE planning meeting13 Safety and electrical systems PX24 fire detect. 20 UX25 fire detect. + red phones UPS AUG UPS DSO Evacuation DSS SNIFFER mainten. Auto-transfert Evacuation Early morning/late evening (tbc) PX24 PAD LACS doors 31

14 17/12/10 ALICE planning meeting14 LHC evacuation tests (7/12 after 18:00 and 24/12 tbc) –no access UX25 EN/EL: interruption on auto-transfert network (9/12 from 07:00 till 07:05): –all wall outlets will be interrupted –including all non-UPS outlets in the ACR (so essentially all WRs) –including outlets SXL2, offices and barracks –non-UPS power for the detector cooling plants will be interrupted –power to all gas systems will be interrupted –the UPS powered systems will not be affected, but will run on batteries for the 2 min. interruption –the electronics racks in the cavern and CRs will not be affected. –See https://edms.cern.ch/file/1106913/1/ENNC_2010_196.pdf https://edms.cern.ch/file/1106913/1/ENNC_2010_196.pdf DSS modification (13/1) –Will stop the full DSS, trigger all interlocks, including stopping power to all racks EN/EL: AUG Test (20/1) (Arrêt Urgence General – General Emergency Stop) –Major electrical perturbation. Also ACR affected Safety and electrical systems Impact on ALICE

15 17/12/10 ALICE planning meeting15 DAQ upgrade plans 21 st Dec PM till the 04 th Jan included –The DAQ will be OFF during the CERN closure. –The ACR PCs will be left ON to give access to the DCS for the detectors teams who need it. 5 th to the 11 th of January included –DAQ restarted on the first working day for 1 week. The DAQ will be switched ON with the present version of all software. Allow a quick commissioning after the installation of new detector modules or the intervention on existing detectors. 12 th to the 23 rd Jan included –The DAQ will be OFF during the cooling interruption at P2. –DAQ renovated (see TB December) 24 th January –The DAQ will be ON again. It will run under SLC5 64 bits unless there would be an unexpected key problem. The electronic logbook will remain available during the whole period. When the DAQ will be OFF, it will be running in the DAQ lab in Meyrin. There will be a few hours of interruption to switch from P2 to Meyrin and back. Pierre/Uli

16 17/12/10 ALICE planning meeting16 DCS plans Baseline: DCS will be operational all times where technically possible –With ‘best effort’ support –With access restrictions during CERN End-of-Year closure (22/12 – 4/1) Many activities and upgrades are planned –Will be coordinated with individual detectors to minimise impact –For central systems, as much as possible in shadow of other perturbations (e.g. cooling stop) –Perturbations (e.g. for reboots etc.) cannot be excluded Detectors are invited to communicate ‘critical periods’, with services needed –Will try to cater for detector needs as much as possible Known perturbations: –Tue 7/12 10:00 – 12:00, interruptions of the GPN link to/from P2 Upgrade of router, test impact on ALICE –Wk50 (13-17/12) – major updates to all PC (many perturbations to be expected) –12/1 – 21/1 (cooling stop), only minimal central services. All detector DCS switched off, except for special requests and if cooling power allows More detailed planning at weekly and daily meetings André / Peter

17 17/12/10 ALICE planning meeting17 DCS plans (details) Wk 50 –Mon 13/12 – Fri 17/12 (daytime): SW upgrades and patches to all systems (Operating system and PVSS) Delayed/extended due to problems with automatic PVSS upgrade procedure (several manual operations needed) Systems unavailable for short (~hrs) periods, frequent reboots –Support to detectors restarting/testing their systems after upgrades Detectors shall test functionality as much as possible Wk 51 –Contingency for system upgrades –Support to detectors restarting/testing their systems after upgrades Detectors shall test functionality as much as possible –Tue 21/12 PM: Limit access to DCS cluster during end-of-year closure Register with your SRC if you require access (see message Peter 2/12/2010) Wk 52 – Wk 01 –Only ‘best effort’ support during CERN closure Wk 02 –Wed 12/01 – (cooling intervention) shutdown of detector systems except special requests, within limits of cooling power André / Peter

18 17/12/10 ALICE planning meeting18 Access request Cavern and surface You should submit an ADI and a task procedure Two persons minimum Work breakdown structure – risk associated at each step ADI https://edh.cern.ch/Document/ADI Task procedure Template EDMS 1103355 Attach task procedure

19 Detectors activities

20 17/12/10 ALICE planning meeting20 EMCal Status of modules: –6 modules in SXL2 Test station installed in SXL2 Requiring a lot of access to connect everything up, test, and debug as they commission the new SMs –Low voltage, high voltage (CR4), and DAQ operating as much as possible during the installation period in January.

