Presentation is loading. Please wait.

Presentation is loading. Please wait.

SOUTHERN REGIONAL LOAD DESPATCH CENTRE BANGALORE

Similar presentations


Presentation on theme: "SOUTHERN REGIONAL LOAD DESPATCH CENTRE BANGALORE"— Presentation transcript:

1 SOUTHERN REGIONAL LOAD DESPATCH CENTRE BANGALORE
ONE DAY WORKSHOP ON AVAILABLE TRANSFER CAPABILITY(ATC) IN INDIAN CONTEXT WELCOME TO 14TH AUGUST 2007 Power Grid Corporation of India Limited

2 ATC FUNDAMENTALS WHY ATC?

3 Presentation Road Map What is Transfer Capability
Difference between Transfer Capability and Transmission capacity Assessment of Transfer Capability What is reliability Margin why are they required What are the risks associated with violation of transfer capability in real time How to Improve Transfer Capability

4 AIM OF POWER SYSTEM ENGINEERS
EARLIER STATEMENT To provide Reliable, Stable and Secured Power supply to the end user with Least possible cost PRESENT STATEMENT To provide Reliable, Stable and Secured Power supply to the end user with Least possible cost WITH Maximizing profit to all stake holders

5 Electricity is a scientific phenomenon
EMF travels at the speed of light Available ‘just-in-time’ Delivered to the customers fresh No one get placed on hold Impartial in its benevolence and wrath Good servant but a ruthless master Interconnected systems with thousands of kilometers of transmission lines and hundreds of generators operating with split second synchronism The largest single machine ever created Grid operation is a continuous interplay of technical phenomena and natural/ human intervention

6 Power flow characteristics
Is directional Does not recognize geographical boundaries, asset ownership Does not check the map to determine the shortest route Flows are dictated purely by Impedances of the transmission lines Point of injection by generators Point of consumption loads “Time & Location matter is fundamental to operation” -Shmuel Oren & Fernando Alvarado

7 Some Definitions ‘TTC is the amount of electric power that can be transferred over the interconnected transmission network in a reliable manner based on all of the following conditions: 1. For the existing or planned system configuration, and with normal (pre-contingency) operating procedures in effect, all facility loadings are within normal ratings and all voltages are within normal limits. 2. The electric systems are capable of absorbing the dynamic power swings, and remaining stable, following a disturbance that results in the loss of any single electric system element, such as a transmission line, transformer, or generating unit. 3. After the dynamic power swings subside following a disturbance that results in the loss of any single electric system element as described in 2 above, and after the operation of any automatic operating systems, but before any post-contingency operator-initiated system adjustments are implemented, all transmission facility loadings are within emergency ratings and all voltages are within emergency limits.

8 Some Definitions continued
4.With reference to condition 1 above, in the case where pre-contingency facility loadings reach normal thermal ratings at a transfer level below that at which any first contingency transfer limits are reached, the transfer capability is defined as that transfer level at which such normal ratings are reached. 5 In some cases, individual system, power pool, subregional, or Regional planning criteria or guides may require consideration of specified multiple contingencies, such as the outage of transmission circuits using common towers or rights-of-way, in the determination of transfer capability limits. If the resulting transfer limits for these multiple contingencies are more restrictive than the single contingency considerations described above, the more restrictive reliability criteria or guides must be observed.’

9 TRANSFER CAPABILITY Transfer Capability’ is the measure of the ability of interconnected electric systems to reliably move power from one area to another over all transmission lines (or paths) between those areas under specified system conditions POINT A POINT B Transfer Capability is different from ‘Transmission Capacity’, which usually refers to the thermal limit or rating of a particular transmission element or component

10 TRANSMISSION CAPACITY vs TRANSFER CAPABILITY
S No. Transmission Capacity Transfer Capability 1 Is a physical property in isolation Is a collective behaviour of a system 2 Depends on design only Depends on design, topology, system conditions, accuracy of assumptions 3 Deterministic Probabilistic 4 Constant under a set of conditions Always varying 5 Time independent Time dependent 6 Non-directional Directional 7 Determined directly by design Estimated indirectly through simulation studies 8 Declared by designer/ manufacturer Declared by the System Operator 9 Generally Understood by all Frequently misunderstood 10 Considered unambiguous & sacrosanct Subject to close scrutiny by all stakeholders

