1 Web Migration Project Update for ATC April 28, 2009

2 Web Migration Project Update Project Goal To provide and support and effective solution for creating and managing websites and departmental business applications that meet the university’s security, communication, design and accessibility guidelines.

3 Web Migration Project Update Project milestones and timelines 1.Move existing websites to new platform -- Complete 12/31/08 2.Move dept. applications to new platform -- Complete 2/27/09 3.Upgrade CMS to latest version of Plone. -- Complete 4/03/09 4.Migrate all static sites to Plone CMS -- Target 6/30/09

4 Web Migration Project Update 1. Move websites to new platform Purchase and Install New Hardware –Ability to handle increasing requests 3,000,000 requests per month 50 – 100 requests per second –Higher Performance –More Scalability – Processing Power –More Memory –More redundancy – failover Shut down old Athena Server.

5 Web Migration Project Update 2. Move existing applications to new platform Before Move - Security risks – Many vulnerabilities –Plan : Segregate Apps into Departmental Virtual Environments 41 Departments identified on VHOST –23 Moved –17 Removed (obsolete) Post move – Vulnerabilities significantly reduced –Depts. Responsibility to correct Security Vulnerabilities. –Eliminate need to convert PHP to Java programs. Java will be Platform for new Development.

6 Web Migration Project Update 3. Upgrade CMS to latest version of Plone Step 1: (12/31/08) –Vendor Linux Box –Software configurations on New Hardware –Load Balancing, Caching, Optimization –Migrate Plone 2.5.3 to 2.5.5 Step 2: (4/03/09) –Vendor Linux Box –Migrate 3 rd Party Products –Migrate UofL Custom Products –Migrate Custom Skins –Migrate Plone 2.5.5 to 3.1.7 Step 3: Post Migration Tuning

7 Web Migration Project Update 4. Migrate static sites to CMS 464 identified (Athena) –261 complete (56%) –118 removed (17%) –47 staging (10%) –31 in review (7%) –7 not started (2%)

8 Web Migration Project Update Features of the Plone CMS No extensive knowledge of HTML/CSS, etc. required Built-in features: –Forms (e-mail & spreadsheet output) –Photo galleries –Calendar and news RSS –Multimedia support Audio podcasting Working toward integrated video support –In-line editing –Workflow/version control –LDAP integration & granular permissions