21 17/12/10 ALICE planning meeting21 EMCal Surveys Zero measurement (wk 51-52), after insertion of 1 st module and after the insertion of 2 nd module: –A-side: CALframe feet and rails + modules (adaptors) –C-side (photogrammetry - 1/2 day) After insertion of 3 rd, after insertion of 4 th and after insertion of 5 th module: –A-side: points chosen depending on results previous survey –C-side: with theodolite from A-side (or full photogrammetry, depending on results previous survey) After insertion of 6 th module: –A-side: full –C-side: full

22 17/12/10 ALICE planning meeting22 PMD Wk 50: –Lift CROCUS (in order to open L3 doors) - can be done by P2 technicians –disconnect cables (after 16/12) Wk 51 (20/1): move PMD in parking position (Pieter) Wks 51-4: repair electronics chains –Need Ar/CO2 at all times Wks 5-6 (night): access to CROCUS (doors closed, use CROCUS platform) February: move PMD to final position Wk 6: survey (transfer survey network to miniframe (Antje)) Wks 1-3 SPIE: new air cooling system – major installation work in January (should be done by end January) –Nacelle HAULOTTE needed

23 17/12/10 ALICE planning meeting23 TOF/PHOS TOF: –HV hardware checks on SM13 (December) –TRM replacement (14 TRMs on the A side) (3/01 – 12/01) –Replacement DC-DC (with no LV spare channels): 16/12 (after 18:00) PHOS: (A.Vinogradow at CERN 1/12 end January) –Investigate module 2 pedestal issues –Try to understand behavior of unstable branch in Module 3 –Remake ISEG crate to connect to the hardware interlock –Fear presence of ice inside cold part - could melt when warming-up crystals Gilda/Yury

24 17/12/10 ALICE planning meeting24 Muon TRG RPC Detector/gas system: –Check gas tightness on few RPC detectors - need nacelle INSIDE and OUTSIDE (Verify availability HAULOTTE) (~3 days between January 10-18) –Upgrade Sensor gas humidity and pressure regulator (CR5, schedule to be defined with the gas team) –Replace few RPC modules with high current: under discussion Electronics: –Maintenance Local decision electronics (December 8 th after 18:00) –Upgrade FE threshold distributors, higher segmentation (level 4 gangway, December 8 th after 18:00) –Upgrade firmware DARC and Regional board in order to speed up MTR decision electronics configuration (wk 6, after the DAQ upgrade) Pascal/Ermanno/Paolo

25 17/12/10 ALICE planning meeting25 Muon TRK plans December: CROCUS firmware upgrade (protection against spurious busy reset signal): –Access to Crocus, Dipole and FASS. Need nacelle wk 49 High occupancy bus patches (under discussion): –Remove one "bad" slat (and replace by one spare) to test it in lab –Access to Dipole and to muon side with nacelle in December –Depending on the results, fix all remaining “bad” slats in January January (from wk 2): replacement 2 quadrants ST2 with faulty wires: –Test spare quadrants in lab (December) –Work scheduled during January 6 - 27, 2011 (access to FASS) –Crane needed on 11th and 18th January –Discussion on 6th January Ermanno/Herve

26 17/12/10 ALICE planning meeting26 ZDC plans Check platform displacement with survey –One week – depending on surveyors availability Paolo

27 17/12/10 ALICE planning meeting27 SPD cooling plans Wk 49 (8/12 after 18:00): cut pipes in order to open the doors Wks 2-3 (during cooling stop): wash 4 bad sectors (machine installed on I-side, close to HMPID pump). Access to the outer side of MNF (side I) to work on the heater of sector 0 (nacelle or scaffolding needed) Wks 3-4 (as soon as the door is closed): reconnect temporarily pipes and test with dummy sector inside MNF (in parallel with shielding in wk 4)

28 17/12/10 ALICE planning meeting28 SSD/SDD SSD: Ton: remove a cooling pipe from SSD corrosion test setup (week 2) Replacement CAEN module (C-side) + repair bad temperature signal at the C-side (week 2) SDD: Calibration of 78 pressure sensors in L3 and on miniframe (January 12 to 14)