11

12 A CHAIN IS ONLY AS STRONG AS ITS WEAKEST LINK
IN A GRID WITH ELEMENTS IN SERIES AND PARALLEL, THE WEAKEST LINK IN SERIES WOULD DETERMIN THE STRENGTH OF THE NETWORK

13 Transfer Capability Limits
Thermal limit Thermal Limits establish the maximum electrical current that a transmission line or electrical facility can conduct over specified time periods before it sustains permanent damage by overheating or before it violates public safety requirements Voltage limit System voltages and changes in voltage must be maintained within the acceptable range as defined in the Grid Codes. For example, minimum voltage limits can establish the maximum amount of electric power that can be transferred without causing damage to the electric system or customer facilities. A widespread collapse of system voltage can result in a black out of portions or the entire interconnected network

14 Stability Limits The transmission network must be capable of surviving disturbance through the transient and dynamic time periods (from milliseconds to several minutes respectively) following a disturbance. All generators connected to ac interconnected transmission system operate in synchronism with each other at the same frequency. Immediately following a system disturbance, generators begin to oscillate relative to each other, causing fluctuations in system frequency, line loadings, and system voltages. For the system to be stable the oscillations must diminish as the electric systems attain a new, stable operating point. If a new, stable point is not quickly established, the generators will likely lose synchronism with one another, and all or a portion of the interconnected system may become unstable. The result of generator instability may damage equipment and cause uncontrolled, widespread interruption of electric supply to customers.

15 Total Transfer Capability: TTC
Thermal Limit Power Flow Voltage Limit Stability Limit Total Transfer Capability Time Total Transfer Capability is the minimum of the Thermal Limit, Voltage Limit and the Stability Limit

16 “Non-simultaneous Transfer Capability is the amount of electric power that can be reliably transferred between two areas of the interconnected electric system when other concurrent normal base power transfers are held constant.” “Simultaneous Transfer Capability is the amount of electric power that can be reliably transferred between two or more areas of the interconnected electric system as a function of one or more other power transfers concurrently in effect.”

17

18 TTC assessment block diagram
Planning criteria Credible contingencies CEA CTU STU Anticipated Network topology + Capacity additions Simulation Analysis Brainstorming LGBR Last Year Reports Weather Forecast Anticipated Substation Load Anticipated Ex bus Thermal Generation TTC Anticipated Ex bus Hydro generation Stakeholders Last Year pattern Operating limits Operator experience

19 Reliability Margins

20 Short Term Open Access Long Term Open Access Reliability Margin
ATC TTC

21 Need for Reliability Margins
Peculiarity in Indian power grids Difference in Planning assumptions and operating conditions Forecasting errors Outage of units etc

22 Peculiarity in Indian power grids
Haulage of power over long distances Resource inadequacy leading to high uncertainty in adhering to maintenance schedules Pressure to meet demand even in the face of acute shortages and freedom to deviate from the drawal schedules. A statutorily permitted floating frequency band of 49.0 to 50.5 Hz Non-enforcement of mandated primary response, absence of secondary response by design and inadequate tertiary response. No explicit ancillary services market Inadequate safety net and defense mechanism

23 Difference in Planning assumptions and operating conditions
Planning criteria The ISTS shall be capable of withstanding and be secured against a selected list of credible contingency outages without necessitating load shedding or rescheduling of generation during Steady State Operation. The credible contingencies considered are Outage of a 132 kV D/C line or, Outage of a 220 kV D/C line or, Outage of a 400 kV S/C line or, Outage of single Interconnecting Transformer, or Outage of one pole of HVDC Bipole line, or Outage of 765 kV S/C line Outage of a single largest in feed Planning is carried out on regional self sufficiency basis In the proposed Planning criteria six dispatch scenario’s are considered

