Senior Design 1 Project Android Pilot Nation Stellar Sea Lions Team –Jordan Fryer –Andrew Olivier –Karen Echon –Jacob Hahn University of Portland School.

Similar presentations


Presentation on theme: "Senior Design 1 Project Android Pilot Nation Stellar Sea Lions Team –Jordan Fryer –Andrew Olivier –Karen Echon –Jacob Hahn University of Portland School."— Presentation transcript:

1 Senior Design 1 Project Android Pilot Nation Stellar Sea Lions Team –Jordan Fryer –Andrew Olivier –Karen Echon –Jacob Hahn University of Portland School of Engineering Advisor Dr. Steve Vegdahl Industry Representative Jason Favors Ben Foran

2 Senior Design 2 Introduction Project Android Pilot Nation is an Android application whose purpose is to create a mobile community for the University of Portland athletic fans. University of Portland School of Engineering

3 Senior Design 3 Scorecard Previous Plans –Approval for Design document. –Set final budget. –Meet with IT. Completed Plans –Approval for Design document. –Set final budget. –Met with IT. Uncompleted Plans –None. University of Portland School of Engineering

4 Senior Design 4 Set Final Budget Search Craigslist, Ebay, etc for used Android mobile devices with 2.1 level API and Google Calendar installed. –Estimated the price range University of Portland School of Engineering

5 Senior Design 5 Met with IT Basically can’t help us. –Parse website data. Flash for Android is “coming soon.” University of Portland School of Engineering

6 Senior Design 6 Additional Accomplishments Created high level design of classes. University of Portland School of Engineering

7 Senior Design 7 Plans for Upcoming Month Purchase development phone. –Solve or bypass Calendar interfacing issue using the developer phone. University of Portland School of Engineering

8 Senior Design 8 University of Portland School of Engineering Milestones StatusDescriptionOriginal Target Previous Target Present Target MissedContact IT8 Oct 10 29 Oct 10 CompleteAndroid Counter Program15 Oct 10 CompleteAndroid File IO Program15 Oct 10 MissedAndroid Calendar Interface Program15 Oct 10 5 Nov 10 CompleteFunctional Specification Approved15 Oct 10 MissedDesign Document First Draft5 Nov 10 9 Nov 10 CompleteFinal Budget Set12 Nov 10 CompleteDesign Document v. 0.9519 Nov 10 18 Nov 10 MissedDesign Document Approved24 Nov 10 25 Nov 10 Implement API30 Jan 11 Test API 13 Feb 11 Implement Central Menu and Activity Organizer 20 Feb 11 Test Central Menu and Activity Organizer 6 Mar 11 Implement News Feed Activity 13 Mar 11

9 Senior Design 9 Concerns/Issues Relying on developer phone in order to implement Calendar functionality. –Emulator doesn’t run Calendar.apk Flash for Android is not implemented by Founder’s Day. –Only way to get live scores is through Stretch Internet in Flash. University of Portland School of Engineering

10 Senior Design 10 Conclusions Design document Approved. Developer’s phone needs to be purchased. Calendar Application needs to be resolved. University of Portland School of Engineering

11 Senior Design 11 Questions? University of Portland School of Engineering

12 Senior Design 12 Understanding Milestone Dates The Milestones slide is one of the most important slides in your presentation. It can be tricky to get the dates correct. The milestones you place on this slide should come directly from your last document that has been approved to version 1.0 (functional specification or design). If this is your first program review (September) just create a milestone for the major tasks you foresee including each of the major versions of your functional specification (0.9, 0.95 and 1.0). After September, you will have more milestones than can fit on one slide. Select the five milestones whose original deadlines immediately proceed the current date and at least five more milestones that follow the current date. The Original Target date is the date when you stated you would complete this document in your functional specification or design. In September, this will be the due dates specified in the course schedule. The Previous Target date is the expected completion date you had in your last program review presentation. I.e., copy the date that was in the “Present” column in your last presentation. For your September program review, leave this column blank. The Present Target date is the date that you currently expect to complete each milestone. If the milestone is complete, then you should put the completion date here. Color code your milestones slide appropriately (see next slide) University of Portland School of Engineering

13 Senior Design 13 Color-Coding Milestones The background color of row in your milestones table should vary depending upon the status of that milestone. Use pale shades of the colors for easy readability. Red (missed)– This milestone’s Original Target date has passed since the last program review and you failed to complete the task on time. Orange (delayed) – This milestone’s Original Target date has not passed, but you believe that you will not complete the milestone on time (i.e., the Present date is later than the Original date). Yellow (behind) – You are currently behind on this milestone but have plans to catch up and meet your date. Green (completed) – This milestone has been completed by the team since the last program review and it was completed on or before the original scheduled date. White – everything else. This will include milestones you completed before the last program review. This will also include milestones that are not yet completed and don’t appear to be in any danger. University of Portland School of Engineering

14 Senior Design 14 Spring Milestones University of Portland School of Engineering StatusDescriptionOriginal Target Previous Target Present Target Implement API3 Sep 10 Test API 16 Sept 10 Implement Central Menu and Activity Organizer 21 Sept 10 Test Central Menu and Activity Organizer 24 Sep 10 24 Sept 10 Implement News Feed Activity 3 Oct 10 Implement Calendar Activity 8 Oct 10 Final Report First Draft 8 Oct 10 29 Oct 10 Test News Feed Activity 15 Oct 10 Test Calendar Activity 15 Oct 10 Final Report Version 0.95 15 Oct 10 5 Nov 10 Final Report Approved 15 Oct 10 Test System 5 Nov 10 9 Nov 10 Project Presentation 12 Nov 10 14 Nov 10


Download ppt "Senior Design 1 Project Android Pilot Nation Stellar Sea Lions Team –Jordan Fryer –Andrew Olivier –Karen Echon –Jacob Hahn University of Portland School."