Sligo County Council in Partnership with the Federation of Group Water Supply Schemes. ‘ Progress on the construction of the group water supply bundles.

Similar presentations


Presentation on theme: "Sligo County Council in Partnership with the Federation of Group Water Supply Schemes. ‘ Progress on the construction of the group water supply bundles."— Presentation transcript:

1 Sligo County Council in Partnership with the Federation of Group Water Supply Schemes. ‘ Progress on the construction of the group water supply bundles in Sligo’ ‘ Progress on the construction of the group water supply bundles in Sligo’ Pat Doyle,Project Engineer. Pat Doyle,Project Engineer. 8 June 06 8 June 06

2 Sligo d.b.o. bundles NORTH BUNDLE COST €2,545,749 1Ballintrillick gwss. 2 Benbulbin gwss10m/3/h. 3Castletown gwss.8m/3/h 4 Drum east gwss 20m/3/h. 5Beltra gwss.10m/3/h 6 Kellogoboy gwss 12m/3/h SOUTH BUNDLE COST €2.936,588 7Castlebalwin gwss.35m/3/h 7Castlebalwin gwss.35m/3/h 8Corrick gwss.10m/3/h 8Corrick gwss.10m/3/h 9 Culfadda gwss. 9 Culfadda gwss. 10 Geevagh Highwood gwss.52m/3/h 11 Keash gwss 12m/3/h CONTRACT SIGNED ON APRIL 11 2005 CONTRACT PERIOD 12 MONTHS CONTRACT PERIOD 12 MONTHS The contractor will maintain these plants for 20years. CONTRACTOR --TREATMENT SYSTEMS LTD. Kilkenny CONTRACTOR --TREATMENT SYSTEMS LTD. Kilkenny

3 Easkey Lough Easkey Lough Talt Lough Gill Sligo Grange Lough Na Labe 6 1 5 4 2 3 North West Group 1.Drum East (250 Houses) 2.Benbulben (53 Houses) 3.Ballintrillick (112 Houses) 4.Castletown (58 Houses) 5.Keelogyboy (92 Houses) 6.Beltra (81 Houses) Ballymote Lough Bo Lough Arrow 12 7 9 11 10 8 South East Group 7.Geevagh Highwood (388 Houses) 8.Castlebaldwin (280 Houses) 9.Carrownadorgny (25 Houses) 10.Keash (130 Houses) 11.Culfadda 11.Culfadda (162 Houses) 12.Corrick / Ballinafad (86 Houses)

4

5 BALLINTRILLICK BALLINTRILLICK

6 Construction process Once the contractor was appointed,they ware allowed a specific period to prepare the design.This design was then submitted to the clients rep. for consideration and approval. (CONSTRUCTION DOCUMENT REVIEW) Once the contractor was appointed,they ware allowed a specific period to prepare the design.This design was then submitted to the clients rep. for consideration and approval. (CONSTRUCTION DOCUMENT REVIEW) Drawings were made available for part 8 planning to co. co. Drawings were made available for part 8 planning to co. co. Once the process of design was agreed,drawings were issued to the project engineer for recording and comment as work progressed. Once the process of design was agreed,drawings were issued to the project engineer for recording and comment as work progressed.

7 PROGRESS DESIGN COMMENCED IN NOVEMBER 2004 DESIGN COMMENCED IN NOVEMBER 2004 PART 8 PLANNING PART 8 PLANNING CONTRACT SIGNED ON APRIL 11 2005 CONTRACT SIGNED ON APRIL 11 2005 PROJECT PROGRAMME PROJECT PROGRAMME PAYMENT PROFILE SUBMITTED PAYMENT PROFILE SUBMITTED CIVIL CONSTRUCTION COMMENCED IN AUGUST 2005 CIVIL CONSTRUCTION COMMENCED IN AUGUST 2005 MECHANICAL CONSTRUCTION BEGAN IN DECEMBER2005 MECHANICAL CONSTRUCTION BEGAN IN DECEMBER2005 PROCESS PROVING MAY/JUNE 2006 PROCESS PROVING MAY/JUNE 2006