24 Difference in Planning assumptions and operating conditions
Operating conditions not accounted during planning Simultaneous outage of more elements like Bus bar operation in a station Simultaneous outage of generators in a station due to auxiliary supply problem or evacuation line outages Weather disturbance causing multiple outage of lines in the same corridor Depletion in Hydro storage and less generation due to fuel shortages Variations in interregional exchanges Forecast errors Transmission lines and generators not coming up as per plan Re configuration of switching arrangements due to constraints like overloading of lines and transformers Socio-economic uncertainties in a progressive economy The above causes the difference in transfer capability in real time compared to Planning assumptions

25 Likely consequences of contingency during various operating conditions
S No. Scenario Likely consequences 1 Real time transfers > TTC System might not survive even a single element outage what to talk of a multiple contingency 2 ATC < Real time transfer< TTC System might survive a single element tripping. But the chances of a cascading failure are high in case of a multiple contingency. 3 Real time transfer < ATC Chances of survival are high for single contingency and moderate for multiple contingency. Providential escape from ‘the valley of death’ on certain occasions cannot be a justification to operate the system at that edges. Luck is a not a part of operating procedure

26 Methods to improve TTC We should of strong defence mechanisams like
System Protection schemes Effective under frequency and under voltage protections Auto re-closing schemes Tools for damping the oscillations like TCSC’s Wide area monitoring and measurement equipment for quick action taking Improved visualisation to the system operator to take immidiate corrective action Empowerment of SLDC/Generator operators to take immidiate corrective actions

27 Effect of Series Compensation on SIL

28 KOLAR SPECIAL PROTECTION SCHEME

29 Performance of the Scheme

30

31 St. Clair’s curve

32 REGIONAL GRIDS QUICK FACTS
400 MU CONS IN A DAY-1.5% IS 6 MU, 2190 MU IN A YEAR, 2/UNIT IS 4400 MILLION RUPEES IS 440 CRORE RUPEES

33 REGIONAL GRIDS INSTALLED CAPACITY TOTAL 134,084 MW
Area : 889,000 SQ KMS Population : 307 Million Peak Demand : 28,000 MW :560 MU / Day REGIONAL GRIDS INSTALLED CAPACITY NORTHERN :- 36,547 MW EASTERN :- 17,159 MW SOUTHERN :- 37,592 MW WESTERN :- 40,280 MW NORTH-EASTERN : ,506 MW TOTAL ,084 MW NORTHERN REGION NORTH-EASTERN REGION EASTERN REGION Area : 425,432 SQ KMS Population : 227 Million Peak Demand : 10,000 MW :200 MU / Day WESTERNREGION Area : 951,488 SQ KMS Population : 230 Million Peak Demand : 29,000 MW :640 MU / Day SOUTHERN REGION Area : 636,249 SQ KMS Population : 223 Million Peak Demand : 25,000 MW :470 MU / Day

34 HYDRO RESOURCES DELHI Source: Powerline (Siemens Ad), Oct-2006
RESOURCES ARE FAR AWAY FROM LOAD CENTERS. NECESSITATES LONG TRANSMISSION LINKS FOR EVACUATION HYDRO RESOURCES DELHI Source: Powerline (Siemens Ad), Oct-2006 KOLKATTA MUMBAI COAL BELT BANGALORE CHENNAI AREAS SHOWN ARE APPROXIMATE AND INDICATIVE

35 THE NATIONAL GRID : PHASE 1
NORTHERN REGION THE NATIONAL GRID : PHASE 1 500 MW SASARAM WR-NR HVDC B2B LINK Commissioned in June 2001 500 MW VINDHYACHAL WR-NR HVDC B2B LINK Commissioned in Nov. 1989 NORTH-EASTERN REGION ER WESTERNREGION BIRPARA(ER) – SALAKATI(NER) KV AC LINK in April 87 EASTERN REGION 400 KV Siliguri-Boangigaon in April 2000 500 MW GAZUWAKA ER-SR HVDC B2B LINK Commissioned in Sep. 1999 SOUTHERN REGION 500 MW BHADRAWATI WR-SR HVDC B2B LINK Commissioned in Sept. 1997 Bhadrawathi 2nd pole in March, 1998 NATIONAL GRID PHASE-1 COMPLETE