29 17/12/10 ALICE planning meeting29 T0 Activities planned from 7-19 December (after 18:00): –Check/repair the amplifiers from A and C side (inside L3) –Check the signal cables from A-side –Check/repair fast electronics modules (racks O18-19) –Need possibility to do standalone runs in parallel

30 17/12/10 ALICE planning meeting30 TRD installation - weeks 51, 52 4 modules at P2 (SM2, SM11, SM 15 and SM16) Installation sequence: 16 → 15 → 11 (or 16 → 11 → 15) 2 technicians (Philippe and Didier) + Survey (Nail from 6/12) + TC permanently at P2 Connection done right after installation Survey: –Space-frame deformations and displacement of beampipe (flange), miniframe and TPC feet. Before-after each insertion –Modules (2 points/SM on 4/7 SM) in wk 50 –Modules (3 points/SM on 10/10 SM) after EMCal (wk 3)

31 17/12/10 ALICE planning meeting31 TRD Week 49: –LV Wiener ~70 PSU Back-Plane modifications (to improve mechanical stability, same as TPC applied already) –Netgear switches replacements (1 day) –LV line fixation: installation of improved patch panels on front of module (C-side) and replacing cables Repair pretrigger (A-side, below PMD) – after 20/12 Week 1: –Finalizing connections, start commissioning Week 2: –Stable running with cosmics 3 to 4 weeks in January or February: –Stable running with cosmics for alignment and with Krypton for gain calibrations (to be still discussed)

32 17/12/10 ALICE planning meeting32 TPC Recover all water inside cooling plant (week 50) Replacement of 15 damaged FECs (equally distributed A-C sides) –~3 days per FEC. Therefore, we would like to use all available time slots where access to the L3 is possible –At the end of this activity we will need a period of about 2 weeks where all aforesaid systems are available for final verification, and access to the TPC in case something is not working correctly. Kr data taking at the end of the shutdown (1 week)

33 17/12/10 ALICE planning meeting33 TPC Replacement of the laser Start the dismantling of the Spectron laser (week 50, Th-Sat after 18:00): –dismount back wall of laser hut (help of P2 technician) –stop cooling water (help of P2 technician) –prepare new water connection (electrical power should be OK) Install new Ekspla laser (week 1): –remove old laser and install new (use crane to transport laser) –connect cooling water (help of P2 technician) –reinstall back wall (maybe after cutting a hole in it) Testing and alignment of new laser (week 2): –possibility to run laser behind closed doors (inside hut) –maybe install laser tube temporarily and shoot into TPC whenever –compatible with other installation work Possible further testing and adjustment (week 3) Borge

34 17/12/10 ALICE planning meeting34 ACORDE Check some ACORDE modules (PMTs optical conections, connectors, etc) above the magnet The plan is to start this activities after the second week of January 2011

35 17/12/10 ALICE planning meeting35 Other activities SPIE + CV: refurbishment ITS dehumidifier in CR – February –New unit at P2 in January –Repair leak (replace leaking part – transport needed) –Recirculation air –Add flowmeter (connect to ELMB: Frederick) EN-EL (T.Bourrel): motorize L3-Dipole-Miniframe circuit breaker. –VIC 16/12 10:30 SPIE: cabling UX25-CR4 – 17/1 New magnet emergency buttons + flashing lights L3 and dipole Frederick: humidity sensor L3 ventilation (extraction) + redo CTP connectors Intervention on cavern lift –One day stop – no access to UX25. To be scheduled

36 17/12/10 ALICE planning meeting36 Other activities Google propose to produce a custom Streetview application for CERN showing both outside and underground areas –Visit Tuesday 21 December at 16:15 Philippe: replace rack filters during cooling stop. Install temporary line PHOS cooling (PS rack and crystal cooling plant)

37 17/12/10 ALICE planning meeting37 Magnet control upgrade Wk 49: nous devons intervenir dans la MCR pour: –changement des alimentations 24V et 48 V des systèmes MSS et MCR (préventif) –changement des modules convertisseurs PT100 des hots points du Solénoïde (correctif suite à deux incidents ayant entrainés l'arrêt du Solénoïde) et en UX25, comme Philippe Bouvier l'a déjà signalé: –recâblage des AU du dipôle et du Solénoïde –signalisation du champ magnétique du dipôle et du Solénoïde Nous étudions toujours une solution pour le monitoring des températures du Solénoïde. L'arrêt de fin d'année va permettre de faire une meilleure approche de ce qui est existant en UX25. En ce qui concerne l'alimentation électrique de la MCR, nous dépendons actuellement d'une seule source de courant sous UPS avec secours diesel. Afin d'établir une redondance pour l'alimentation de la MCR je souhaiterais installer une seconde source d'alimentation sous UPS. Je sais qu'une étude est faite à ALICE pour augmenter la puissance des UPS existants en 2012. Je souhaiterais que cette demande soit incluse pour le calcul de puissance des nouveaux UPS (besoin pour la MCR: 16A en monophasé) Pascal