8 BENBULBIN T.PLANT

9 Replacement of existing reservoir at Ballintrillick GWS N. Sligo

10 Newly replaced reservoir and treatment plant Ballintrillick GWS N. Sligo

11 Design demand Design year = 2005. Design year = 2005. Design period = 20years. Design period = 20years. Per Capita Consumption (PCC) = 180 litres per person per day consistent with the Per Capita Consumption (PCC) = 180 litres per person per day consistent with the Department of Environment and Local Government guideline figures for GWSs Department of Environment and Local Government guideline figures for GWSs Agricultural Demand = 814 litres per connection, based upon W.S Atkins National Agricultural Demand = 814 litres per connection, based upon W.S Atkins National Water Study Report, 2000. Water Study Report, 2000. Other connections = 1000 litres per connection assumed. Other connections = 1000 litres per connection assumed.

12 PRESSURE VESSEL AND INSTRUMENT PANEL

13 BENBULBIN

14 Project management-construction Project inception Project Review Design and Planning Procurement Development Delivery Project Management Contract Management

15 ESB JOB TRACKER FOR SLIGO COUNTY COUNCIL WATER SCHEMES 2005/06 Job IDLocationContractorPaymentMICStageComments Cert in. 127847BallintrillickYes€26,000.0025ConnectedCompleted 11/01/06Yes 127413KeelogyboyYes€46,98925DesigningDesign to be handed to Contractor ws 23/01 for build FebruaryNo 127410BenbulbenYes€7,51925ConstructionLine outages in progress ws 23/01 for completion end Jan 06.power team on siteNo 127408CastletownYes€15,29615ConstructionAs per Benbulben above power team to mobilize next weekNo 127412Drum EastYes€6,30225ConstructionAs per Benbulben & Castletown {ducting S Campbell}No 124494BeltraNo€3,53625ConstructionAlteration and Linework Done 8/12/05 can be connected when cert in.No 127535CorrickYes€8,48015ConstructionContractor finished linework 23rd Dec. Can be connected when cert in.No 127551KeashNo€19,47015DesigningDuchas approval rec'd with conditions (Area of Conservation). Line isNo now being designed on site with Duchas representative input & to minimise risk of damage ESB Crews will do construction rather than Contractors. Probably construct in March subject to agreements. 127552KeashNo€4,11020DesigningAs per above (Shared line) esb to meet Duchas again this week on siteNo

16 E.S.B. crews at work at Castletown GWS,Benbulbin N.Sligo

17 CASTLETOWN

18 BELTRA

19 BELTRA

20 Castlebaldwin intake CASTLEBALWIN INTAKE

21 CASTLEBALWIN INTAKE ON LOUGH ARROW

22 ADSORPTION CLARIFIER ADSORPTION CLARIFIER

23 CORRICK BEFORE CONSTRUCTION

24 CORRICK TREATMENT WORKS OVERLOOKING LOUGH ARROW

25 KEASH

26 KEASH, BRICKLIEVE

27 Projects construction management Water Services,Sligo co.co. Personnel: 1no.Project Engineer, 2no. SRE, 2no. SRE, 2no.RE, 2no.RE, 2no. A/RE, 2no. A/RE, 1no G1 technician 1no G1 technician Working closely with the employers representative and main line staff to help deliver projects.