36 THE NATIONAL GRID : PHASE II
NORTHERN REGION THE NATIONAL GRID : PHASE II GORAKHPUR(NR) - MUZZAFARPUR(ER) 400 KV AC D/C Commissioned in Aug. 2006 500 MW VINDHYACHAL WR-NR HVDC B2B LINK Commissioned in Nov. 1989 500 MW SASARAM WR-NR HVDC B2B LINK Commissioned in June 2001 PATNA(ER) - BALIA(NR) 400 KV A/C D/C Commissioned in Jun. 2007 NORTH-EASTERN REGION GWALIOR(WR) - AGRA(NR) 400 KV A/C S/C Commissioned in Jun. 2007 ER WESTERNREGION BIRPARA(ER) – SALAKATI(NER) 220 KV AC LINK in April 87 (400 KV Siliguri-Boangigaon in April2000) EASTERN REGION 500 MW GAZUWAKA ER-SR HVDC B2B LINK Commissioned in Sep. 1999 SOUTHERN REGION GAZUWAKA 2nd pole in March, 2005 500 MW BHADRAWATI WR-SR HVDC B2B LINK Commissioned in Sept. 1997 (2nd pole in March, 1998) RAIPUR(WR) – ROURKELA(ER) 400 KV AC D/C Commissioned Mar. 2003 2000 MW TALCHER(ER)-KOLAR(SR) HVDC LINK comissioned in SEP 2002 TALCHER(ER)-KOLAR(SR) HVDC LINK CAPACITY ENHANCED TO 2500 MW in JUL 2007

37 Inter Regional Links – Till March 2006
Name of the Link Capacity (MW) East-North Dehri-Sahupuri 220kV S/c 150 Sasaram HVDC back-to-back 500 Sub-Total 650 East-West Budhipadar-Korba 220kV T/c 450 Rourkela-Raipur 400kV D/c 1200 1650 West-North Vindhyachal HVDC back-to-back Existing 220kV AC Lines 200 700 East-South Gazuwaka HVDC back-to-back 1000 Talcher-Kolar HVDC bipole 2000 3200 West-South Chandrapur HVDC back-to-back 300 1300 East-North East Bongaigaon-Siliguri 400kV D/c 800 Birpara-Salakati 220kV D/c Total 8500 700 MW 650 MW 36,547 MW 1650 MW 2506 17,159 1000 MW 40,280 MW 1300MW 1200 MW 2000MW 39,592 MW IR Capacity = 8,500 MW

38 Inter Regional Links – Till July 2007
Name of the Link Capacity (MW) East-North Dehri-Sahupuri 220kV S/c 150 Sasaram HVDC back-to-back 500 Muzaffarpur-Gorakhpur 400kV D/c (Quad) 2000 Patna-Balia 400kV D/c (Quad) Sub-Total 4650 East-West Budhipadar-Korba 220kV T/c 450 Rourkela-Raipur 400kV D/c 1200 1650 West-North Vindhyachal HVDC back-to-back Existing 220kV AC Lines 200 Gwalior-Agra 765kV S/c 1500 2200 East-South Gazuwaka HVDC back-to-back 1000 Talcher-Kolar HVDC bipole (Enhanced) 2500 3700 West-South Chandrapur HVDC back-to-back 300 1300 East-North East Bongaigaon-Siliguri 400kV D/c 800 Birpara-Salakati 220kV D/c Total 14500 2200 MW 4650 MW 36,547 MW 1650 MW 2506 17,159 1000 MW 40,280 MW 1300MW 1200 MW 2500MW 39,592 MW IR Capacity = 14,500 MW