38 Day-by-day schedule UX25 and MNF - Wk 51

39 17/12/10 ALICE planning meeting39 Activities in UX25 - Week 51 - 20/12 Monday TRD and EMCal Survey Prepare TRD 16 installation - PM EMCal Survey (1/2 day) PMD ventilation Including installation BBF rails SR16-15 GS/ASE: PX24 fire detection maintenance TPC FEC YP rails

40 17/12/10 ALICE planning meeting40 Activities in MNF - Week 51 - 20/12 Monday TPC cooling pipes (Yannick) - AM Move PMD in parking position

41 17/12/10 ALICE planning meeting41 Activities in UX25 - Week 51 - 21/12 Tuesday Install TRD 16 PMD ventilation GS/ASE: PX24 fire detection maintenance TPC FEC Google Streetview visit (5 people). 16:15

42 17/12/10 ALICE planning meeting42 Activities in MNF - Week 51 - 21/12 Tuesday PMD: replacement electronics chains

43 17/12/10 ALICE planning meeting43 Activities in UX25 - Week 51 - 22/12 Wednesday TRD Survey Prepare TRD 15 installation Connect TRD 16 Visit: RIKEN RIBF Accelerator technical coordination group. Ken Oyama

44 17/12/10 ALICE planning meeting44 Activities in MNF - Week 51 22/12 Wednesday PMD: replacement electronics chains

45 17/12/10 ALICE planning meeting45 Activities in UX25 - Week 51 - 23/12 Thursday Install TRD 15 Connect TRD 16 TRD Survey

46 17/12/10 ALICE planning meeting46 Activities in MNF - Week 51 - 23/12 Thursday PMD: replacement electronics chains

47 17/12/10 ALICE planning meeting47 Activities in UX25 - Week 51 - 24/12 Friday LHC evacuation test. no access UX25

48 17/12/10 ALICE planning meeting48 Activities in MNF - Week 51 - 24/12 Friday LHC evacuation test. no access UX25

49 17/12/10 ALICE planning meeting49 Activities in UX25 - Week 51 - 25/12 Saturday Christmas day

50 17/12/10 ALICE planning meeting50 Activities in MNF - Week 51 - 25/12 Saturday PMD: replacement electronics chains

51 17/12/10 ALICE planning meeting51 Activities in UX25 - Week 51 - 26/12 Sunday TRD team at CERN: 26 to 30/12

52 17/12/10 ALICE planning meeting52 Activities in MNF - Week 51 - 26/12 Sunday PMD: replacement electronics chains

53 Day-by-day schedule UX25 and MNF - Wk 52

54 17/12/10 ALICE planning meeting54 Activities in UX25 - Week 52 - 27/12 Monday Connect TRD 15 Prepare TRD 11 installation Including installation BBF rails SR11 TRD Survey Diego at CERN (noon)

55 17/12/10 ALICE planning meeting55 Activities in MNF - Week 52 - 27/12 Monday PMD: replacement electronics chains

56 17/12/10 ALICE planning meeting56 Activities in UX25 - Week 52 - 28/12 Tuesday Connect TRD 15 Prepare TRD 11 installation

57 17/12/10 ALICE planning meeting57 Activities in MNF - Week 52 - 28/12 Tuesday PMD: replacement electronics chains

58 17/12/10 ALICE planning meeting58 Activities in UX25 - Week 52 - 29/12 Wednesday Install TRD 11 TRD Survey

59 17/12/10 ALICE planning meeting59 Activities in MNF - Week 52 29/12 Wednesday PMD: replacement electronics chains

60 17/12/10 ALICE planning meeting60 Activities in UX25 - Week 52 - 30/12 Thursday Connect TRD 11 TRD Survey EMCal infrastructure Move EMCal rotator + SM5 onto low beta platform, and perform handling test

