Phas eInterventionMotivation Needed by Phase 1B 19 passing loops extended (4.4km) with OHTE & Signalling Loop 7 replaced by loop 7A to facilitate more.

Similar presentations


Presentation on theme: "Phas eInterventionMotivation Needed by Phase 1B 19 passing loops extended (4.4km) with OHTE & Signalling Loop 7 replaced by loop 7A to facilitate more."— Presentation transcript:

1 Phas eInterventionMotivation Needed by Phase 1B 19 passing loops extended (4.4km) with OHTE & Signalling Loop 7 replaced by loop 7A to facilitate more efficient operations To provide increased operational capacity to achieve 47Mtpa2010 Phase 1C Port link line Introduce a direct link from Postmasburg To provide increased operational capacity to achieve 60Mtpa2013 Phase 2A Intermediate loops (4,4 km) with OHTE & Signalling Telecommunication system extensions Track work for Salkor and yard automation Service Lines for Tippler 3 Maintenance Facilities and support equipment Condition Monitoring Equipment Power Upgrade To provide increased operational capacity to achieve 80Mtpa2014 Phase 2B 9 remaining loops (4,4 km) with OHTE & Signalling Telecommunication system extensions Track work for Salkor and yard automation Service Lines for Tippler 4 Maintenance Facilities and support equipment Condition Monitoring Equipment Power Upgrade To provide increased operational capacity to achieve 105Mtpa2015 Rail Development Plans Ore Line

2 Rail Development Plans Western and Southern Cape LocationIntervention Princip le Motivation Needed by Bellville Relocate washing facility to Bellville 2 Operational Simplification 2012 Belcon Optimise yard at Belcon 2 If Belcon development continues 2019 Kraaifontein to Bellville Re-signalling fully directional with CTC 2 Out dated train control 2014 Wellington to Kraaifontein Re-signal2 Out dated train control 2014 Source: Transnet Group Planning

3 Rail Development Plans Eastern Cape and Central Port System – Manganese Export Corridor Source: Transnet Group Planning LocationIntervention Neede d Hotazel to SishenTwo new substations2021 Hotazel to Kimberley Extension of 5 passing loops to accommodate long trains, with 3k.V D.C OHTE, and CTC signalling2019 Hotazel to Kimberley OHTE upgrades, signalling renewal, 3 substations, 25kV upgrade from hotazel to Kimberley, Power supply upgrade, loco run round at Beaconsfield, Changeover yard at Warrenton2013 Hotazel to Kimberley Double remaining single (283km) line sections. Electrify with 3k.V D.C OHTE, and provide CTC signalling2022 Kimberley to De Aar Extension of short Crossing Loops, doubling of OHTE, upgrade signalling and power supply, 164km track reinstatement to provide full double line2019 De Aar to CookhouseExtension of crossing loops, New traction substations, Eskom power supply2021 Cookhouse to AddoExtension of all short passing loops2027 PE + NgquraFull rationalisation of arrival and departure yards (Operational Simplification)2017

4 Rail Development Plans Eastern Cape and Central Port System – Long Term Plans LocationInterventionPPMotivation Needed by Cookhouse to East London Upgrade track axle load to 20t and improve geometry (gradients and curves)3 Improve operational characteristics for Port Interconnectivity.2020 Kimberley to Bloemfontein Maintain as operational alternative to connect Capecor and Hotazel traffic to Durban2 Operational flexibility and capacity alternative2025 Bloemfontein to Maseru Maintain and develop in synchronization with PRASA development plans3Cross-border connectionTBD Noupoort to Bloemfontein Develop as container corridor to Gauteng Substations 25kV AC Electrification and CTC Signaling Additional passing loops General realignment1 Decision dependent upon Manganese volumes as well as Container hub development in Ngqura.TBD 1 1 2 2 3 3 4 4 Source: Transnet Group Planning