39 IR Links – Till 2007 – 08 Till 2007 – 08 IR Capacity = 19,700 MW
Name of the Link Capacity (MW) East-North Bihar Sharif(ER)-Balia 400kV D/c (Quad) 2000 Barh(ER)-Balia 400kV D/c (Quad) Sub-Total 4000 East-West 400kV Ranchi(ER)-Sipat(WR) D/c Line with Series Compensation 1200 Total 5200 Name of the Link Capacity (MW) East-North Dehri-Sahupuri 220kV S/c 150 Sasaram HVDC back-to-back 500 Muzaffarpur-Gorakhpur 400kV D/c (Quad) 2000 Patna-Balia 400kV D/c (Quad) Sub-Total 4650 East-West Budhipadar-Korba 220kV T/c 450 Rourkela-Raipur 400kV D/c 1200 1650 West-North Vindhyachal HVDC back-to-back Existing 220kV AC Lines 200 Gwalior-Agra 765kV S/c 1500 2200 East-South Gazuwaka HVDC back-to-back 1000 Talcher-Kolar HVDC bipole (Enhanced) 2500 3700 West-South Chandrapur HVDC back-to-back 300 1300 East-North East Bongaigaon-Siliguri 400kV D/c 800 Birpara-Salakati 220kV D/c Total 14500 2200 MW 8650 MW 36,547 MW 2850 MW 2506 17,159 1000 MW 40,280 MW 1300MW 1200 MW 2500MW 39,592 MW Till 2007 – 08 IR Capacity = 19,700 MW

40 NARENDRA-KOLHAPUR D/C AND BACK TO BACK 2X 500 MW HVDC SYSTEM PROPOSED
1 TALCHER SR WOULD BE SYNCHRONOUSLY CONNECTED WITH REST OF INDIA THROUGH 765 KV D/C RAICHUR-SHOLAPUR-PUNE LINK RGM NARENDRA-KOLHAPUR D/C AND BACK TO BACK 2X 500 MW HVDC SYSTEM PROPOSED KOLHAPUR TALA PROJECT-LARGE CENTRAL GRID ARUNACHAL TO GUJARAT ON SAME FREQ KOLAR SR INTERCONNECTION BY 2012

41 INTER-REGIONAL TRANSFER BY END OF 11th PLAN (2012)
SOUTHERN REGION WESTERNREGION NORTHERN REGION NORTH-EASTERN REGION INTER-REGIONAL TRANSFER BY END OF 11th PLAN (2012) 4000 MW 11850 MW 1200 MW 6050 MW 5500 MW 1400 MW 6150 MW EASTERN REGION 36,700 MW OF INTER-REGIONAL POWER BY 2012

42 Source wise composition of installed capacity in India (1,34,084 in 2007) AS on 30-06-07

43 ALL INDIA GENERATION COMPOSITION
Total Market Size = BU Total Installed Capacity 1,34,084 MW

44 Sector wise consumption of electricity in India
Total Installed Capacity 1,34,084 MW

45 ALL INDIA MARKET COMPOSITION
(1,34,084 in 2007) AS on

46 THE SOUTHERN REGION GRID
ATC ISSUES AND HOTSPOTS

47 ‘NEW’ GRID 1 2 TWO ELECTRICAL REGIONS w.e.f Aug. 2006
NORTHERN REGION 1 NORTH-EASTERN REGION ‘NEW’ GRID EASTERN REGION TALCHER WESTERNREGION MAJOR INTERCONNECTIONS HVDC INTERCONNECTS TALA PROJECT-LARGE CENTRAL GRID ARUNACHAL TO GUJARAT ON SAME FREQ 2 SOUTHERN REGION AC INTERCONNECTS 2X500 MW BACK TO BACK STATION AT GAZUWAKA(SR) KOLAR 1000 MW BACK TO BACK STATION AT BHADRAWATI(WR) TALCHER-II TO KOLAR 2000 MW BIPOLE LINK