61 17/12/10 ALICE planning meeting61 Activities in MNF - Week 52 - 30/12 Thursday PMD: replacement electronics chains

62 17/12/10 ALICE planning meeting62 Activities in UX25 - Week 52 - 31/12 Friday EMCal infrastructure

63 17/12/10 ALICE planning meeting63 Activities in MNF - Week 52 - 31/12 Friday PMD: replacement electronics chains

64 17/12/10 ALICE planning meeting64 Activities in UX25 - Week 52 - 1/1/2011 Saturday New Year day

65 17/12/10 ALICE planning meeting65 Activities in MNF - Week 52 - 1/1/2011 Saturday New Year day

66 17/12/10 ALICE planning meeting66 Activities in UX25 - Week 52 - 2/1 Sunday

67 17/12/10 ALICE planning meeting67 Activities in MNF - Week 52 - 2/1 Sunday

68 Day-by-day schedule UX25 and MNF - Wk 1 - 2011

69 17/12/10 ALICE planning meeting69 Activities in UX25 - Week 1 - 3/1 Monday Connect TRD 11 PMD ventilation Install EMCal 40deg-C (PM) Lower SM6 onto low beta platform SM5 TOF TRM PH-DT: new gas monitoring system (no fresh gas injection whole week) (tbc) Move HAULOTTE TPC FEC Laser Install new Ekspla laser

70 17/12/10 ALICE planning meeting70 Activities in MNF - Week 1 - 3/1 Monday PMD: replacement electronics chains

71 17/12/10 ALICE planning meeting71 Activities in UX25 - Week 1 - 4/1 Tuesday PMD ventilation EMC Survey EMC Survey (AM) Install EMCal 40deg-A (PM) SM6 TOF TRM Laser TPC FEC

72 17/12/10 ALICE planning meeting72 Activities in MNF - Week 1 - 4/1 Tuesday PMD: replacement electronics chains

73 17/12/10 ALICE planning meeting73 Activities in UX25 - Week 1 - 5/1 Wednesday TPC RR cooling RAMSES: reinstallation of Data Acquisition modules CR5 Maintenance UPS ESS307/2X (transparent) GS/ASE: UX25 fire detection maintenance PMD ventilation EMC Survey Lower SM7 onto low beta platform TOF TRM Laser TPC FEC

74 17/12/10 ALICE planning meeting74 Activities in MNF - Week 1 - 5/1 Wednesday PMD: replacement electronics chains

75 17/12/10 ALICE planning meeting75 Activities in UX25 - Week 1 - 6/1 Thursday TPC cooling PMD ventilation Install EMCal 60deg-C SM7 Lower SM8 onto low beta platform EMC Survey TOF TRM Laser GS/ASE: UX25 fire detection + red phones maintenance TPC FEC

76 17/12/10 ALICE planning meeting76 Activities in MNF - Week 1 - 6/1 Thursday PMD: replacement electronics chains

77 17/12/10 ALICE planning meeting77 Activities in UX25 - Week 1 - 7/1 Friday TPC cooling PMD ventilation Install EMCal 60deg-A SM8 EMC Survey TOF TRM Laser GS/ASE: UX25 fire detection + red phones maintenance TPC FEC

78 17/12/10 ALICE planning meeting78 Activities in MNF - Week 1 - 7/1 Friday PMD: replacement electronics chains

79 17/12/10 ALICE planning meeting79 Activities in UX25 - Week 1 - 8/1 Saturday Laser

80 17/12/10 ALICE planning meeting80 Activities in MNF - Week 1 - 8/1 Saturday

81 17/12/10 ALICE planning meeting81 Activities in UX25 - Week 1 - 9/1 Sunday

82 17/12/10 ALICE planning meeting82 Activities in MNF - Week 1 - 9/1 Sunday

83 Day-by-day schedule UX25 and MNF - Wk 2

84 17/12/10 ALICE planning meeting84 Activities in UX25 - Week 2 - 10/1 Monday PMD ventilation PH-DT: new gas monitoring system (no fresh gas injection whole week) (tbc) TPC cooling VIP visit (Mr Herman Josef Lamberti, Deutschen Bank). From 15:30 Lower SM9 onto low beta platform Muon TRG: RPC Check gas tightness on few RPC detectors (need both nacelles) SDD/ SSD Laser Testing and alignment of new laser HAULOTTE needed 1 day (if possible to move it) TPC FEC SDD: calibration of 78 pressure sensors (10-12/1) SSD: replacement CAEN module (C-side) + repair bad temperature signal (C-side)

