Presentation is loading. Please wait.

Presentation is loading. Please wait.

EHealth Records Programme Therapies EPR Project Service Design Meeting Gaelle Fertil, Therapies Project Manager Monday 19 th July 2010.

Similar presentations


Presentation on theme: "EHealth Records Programme Therapies EPR Project Service Design Meeting Gaelle Fertil, Therapies Project Manager Monday 19 th July 2010."— Presentation transcript:

1 eHealth Records Programme Therapies EPR Project Service Design Meeting Gaelle Fertil, Therapies Project Manager Monday 19 th July 2010

2 Agenda: 1.Project Background 2.Project Objectives 3.Project Scope 4.Stage 1 – Referrals Go-live 5.Stage 2 – Electronic clinical noting 6.Scanning and Upload Solution 7.External Suppliers 8.Hardware Requirements 9.Testing Overview 10.Outstanding issues 11.Current Statement of Revenue Costs Therapies EPR Project Service Design

3 Project Background:  Existing Therapies system (TSS) reached end of life 2006.  Directorate encouraged to replace with solution delivered via “core systems”.  “Therapies Clinical Notes” work stream identified in 2007 “eHealth Project Brief”.  Therapies EPR Project approved at February 2009 CPB as Trust Risk Rating 1.  Clive Mellish took over management of project June 2009, followed by Anthony McCourt in March 2010, followed by Gaelle Fertil in June 2010.  Significant analysis undertaken to identify requirements and enable definition project scope and objectives.  Project split in two:  immediate interim delivery – Phase 1, divided into 2 stages:  Pan Trust Referrals Go-live – 19 th July  Therapies Directorate OP electronic noting staged Go-live  long term strategic delivery (via re-invigorated eHealth strategy) - TBC  Project re-start and associated costs signed off by CPB in November 2009. Therapies EPR Project Service Design

4 Project Objectives:  To enable a paper-lite environment across the Central Therapies Directorate.  To deliver solutions in response to Therapies requirements which can be then be reused and applied Trust-wide. Therapies EPR Project Service Design Project Scope:  Phase 1  “Native” iCM functionality  Scanning and Upload solution to capture residual paper  Delivery to outpatient pathways in:  Foot Health  Nutrition and Dietetics  Occupational Therapy  Patient Appliances  Psychology  Physiotherapy  Social Work Support and Hospital Discharge Department/Safeguarding  Speech and Language Therapy  Spiritual Health

5 Stage 1 – Referrals Go-live 19 th July  Using native iCM Functionality, referrals are orders in EPR.  14 Referrals going live (x1 Psychology deferred): Physiotherapy OUTPATIENT Referral Occupational Therapy INPATIENT Referral Occupational Therapy OUTPATIENT Referral Hand Therapy OUTPATIENT Referral Patient Appliances Referral (OP and IP use) Patient Appliances Order (OP and IP use) Speech & Language Therapy INPATIENT Referral Speech & Language Therapy OUTPATIENT Referral Foot Health Referral (OP and IP use) Nutrition & Dietetics Referral (OP and IP use) Chaplaincy Referral Social Services Section 2 Referral Social Services Section 5 Referral Adult Safeguarding Referral  Training has been provided by the project  Security rights have been set up: 2 levels of security rights - Order and Modify. Training tracker has been updated  IT Apps have been provided with briefing about the Go-live Therapies EPR Project Service Design

6

7

8

9

10

11

12

13

14 Stage 2 – Electronic clinical noting  Figures show total number of items of each category that need to be configured in iCM (i.e. not volumes).  Results relate to submission via the “Results Submission” solution and require an order item in iCM and an order requisition form to be created.  Reports will be bespoke Crystal reports, where they can be created – requirements for reports are in discussion. Therapies EPR Project Service Design 6 11

15 Stage 2 - Scanning and Upload Solution  Figures show count of document type to be scanned in to iCM (i.e. not volume).  S&U Solution is as per King’s supplied and built solution, on EPR+ framework.  Monthly volume is 16,000 per month. Therapies EPR Project Service Design

16 Stage 2 - Scanning and Upload Solution Therapies EPR Project Service Design

17 External Suppliers:  Scanning and Upload solution – King’s College London  No service agreement in place  EPR+ framework – King’s College London  No service agreement in place  Growth Chart (TBC) – Harlow Printing Ltd  Solution in requirements and design phase  Subject to further discussions at CPB Therapies EPR Project Service Design

18 Hardware Requirements Therapies EPR Project Service Design  Figures show approximate count of expected requirement for hardware to enable effective, efficient use of solution but will be confirmed during hardware review later in project.  Number of scanners required dependent on solution adopted. Figures shown are expected minimum required (one per distinct location).  Number of “PCs” denotes number of input devices required, not necessarily desktop computers: could be laptops, tablets, PDAs etc.  Additional technology may also be required e.g. smart pens, magic whiteboards, annotation tablets etc. which will be determined during the hardware review.

19 Testing Overview:  iCM:  Configuration Testing  User Acceptance Testing  Performance Testing – using Syntel  S&U solution:  System Testing (currently failed) – Development team  Performance Testing – using Syntel  Growth Chart (TBC) – Harlow Printing Ltd  System Testing – Development team  User Acceptance Testing Therapies EPR Project Service Design

20 Outstanding Issues:  Outstanding service level agreements with external supplier  Assume the currently service agreement with EPR is sufficient  Ability for EPR to function on wireless network  ER18 – iCM “crashing issue”  Other outstanding iCM issues identified during initial round of UAT  Scanning and Upload issues  Agreement on scope of performance testing by Syntel Therapies EPR Project Service Design

21 Current Revenue Costs as signed off in PID: Therapies EPR Project Service Design DescriptionCost PA Reactive Support Assumption for number of calls taken by service desk for project is 30 calls / month. Same amount for referring problems on and problem resolution (2nd and third line). £4,500 Proactive Support Relationships and supplier management. 20 days / year for "large project" like this. Every business area meets with Application Support Manager to look at how 'things are going'. Application Support Manager also meets with suppliers on a quarterly basis. For large project = £400 / day = £8000 / year. Handover / training = £400 / day @ 5 days = £2000 / year. Capacity planning: 5 day / year (includes meetings to discuss capacity etc) at £400 / day = £2000 / year. 3 rd Line Development activities (15 days / year) for Scanning and Upload Solution Disaster recovery: minimum 20 days for large project - not applicable for Therapies EPR project. £8,000 £2,000 £6,300 Change Changes to configurable items (e.g. changes to flowsheets / knowledge trees, printer reconfiguration etc.) System administration (user management) 20 days @£400 / day = £8000£8,000 Training Assuming an estimated attrition rate of 10% 0.5xFTE at Band 6 (£16,000 pa)£16,000 Annual Total:£51,300  “IT Operations" costs excluded, as IT&T had no metrics to estimate these costs

22 ? Discussion: Service Design Therapies EPR Project


Download ppt "EHealth Records Programme Therapies EPR Project Service Design Meeting Gaelle Fertil, Therapies Project Manager Monday 19 th July 2010."

Similar presentations


Ads by Google