28 Employers requirements To Provide for the Construction of a new Water Treatment Works in Accordance with the EU (Drinking Water) Regulations, 2000 S.I. No439 To Provide for the Construction of a new Water Treatment Works in Accordance with the EU (Drinking Water) Regulations, 2000 S.I. No439 To ensure compliance with the maximum admissible concentrations (MAC) for colour, manganese and iron and to eliminate the threat from concentrations of trihalomethanes (THMs) To ensure compliance with the maximum admissible concentrations (MAC) for colour, manganese and iron and to eliminate the threat from concentrations of trihalomethanes (THMs)

29 Table 3.3.4:- Estimated Unaccounted For Water (UFW) - 2005 GWS Theor. Domestic Theor. Agric. Theor. Other 2005 Total Theor. Demands 2005 Existing Consumption Estimated 2005 UFW Esti m a t e d 2 0 0 5 UF W Unit m 3 /day % Geevagh/High.280383116741,02334952 Keash789201702275734 Culfadda1088121922738142 Corrick70202937000 Castlebaldwin1841252233145011936 Doongeela12113261200

30 SUMMARY OF DUTIES circularlL7/04 1.1 To supervise the construction, completion and maintenance of the contract works on the scheme to ensure that they are executed fully in accordance with the Contract Documents. 1.1 To supervise the construction, completion and maintenance of the contract works on the scheme to ensure that they are executed fully in accordance with the Contract Documents. 1.2 To ensure that all materials used in the works are in accordance with the Specification. 1.2 To ensure that all materials used in the works are in accordance with the Specification. 1.3 To execute or supervise tests carried out on site and to inspect materials and manufacture at source other than that which may be carried out by the Consulting Engineer's Head Office Staff. 1.3 To execute or supervise tests carried out on site and to inspect materials and manufacture at source other than that which may be carried out by the Consulting Engineer's Head Office Staff.

31 Duties continued. To record and check the progress of the work against the programme including regular monthly updating of the programme and of the cash flow statements. To record and check the progress of the work against the programme including regular monthly updating of the programme and of the cash flow statements. To keep a comprehensive diary constituting a detailed history of the work of construction and of significant happenings at the site and submit regular progress reports to the Consulting Engineer. To keep a comprehensive diary constituting a detailed history of the work of construction and of significant happenings at the site and submit regular progress reports to the Consulting Engineer. To record with particular detail information relating to delays, adverse physical conditions, disputes with landowners, and all Contractor's plant and labour and all Sub-Contractors' plant and labour. To record with particular detail information relating to delays, adverse physical conditions, disputes with landowners, and all Contractor's plant and labour and all Sub-Contractors' plant and labour.

32 To measure in agreement with the Contractor's staff on a monthly basis. To measure in agreement with the Contractor's staff on a monthly basis. To check all interim valuations and submit report to employers representative with recommendation. To check all interim valuations and submit report to employers representative with recommendation. attend regular measurement meetings with Consulting Engineer where any difficulties with interim measurement are to be discussed. attend regular measurement meetings with Consulting Engineer where any difficulties with interim measurement are to be discussed. examine in detail any claims submitted by the Contractor and to make written reports on same. examine in detail any claims submitted by the Contractor and to make written reports on same. Ensure compliance with Safety, Health and Welfare at Work. Ensure compliance with Safety, Health and Welfare at Work. for regular photographic records of the progress of the works for regular photographic records of the progress of the works

33 To carry out inspections at regular intervals to ensure that the Contractors are meeting their obligations with regard to the payment of P.A. Y.E., P.R.S.I., and Pension Fund/Sick Pay Contributions on behalf of their employees. To carry out inspections at regular intervals to ensure that the Contractors are meeting their obligations with regard to the payment of P.A. Y.E., P.R.S.I., and Pension Fund/Sick Pay Contributions on behalf of their employees. Surveillance of testing and commissioning during process proving period. Surveillance of testing and commissioning during process proving period. To assist in the preparation of all Final Accounts To assist in the preparation of all Final Accounts Assist with reporting on the PMS Assist with reporting on the PMS

34

35 Benbulbin GWS new reservoir and treatment plant, N. Sligo

36 KEELOGOBOY

37 DRUM EAST

38 ADSORPTION CLARIFIER ADSORPTION CLARIFIER


Download ppt "Sligo County Council in Partnership with the Federation of Group Water Supply Schemes. ‘ Progress on the construction of the group water supply bundles."