5 Rail Development Plans Gauteng Freight Ring and Central Core: Capecor and Natcor Approach LocationIntervention Needed by Bloemfontein to Vereeniging Upgrade electrification to enable second line for electric locomotives2030 Fieldsview to Macfarlane Provide Intermediate passing loop and infill CTC signalling. 3kV DC2032 Macfarlane to Klerksdorp Double single line sections. CTC signalling with 3kV DC electrification2020 Potchefstroo m to Koekemoer Implement CTC Signal infill scheme to reduce headway2035 Chord at CachetNew chord2015 Cachet to Welverdiend Double single track sections and provide CTC signalling. Electrify with 3kV D.C.2025 Oberholzer to Randfontein Double single track sections and provide CTC signalling. Electrify with 3kV D.C.2030 NATCOR Approach to City Deep New south west chord at Glenroy, Double single track section between Glenroy and Rooikop, Junction modifications at Elsburg2027 2 2 3 1 1 3 4 4 5 5 6 6 7 7 8 8 Source: Transnet Group Planning

6 Rail Development Plans Gauteng: Freight Ring Concept Gauteng is at the centre of most regional and port connections in Southern Africa Flows are complex and there are no clear bypass routes A freight ring can potentially - –Facilitate uninterrupted flow of freight –Provide a key link between Hubs and Terminals –Provide dedicated freight routes segregated from congested PRASA routes. –Set a logical separation of electrification between 3kV DC and 25kV AC. CapeCor and Central Ports Free State and Central Ports Natal Corridor The Maputo Corridor Coal Line Zimbabwe Traffic The Waterberg Botswana Traffic Source: Transnet Group Planning

7 Rail Development Plans Gauteng Freight Ring: Finding a viable route Western Bypass a. Cost b. Constructability: sink hole formation c. Topography: Gradients (Magaliesburg) d. Environmental 12 3 1 2 4 Southern / Western Bypass a. Cost b. Constructability: sink hole formation c. Topography: Tunnels required d. Gold Mining activity South Eastern Bypass a. Cost 1 23 4 5 East-West through pass a. Cost b. Environmental c. Lack of Transportation reserve 1 1 1 1 Northern Bypass a. Cost but unavoidable 2 Western Bypass a. Cost b. Environmental Route perhaps not needed 2 Options Eliminated Potential solutions 2 1 Key Source: Transnet Group Planning

8 Rail Development Plans Gauteng Freight Ring Concept The eventual freight ring will not be closed on the western side because no feasible route was found. Instead, a bypass further west connecting Rustenburg, Swartruggens, Lichtenburg and Mafikeng is proposed but only if volumes justify the investment. Source: Transnet Group Planning

9 Rail Development Plans Gauteng Freight Ring and Central Core: Freight Ring LocationIntervention Needed by Pendoring to Rustenburg Double existing single track sections, 25kV and CTC2027 Pyramid South to Wildebeeshoek Double existing single track sections, 25kV and CTC2027 Freight Ring to Maputo Corridor) New single track chord from South to East2015 Baviaanspoort to Leeufontein Double existing single track sections, 3kV and CTC2032 Tweedracht to Kleinzonderhout Double existing single track sections, 3kV and CTC2033 Roodekoppies to Knoppiesfontein Double existing single track sections, 3kV and CTC2025 Ystervarkfontein to Katbosfontein Double existing single track sections, 3kV and CTC2036 Zestfontein to Cowles Dam Signal infill scheme to reduce headway to 8mins2027 Aurum - Rooivlei Signal infill scheme to reduce headway to 8mins2037 Rooivlei - Rietvallei Signal infill scheme to reduce headway to 8mins2027 Houtheuwel to Skansdam New double track 3kV DC, CTC signalling2029 Source: Transnet Group Planning

10 Rail Development Plans NATCOR LocationIntervention Needed by Kaydale to Palfmord Implement CTC Signal infill scheme to reduce headway to approximately 8mins2028 Palmford to Ennersdale Implement CTC Signal infill scheme to reduce headway to approximately 8mins2031 Ennersdale to Pietermaritzburg Implement CTC Signal infill scheme to reduce headway to approximately 8mins2028 Kaydale to Pietermaritzburg Provide additional (3rd line) electrified with 3kV D.C traction and signalled with CTC system2035 Bayhead to Cato RidgeNew Bypass2030 Source: Transnet Group Planning