Presentation is loading. Please wait.

Presentation is loading. Please wait.

Status of SMACC-QA 1.Recently resolved issues 2.Update from QC teams 3.Statistics S56 and S67 4.Auditors findings 5.4th Splice Review – 22/24 July Ranko.

Similar presentations


Presentation on theme: "Status of SMACC-QA 1.Recently resolved issues 2.Update from QC teams 3.Statistics S56 and S67 4.Auditors findings 5.4th Splice Review – 22/24 July Ranko."— Presentation transcript:

1 Status of SMACC-QA 1.Recently resolved issues 2.Update from QC teams 3.Statistics S56 and S67 4.Auditors findings 5.4th Splice Review – 22/24 July Ranko Ostojic 28 June 2013

2 Inspection of ultrasound welding Change of ultrasound welding machine settings from CP=0.6 to 0.8 in 2009. Gauge used for inspection has 3.1 mm width and is too small for CP=0.8. Based on measurements of recently produced welds, modification of gauge width to 3.4 mm proposed and accepted. Test procedure (LHC-QBBI-TP-0003) updated.

3 Inspection of the shunts Visual inspection of the top and bottom shunts modified (criterion of continuity of fillets suppressed) New version of the test procedure released (LHC-QBBI-TP-0007).

4 Insulation boxes The problem

5 Insulation boxes Inspection procedure New inspection procedure was discussed, updated, went through the EDMS approval process and released. The procedure defines the role of the LMF-QC and ELQC teams in the inspection process at different times, when access to the box extremities differs due to presence (or lack) of Eccobond filling and compression tooling. The MME-welding team rechecks the clearance box-M-flange on the bellows side before welding.

6 Insulation boxes Modification of baseline All new splices will be realigned before soldering. Significant number of boxes will have rounded corners at the extremities (wall thickness reduced from 3 mm to 1.3 mm). New version of the assembly procedure (LHC-QBBI-TP-0024) in preparation.

7 Insulation boxes The standard repair In case of reduced clearance: Corners cut back so that the box cover is outside M-flanges. U-pieces (VP310), recovered from the existing insulation, reinstalled on busbars. The U-pieces are glued to the busbars and blocked by the box covers. They mechanically protect the busbars (VP310 is resistant to high temperatures) and improve electrical insulation.

8 Revisiting geometrical acceptance criteria Global alignment gauge Geometrical constraints of the insulation box were reanalyzed. The dimensions of the gauges are confirmed.

9 Revisiting geometrical acceptance criteria Height gauge A new type of gauge for checking the bottom surface of the busbars was tried out but with inconclusive result. The dimensions of the present C-gauges are confirmed.

10 Update from QC teams ICIT Resurgence of cases of equipment damage: – temperature sensor wires broken during diode opening – nested bellows scarred during M-line cutting ELQC (details in LSC#13 of 21 June) Investigations ongoing on the heavily damaged SC cable found in a quadrupole segment with an R cold outlier. ELQA Frequent test disruptions due to poorly insulated clamps. High humidity in the tunnel a concern. Up to now, only “technological” shorts. Frequency of ELQA tests: every day or every two days? Perform tests every day till completion of S56, then review procedure and frequency of tests. WELD DN200 weld inspections proceeding well. VAC M-leak checks yet to start when first vacuum subsector is ready.

11 Statistics QC of existing splices Sector 5-6 Final Inspected splices 1272% Conform95675.2 Non-conform31624.8 R8302.4 Splice alignment574.5 Splice height17814.0 Deformed lip151.8 Splice width60.5 Flange exchange221.7 Geometrical defects 20.8%

12 Statistics QC of existing splices Sector 6-7 27 June 2013 Inspected splices 720% Conform50470.0 Non-conform21630.0 R89713.5 Splice alignment466.4 Splice height679.3 Deformed lip40.6 Assembly20.2 Geometrical defects 16.3% 57% of S6-7

13 Auditor findings Cleanliness of surfaces is a standing concern Traces of glue and Kapton on machined surfaces and machining tools. Efficiency of cleaning (oxidization, glue) before soldering? Traceability of solder?

14 4th Splice Review 22/24 July 2013 Purpose: – to review the quality of the consolidation activities of the LHC superconducting circuits and magnets (SMACC) – to analyse the trends, and to consider any changes in the procedures that may be required following the consolidation of the first sector(s).

15 4th Splice Review - Agenda Monday 22 July 09:0001:00Committee training for tunnel tour 10:0003:00Committee tunnel tour 13:00Lunch 16:0001:30Committee preparation session 17:30Adjourn for the day

16 4th Splice Review - Agenda Tuesday 23 July 08:3000:10IntroductionJ-P. Tock 08:4000:20Status of SMACC activitiesJ-P. Tock 09:0000:20Overview of SMACC-QAR. Ostojic 09:2000:10Discussion 09:3000:20Coffee Status of production activities and internal QC 09:5000:30The splice consolidation trainF. Savary 10:2000:20Welding activitiesS. Atieh 10:4000:20Discussion 11:0000:15Special intervention teamN. Bourcey 11:1500:20DFBA consolidationA. Perin 11:3500:25Discussion 12:00Lunch QC of consolidation activities 14:0000:15IC quality controlD. Bodart/C. Garion 14:1500:30Local splice quality controlCh. Scheuerlein 14:4500:20Weld quality controlJ-M. Dalin 15:0500:20Discussion 15:2500:20Tea 15:4500:20Quality control of electrical circuitsK. Dahlerup-Petersen 16:0500:20Quality control of vacuum systemsP. Cruikshank 16:2500:15Report from CERN AuditorsS. Feher 16:4000:20Discussion 17:0001:00Committee closed session 18:00Adjourn for the day 19:30Dinner

17 4th Splice Review - Agenda Wednesday 24 July 08:3000:30Committee closed session 09:0003:00Response to reviewers questions, discussion 12:00Lunch 14:00Committee closed session 17:00Preliminary conclusionsJ. Strait

18 Summary A number of inspection criteria were re-discussed and the procedures updated. – A significant number of QC steps of the “train” (except welding) have been performed with updated procedures. In S56, 25% of the splices had to be redone, 20% due to geometrical defects. In S67, 30% of the splices are defective, 13% due to electrical defects (R8). Geometrical defects continue to dominate. The criteria for geometrical defects were re-examined and are confirmed. – A similar number of defective splices may be expected in other sectors. Heavily damaged SC cable was found in a quadrupole segment with an R cold outlier. A strategy of repair must be clarified before other defective splices of this type are opened. Protection of IC components and cleanliness during work remain a major concern.

19 Statistics Critical NCRs OpenClosed LMF train Internal QC-2 ICIT21 ELQC650 WELD-- ELQA-1 VAC115 Sector 5-6 27 June 2013


Download ppt "Status of SMACC-QA 1.Recently resolved issues 2.Update from QC teams 3.Statistics S56 and S67 4.Auditors findings 5.4th Splice Review – 22/24 July Ranko."

Similar presentations


Ads by Google