85 17/12/10 ALICE planning meeting85 Activities in MNF - Week 2 - 10/1 Monday PMD: replacement electronics chains

86 17/12/10 ALICE planning meeting86 Activities in UX25 - Week 2 – 11/1 Tuesday PMD ventilation TPC cooling SSD/SDD cooling Visit (30 students. Peter Glaessel and Kai Schweda) Muon TRG: RPC SPD cooling Wash 4 bad sectors + repair heater (nacelle) Laser TPC FEC PH-DT: new gas monitoring: Stop C2H2F4, Isobutane, CH4 and SF6 (tbc)

87 17/12/10 ALICE planning meeting87 Activities in MNF - Week 2 - 11/1 Tuesday PMD: replacement electronics chains

88 17/12/10 ALICE planning meeting88 Activities in UX25 - Week 2 - 12/1 Wednesday PMD ventilation Cooling towers maintenance (start 14:00) (No primary water) SNIFFER maintenance Install EMCal 80deg-C SM9 Lower SM10 onto low beta platform EMC Survey Muon TRG: RPC SPD cooling SDD/ SSD Laser SSD: removal of cooling pipe from corrosion test setup TPC FEC Cleaning rack filters (Philippe) Maintenance UPS EBS106/2X and EBS128/2X (transparent)

89 17/12/10 ALICE planning meeting89 Activities in MNF - Week 2 - 12/1 Wednesday PMD: replacement electronics chains

90 17/12/10 ALICE planning meeting90 Activities in UX25 - Week 2 - 13/1 Thursday PMD ventilation Cooling towers maintenance (No primary water) HMPID cooling RAMSES: radiation source tests EN/CV: maintenance SG2 ventilation DSS modification. Will stop the full DSS, trigger all interlocks, including stopping power to all racks SNIFFER maintenance Install EMCal 80deg-A SM10 EMC Survey SPD cooling SDD TPC FEC Visit: Danish high school class (C. Søgaard)

91 17/12/10 ALICE planning meeting91 Activities in MNF - Week 2 - 13/1 Thursday PMD: replacement electronics chains

92 17/12/10 ALICE planning meeting92 Activities in UX25 - Week 2 - 14/1 Friday PMD ventilation Cooling towers maintenance (No primary water) SPD cooling SNIFFER maintenance EN/CV: maintenance SG2 ventilation RAMSES: radiation source tests VAC Start pumping out EMC Survey SPD cooling SDD TPC FEC LACS: revision UX25 access doors Removal EMCal infrastructure

93 17/12/10 ALICE planning meeting93 Activities in MNF - Week 2 - 14/1 Friday PMD: replacement electronics chains

94 17/12/10 ALICE planning meeting94 Activities in UX25 - Week 2 - 15/1 Saturday Cooling towers maintenance (No primary water)

95 17/12/10 ALICE planning meeting95 Activities in MNF - Week 2 - 15/1 Saturday

96 17/12/10 ALICE planning meeting96 Activities in UX25 - Week 2 - 16/1 Sunday Cooling towers maintenance (No primary water)

97 17/12/10 ALICE planning meeting97 Activities in MNF - Week 2 - 16/1 Sunday

98 Day-by-day schedule UX25 and MNF - Wk 3

99 17/12/10 ALICE planning meeting99 Activities in UX25 - Week 3 - 17/1 Monday TOF/PHOS/ EMC cooling Cooling towers maintenance (No primary water) Maintenance UX25, Muon TRK-TRG ventilation SPD cooling SPIE: cabling UX25-CR4 TRD/EMC Survey PMD ventilation TPC FEC Removal EMCal infrastructure

100 17/12/10 ALICE planning meeting100 Activities in MNF - Week 3 - 17/1 Monday PMD: replacement electronics chains

101 17/12/10 ALICE planning meeting101 Activities in UX25 - Week 3 – 18/1 Tuesday Cooling towers maintenance (No primary water) Maintenance UX25, Muon TRK-TRG ventilation SPD cooling TOF/PHOS/ EMC cooling TRD/EMC Survey TPC FEC

102 17/12/10 ALICE planning meeting102 Activities in MNF - Week 3 - 18/1 Tuesday PMD ventilation PMD: replacement electronics chains