48 INTER REGIONAL TRANSFER CAPACITY SR WITH OTHER REGIONS
WITH ER JEYPORE-GAZUWAKA MW TALCHER-KOLAR MW WITH WR RAMAGUNDAM-CHANDRAPUR MW TOTAL CONCURRENT CAPACITY IS 4000 MW 220 KV LINKS ARE IGNORED BECAUSE THEY ARE NOT IN ACTIVE USE

49 GENERAL DIRECTION OF POWER FLOW IS FROM NORTH TO SOUTH
SR GRID MAP GAZUWAKA RAICHUR GOOTY SALEM UDUMALPET TRICHUR MADURAI TRICHY MADRAS NEYVELI GUTTUR KAIGA BHADRWATHI MUNIRABAD P N KOLAR HOSUR THIRUVANANTHAPURAM NELLORE NLM SIMHADRI HIRIYUR TALGUPPA KADAPA NARENDRA CHITTOOR MAPS KALPAKA VEMAGIRI NUNNA KHAMMAM RAMAGUNDAM MBN KNL GHANAPUR SSLM MMDPLI NSR S'HALLI HOODY 35 160607 105155 49.42 43 197 1 195 225 227 258 242 240 236 303 2 147 96 108 318 110 37 218 34 278 252 229 341 107 267 123 20 119 52 320 68 388 420 419 143 141 71 265 122 280 401 151 158 221 321 300 257 17 389 381 209 243 272 187 343 329 344 205 348 78 133 131 251 253 198 202 v 299 314 200 273 185 RAYALASEEMA AXIS 404 402 395 405 408 409 391 403 232 406 410 396 397 386 407 384 399 398 1542 284 GENERAL DIRECTION OF POWER FLOW IS FROM NORTH TO SOUTH

50 UI IMPORT BY SR FROM CG ON 05-MAR-07
PEAK IMPORT OF 3670 MW FROM ‘NEW’ GRID UI IMPORT FROM CG CG FREQ SR FREQ 20.31 MUs IMPORTED FROM CG AMOUNT SAVED FOR SR CONSTITUENTS = 2.20 CRs

51 AREAS OF CONSTRAINT HYDERABAD URBAN AREA HIGH 400/220 KV ICT LOADINGS
220 KV LINE OVER LOADING DEC TO FEB SENSITIVE TO IMPORT FROM WR AT RAMAGUNDAM NEW STATIONS PLANNED………..WOULD BE IN PLACE BY SRISAILAM EVACUATION PROBLEMS DEPENDS ON RAINFALL IN CATCHMENT AREA (N KARNATAKA, SW MAHARASHTRA) OVERLOADING OF SRISAILAM-KURNOOL AND KURNOOL-GOOTY 400 KV S/C LINKS SENSITIVE TO IMPORT FROM GAZUWAKA AREA NO TIME FRAME AS YET FOR AUGMENTATION NUNNA-NELLORE D/C LINK WOULD BE SOLVED WITH NEW GENERATION COMING UP SOUTH BY 2009 GOOTY-BANGALORE CORRIDOR FULL GENERATION AT RAICHUR, ALMATTI, BTPS AND IMPORT FROM WR/ER WIND ENERGY EVACUATION ISSUES IN SOUTH TAMILNADU 2000 MW WIND IN TN, PARTICULARLY ALONG KERALA BORDER AND IN KANYAKUMARI AREA EVACUATION PROBLEMS AS NETWORK WAS NOT DESIGNED FOR THIS DEDICATED SS AND TL IN PROGRESS WOULD SATURATE AT MW SEASONAL AND UNPREDICTABLE CONSTRAINT – KERALA HAS TO MAINTAIN HYDRO TO PREVENT LINE OVERLOADING

52 HOT SPOTS COIMBATORE AREA MADRAS CITY BANGALORE CITY SUBTRANSMISSION
LINE OVERLOADING PROBLEMS MADRAS CITY 110 KV GMR VASAVI EVACUATION ROW PROBLEMS BANGALORE CITY SUBTRANSMISSION RELIABILITY ISSUES


Download ppt "SOUTHERN REGIONAL LOAD DESPATCH CENTRE BANGALORE"

Similar presentations


Ads by Google