Presentation is loading. Please wait.

Presentation is loading. Please wait.

The EMMA Project Rob Edgecock STFC Rutherford Appleton Laboratory & Huddersfield University.

Similar presentations


Presentation on theme: "The EMMA Project Rob Edgecock STFC Rutherford Appleton Laboratory & Huddersfield University."— Presentation transcript:

1 The EMMA Project Rob Edgecock STFC Rutherford Appleton Laboratory & Huddersfield University

2 Outline Outline Why we needed to build EMMA How we got to where we are Design of the machine Construction Commissioning Conclusions

3 Motivation for EMMA Motivation for EMMA EMMA: linear non-scaling Fixed Field Alternating Gradient accelerator ~ cyclotron Strongly focussed cf cyclotrons

4 Motivation for EMMA Motivation for EMMA Neutrino Factory Linear non-scaling FFAG - invented 1997/9, C.Johnstone et al - for muon acceleration in a Neutrino Factory Acceleration Must be fast Large acceptance

5 Motivation for EMMA Motivation for EMMA /p Path length /p Travel time Linear non-scaling FFAGs: - invented 1997/9 - for muon acceleration in a Neutrino Factory - large dynamic aperture - small orbit excursion – higher frequency RF - CW acceleration

6 Motivation for EMMA Motivation for EMMA Serpentine, bucketless, asynchronous, etc acceleration 27 14 8 Fast resonance crossings

7 Motivation for EMMA Motivation for EMMA Realised early on:  Other potential applications: - hadron therapy - ADSR - other high power proton beam applications  One or two issues: - tiny momentum compaction - unique longitudinal dynamics - possible transverse dynamics problems - resonance crossings - constraints on construction - standard tracking codes not applicable - purpose built codes need benchmarking Must build one! Hence, EMMA

8 EMMA Evolution EMMA Evolution NS-FFAGs invented 1997/99 First mention of “EMMA”: FFAG03/NuFact03 - 10-20 MeV electron model of muon FFAG Clear early on three things required:  funding  an electron beam  space Contacted MP in 2004  SRS injector  ERLP Developing ASTeC/DL from this point

9 EMMA Location EMMA Location Could meet all the EMMA requirements. Space available in the hall. All the required skills for design and construction available in ASTeC and at DL. International Collaboration BNL, CERN, CI, FNAL, JAI, LPSC Grenoble, STFC, TRIUMF

10 Funding Funding First punt: FP6 NEST  April 2004  Very good review  Except – not a good match to the scheme  Maximum 2MEUR available Good practice for: RCUK Basic Technology Fund  Consortium building 2004-2006  Led to BASROC & CONFORM, PI Roger Barlow  First proposal: 4 th April 2006  Serious work started for second proposal, submitted in July  Work led by STFC  Centred on ASTeC and TD at DL  Funded from 1 st April 2007

11 EMMA Layout EMMA Layout Section of ALICE Injection line: transports beam from ALICE to EMMA EMMA ring Diagnostics beam line EMMA 10-20 MeV 42 cells, doublet lattice 19 RF Cavities Lots of diagnostics

12

13 Construction Status Construction Status Injection line: completed in March Ring: “completed” 18 th June 2010 22 nd June 2010

14 Commissioning Commissioning EMMA ring - “completed” on 18th June 2010 - start-up: 20 th June - ring complete: end of July 2010 - 1 st commissioning period: Aug to Oct

15 1 st Commissioning 1 st Commissioning First Turn Second Turn 16 th August 2010 15 MeV Beam Magnets set for 18 MeV 24 th August 2010 12 MeV Beam Magnets set for 18 MeV No RF

16 Acceleration Acceleration Demonstrating accel. in FF machine not so easy! Need to look for orbit changes: - ToF - Tune Some evidence obtained before Oct shutdown, but:

17 Acceleration Acceleration During Oct-Feb shutdown: - some ring magnets re-aligned - some BPM readout improved - extraction line completed

18 2 nd Commissioning Period 2 nd Commissioning Period Real energy: 12 MeV Measurements at equivalent Time of flight Tunes Mean positions

19 Acceleration Acceleration Longitudinal phase Tunes Beam positions

20 Extraction line Extraction line No RF Septum = 12 MeV With RF Septum = 20.2 MeV

21 Resonances Resonances During acceleration: - both horizontal and vertical cell tunes change by > 0.1 - ring tune changes > 4.2 - 4 integer tunes crossed The σ of beam orbit oscillations

22 Conclusions Conclusions EMMA is the proof-of-principle non-scaling FFAG Construction was a challenge - novel machine - very compact: “…everything takes 5 times longer in EMMA…”, Neil Bliss, project manager Commissioning has been successful: - EMMA works! - Beam accelerated from 12 to 18 MeV/c in 6 turns - Small orbit excursion ~10 mm - Many resonances crossed, no observable growth in beam oscillation amplitude Long way to go: full experimental programme just started Upgrades planned: - improve EMMA performance - learn more for applications EMMA is a great success and would not exist without ASTeC!


Download ppt "The EMMA Project Rob Edgecock STFC Rutherford Appleton Laboratory & Huddersfield University."

Similar presentations


Ads by Google