103 17/12/10 ALICE planning meeting103 Activities in UX25 - Week 3 - 19/1 Wednesday Cooling towers maintenance (No primary water) Maintenance UX25, Muon TRK-TRG ventilation Maintenance harmonic filter (EOF128/2X) TOF/PHOS/ EMC cooling TRD/EMC Survey PMD ventilation TPC FEC

104 17/12/10 ALICE planning meeting104 Activities in MNF - Week 3 - 19/1 Wednesday PMD: replacement electronics chains

105 17/12/10 ALICE planning meeting105 Activities in UX25 - Week 3 - 20/1 Thursday Cooling towers maintenance (No primary water) Maintenance L3, UX25, Muon TRK-TRG ventilation AUG test. No access UX25

106 17/12/10 ALICE planning meeting106 Activities in MNF - Week 3 - 20/1 Thursday

107 17/12/10 ALICE planning meeting107 Activities in UX25 - Week 3 - 21/1 Friday Restart primary water Maintenance L3, UX25, Muon TRK-TRG ventilation Close doors No access L3 (no ventilation)

108 17/12/10 ALICE planning meeting108 Activities in MNF - Week 3 - 21/1 Friday PMD: replacement electronics chains No access L3 (no ventilation)

109 17/12/10 ALICE planning meeting109 Activities in UX25 - Week 3 - 22/1 Saturday No access L3 (no ventilation) Close doors

110 17/12/10 ALICE planning meeting110 Activities in MNF - Week 3 - 22/1 Saturday No access L3 (no ventilation)

111 17/12/10 ALICE planning meeting111 Activities in UX25 - Week 3 - 23/1 Sunday No access L3 (no ventilation)

112 17/12/10 ALICE planning meeting112 Activities in MNF - Week 3 - 23/1 Sunday No access L3 (no ventilation)

113 Day-by-day schedule UX25 and MNF - Wk 4

114 17/12/10 ALICE planning meeting114 Activities in UX25 - Week 4 - 24/1 Monday No access L3 (no ventilation) L3 and PMD ventilation Maintenance UX25, Muon TRK-TRG ventilation SPD cooling Reconnect pipes

115 17/12/10 ALICE planning meeting115 Activities in MNF - Week 4 - 24/1 Monday PMD: replacement electronics chains No access L3 (no ventilation) PMD ventilation SPD cooling SPD: test with dummy sector

116 17/12/10 ALICE planning meeting116 Activities in UX25 - Week 4 – 25/1 Tuesday L3 and PMD ventilation No access L3 (no ventilation) Maintenance UX25, Muon TRK-TRG ventilation

117 17/12/10 ALICE planning meeting117 Activities in MNF - Week 4 - 25/1 Tuesday PMD: replacement electronics chains SPD cooling PMD ventilation No access L3 (no ventilation)

118 17/12/10 ALICE planning meeting118 Activities in UX25 - Week 4 - 26/1 Wednesday TPC FEC Green bridge

119 17/12/10 ALICE planning meeting119 Activities in MNF - Week 4 - 26/1 Wednesday PMD: replacement electronics chains SPD cooling

120 17/12/10 ALICE planning meeting120 Activities in UX25 - Week 4 - 27/1 Thursday TPC FEC Green bridge

121 17/12/10 ALICE planning meeting121 Activities in MNF - Week 4 - 27/1 Thursday SPD cooling

122 17/12/10 ALICE planning meeting122 Activities in UX25 - Week 4 - 28/1 Friday TPC FEC MNF wall

123 17/12/10 ALICE planning meeting123 Activities in MNF - Week 4 - 28/1 Friday PMD: replacement electronics chains SPD cooling

124 17/12/10 ALICE planning meeting124 Activities in UX25 - Week 4 - 29/1 Saturday MNF wall

125 17/12/10 ALICE planning meeting125 Activities in MNF - Week 4 - 29/1 Saturday

126 17/12/10 ALICE planning meeting126 Activities in UX25 - Week 4 - 30/1 Sunday

127 17/12/10 ALICE planning meeting127 Activities in MNF - Week 4 - 30/1 Sunday

128 17/12/10 ALICE planning meeting128 VIP visits 7/12 14:00 to 15:00: portuguese press visit to CERN. 10 persons.F.Baltasar 15/12 16:30: finance and Council Delegates 22/12: RIKEN RIBF Accelerator technical coordination group. Ken Oyama 10/1 (16:15): Mr Herman Josef Lamberti, Deutsche Bank, Germany

129 17/12/10 ALICE planning meeting129 AOB Peter Ginter: wk 4