CTC 440 Review Determining peak flows Rational method Q=CIA

Similar presentations


Presentation on theme: "CTC 440 Review Determining peak flows Rational method Q=CIA"— Presentation transcript:

1 CTC 440 Review Determining peak flows Rational method Q=CIA
Intensity determined from IDF curves Set time of concentration=storm duration

2 CTC 440 Sizing Structures Hydraulic Devices Pipes Culverts Inlets
Ditch &/or gutter flow Storm drainage systems Detention structures

3 Subjects Open Channel Flow Ditch flow Gutter flow
Pipe flow (non-pressurized)

4 Objectives Know how to use Manning’s equation for uniform flow calculations Know how to calculate Normal Depth

5 Open Channel Flow Open to the atmosphere
Creek/ditch/gutter/pipe flow Uniform flow-EGL/HGL/Channel Slope are parallel velocity/depth constant Varied flow-EGL/HGL/Channel Slope not parallel velocity/depth not constant

6 Uniform Flow in Open Channels
Water depth, flow area, Q and V distribution at all sections throughout the entire channel reach remains unchanged The EGL, HGL and channel bottom lines are parallel to each other No acceleration or deceleration

7 Manning’s Equation Irish Engineer
On the Flow of Water in Open Channels and Pipes Empirical equation See more:

8 Manning’s Equation-Metric
Q=AV=(1/n)(A)(Rh)2/3S1/2 Where: Q=flow rate (cms) A=wetted cross-sectional area (m2) Rh=Hydraulic Radius=A/WP (m) WP=Wetter Perimeter (m) S=slope (m/m) n=friction coefficient (dimensionless)

9 Manning’s Equation-English
Q=AV=(1.486/n)(A)(Rh)2/3S1/2 Where: Q=flow rate (cfs) A=wetted cross-sectional area (ft2) Rh=Hydraulic Radius=A/WP (ft) WP=Wetter Perimeter (ft) S=slope (ft/ft) n=friction coefficient (dimensionless)

10 Manning’s Friction Coefficient
Typical values: Concrete pipe: n=.013 CMP pipe: n=.024

11 Example-Find Q Find the discharge of a rectangular channel 5’ wide w/ a 5% grade, flowing 1’ deep. The channel has a stone and weed bank (n=.035). A=5 sf; WP=7’; Rh=0.714 ft S=.05 Q=38 cfs

12 Example-Find S A 3-m wide rectangular irrigation channel carries a discharge of 25.3 a uniform depth of 1.2m. Determine the slope of the channel if Manning’s n=.022 A=3.6 sm; WP=5.4m; Rh=0.667m S=.041=4.1%

13 Triangular/Trapezoidal Channels
Must use trigonometry to determine area and wetted perimeters

14 Pipe Flow Hydraulic radii and wetted perimeters are easy to calculate if the pipe is flowing full or half-full If pipe flow is at some other depth, then tables, figures, or software (flowmaster) are usually used

15

16 Using Manning’s equation to estimate pipe size
Size pipe for Q=39 cfs Assume full flow Assume concrete pipe on a 2% grade Put Rh and A in terms of Dia. Solve for D=2.15 ft = 25.8” Choose a 27” or 30” RCP Velocity is approx. 9.8 ft/sec

17 Using Manning’s equation to estimate pipe size
Size pipe for Q=220 cfs Assume full flow Assume concrete pipe on a 2% grade Put Rh and A in terms of Dia. Solve for D=4.1 ft = 49.5” Choose a 54” RCP Velocity is approx ft/sec ===high

18 Normal Depth Given Q, the depth at which the water flows uniformly
Use Manning’s equation Must solve by trial/error (depth is in area term and in hydraulic radius term)

19 Normal Depth Example Find normal depth in a 10.0-ft wide concrete rectangular channel having a slope of ft/ft and carrying a flow of 400 cfs. Assume: N=0.013

20 Normal Depth Example 7-3 Assumed D (ft) Area (sqft) Peri. (ft) Rh (ft)
Q (cfs) 2.00 20 14 1.43 1.27 356 3.00 30 16 1.88 1.52 640 2.15 21.5 14.3 1.50 1.31 396

21 Inlets Capacity usually estimated using orifice or weir equations

22 Froude Number F=Vel/(g*D).5 F=Froude # V=Velocity (fps or m/sec)
D=hydraulic depth=a/T (ft or m) g=gravitational constant F=1 (critical flow) F<1 (subcritical; tranquil flow) F>1 (supercritical; rapid flow)

23 Stormwater Definitions
SWPPP-Stormwater Pollution Prevention Plan NPDES-National Pollutant Discharge Elimination System SPDES-State Pollutant Discharge Elimination System MS4-Municipal Separate Storm Sewer System NOI-Notice of Intent Blue Book-”New York Standards and Specification for Erosion and Sediment Control”

24 History Water Quality Act-1987 Phase I Stormwater Regulations-1990
First regulations dealing with discharge of stormwater Phase I Stormwater Regulations-1990 NYSDEC is local permitting authority NYSDEC issued 2 general permits-1993 Industrial Site Runoff Construction Projects > 5 acres (Phase I) Phase II Stormwater Regulations-1999 Apply to Construction Projects > 1 acre

25 SWPPP-Contents Standards for Construction Activities
Background project info Site Map Soil Description Construction Phasing Plan Pollution Prevention Measures Description of Construction and Waste Materials Temporary and Permanent Structural and Vegetative Measures

26 SWPPP-Contents (contents)
Map showing control measures Details of control measures Identify temporary measures to be converted to permanent control measures Maintenance Schedule Name of receiving water Description of structural practices used to divert flows Description of existing data that describes the stormwater runoff characteristics at the site

27 Commonly Used SWPPP Measures
Construction Entrance Mulching/Seeding Silt Fences Straw Bale Dikes Drop Inlet Protection Stone Check Dams Prefabricated Check Dams

28 Construction Entrance

29 Erosion Control (Mulching/Seeding)

30 Silt fences www.acfenvironmental.com/ bmp_siltfence.htm
bmp/appn_soil.html

31 Straw Bale Dikes http://www.salmonhabitat.org/images/v3f52b.gif

32 Drop Inlet Protection

33 Stone Check Dams http://www.ncc-swnpdes.com/images/stone_creek_dam.jpg

34 Other Check Dams

35 Detention Structures Designed for water quality, attenuation of peak flows, infiltration, aesthetics

36


Download ppt "CTC 440 Review Determining peak flows Rational method Q=CIA"