Presentation is loading. Please wait.

Presentation is loading. Please wait.

Geotechnical investigation and risk assessment at Budapest metro line 4 Dr. Tibor Horváth Geovil Ltd. INTERNATIONAL SOCIETY FOR SOIL MECHANICS AND.

Similar presentations


Presentation on theme: "Geotechnical investigation and risk assessment at Budapest metro line 4 Dr. Tibor Horváth Geovil Ltd. INTERNATIONAL SOCIETY FOR SOIL MECHANICS AND."— Presentation transcript:

1

2

3

4

5 Geotechnical investigation and risk assessment at Budapest metro line 4 Dr. Tibor Horváth Geovil Ltd. INTERNATIONAL SOCIETY FOR SOIL MECHANICS AND GEOTECHNICAL ENGINEERING HUNGARIAN NATIONAL COMMITTEE 24th -25th September 2010, Budapest ISSMGE TC 302 “Failures, Disputes, Causes and Solutions in Geotechnics”

6 MAIN FEATURES OF METRO LINE 4 Length of line: 12.7 km Phase I: 7.4 km Phase II: 3.2 km Phase III: 2.1 km Number of stations: 16 Phase I: 10 stations Phase II: 4 stations Phase III: 2 stations Extensions: Phase II currently holds licences from both railway and environmental authorities as far as Bosnyák tér, while the planned Phase III would extend as far as the Budaörs F lower M arket.

7 The route proceeds at a relatively shallow depth, at a rail-top level of 16-22 metres below the surface on average, the depth of 32-34 metres under the Danube, passing beneath an almost entirely built-up area and through extremely varied geological strata. Buda sectionDanubePest section

8 Enginner geological profile of Buda side Kiscelli marly clay stone, weathered Kiscelli marly clay stone, fissured

9 Engineering geological profile of river Danube crossing

10 Engineering geological profile of Pest side Pleisztocene, river sediments Miocéne, litoral facies of of a mediterrain sea

11 Risk Classification by Likelihood „L „ 1 – Frequent An effect derived in the frame of a survey from any risk successively experienced/monitored during the project and supported statistics derived, if applicable, from the project and other relevant events. 2 – Likely An effect derived in the frame of a survey from any risk often experienced/monitored during the project and supported statistics derived, if applicable, from the project and other relevant events. 3 – Occasional An effect derived in the frame of a survey from a risk occasionally experienced/monitored during the project and supported statistics derived, if applicable, from the project and other relevant events. 4 – Unlikely An effect derived in the frame of a survey from an unlikely risk during the project and supported statistics derived, if applicable, from the project and other relevant events. 5 – Improbable An effect derived in the frame of a survey from an improbable risk often experienced/monitored during the project and supported statistics derived, if applicable, from the project and other relevant events. Risk Classification by Severity „S „ 1 – Catastrophic Several immediate or deferred fatality cases attributable to injuries or illness. Loss of production for more than seven days. (Total loss €5 millions) 2 – High A single immediate or deferred fatality case attributable to injuries or illness. Loss of production of one to seven days due to damage to work or equipment. (Total loss above €1 million, but below €5 millions) 3 – Significant Injury, illness or dangerous circumstance subject to reporting. The loss of production due to injury exceeds one shift. Max. one day’s loss of production due to damage to work or equipment. (Total loss of more than €25,000 but less than €1 million) 4 – Low Minor injury. No loss of time or the person can return, after receiving medical attention, to work yet in the same shift. Damage not causing a significant delay in work performance or equipment. (Total loss of max. €25,000)

12 Risk Assessment Classification Matrix ”RI” (Risk Index) Risk Severity / Likelihood 1 – Catastrophic2 – High3 – Significant4 – Low 1 – Frequent 123 4 2 – Likely 246 8 3 – Occasional 369 12 4 – Unlikely 4812 16 5 – Improbable 51015 20 Risk Index (R)Risk classificationMarking 1 – 4 Very high V (Very high) 5 – 9 High H ( High ) 10 – 14 Medium M (Medium) 15 – 29 Low L (Low) Risk Index, Classification and Marking After determining the likelihood and severity of the risk we determined the risk index by means of the assessment matrix. Risk index = Likelihood of occurrence x Severity of risk RI = L x S The risk index has been calculated for the “starting/initial” cases and the cases yet remaining despite the efforts made to alleviate severity of the risks involved.

13 Elements of Risk Assessment Arise from Geology, Hydrogeology and Geotechnical features General risk from the level of geotechnical investigation, Personal risk Third party risk Environmental risk Risk of equipments Risk of program and delay Annex "A1.": Geotechnical risk level matrix table of Rákóczi Square Station with the section to be built by installing a diaphragm wall Initial conditions, risksResidual conditions, risks RiskLSRIRRReductionLSRIRRComments GENERAL RISK FROM THE LEVEL OF GEOTECHNICAL SURVEYING The geotechnical and hydrogeological data available for the preparation of working drawings and for construction are not reliable and insufficient. 212 V Supplementary geotechnical and hydrogeological surveys. Continuous geotechnical service during construction. 4416L In order to reduce risk, we suggest 2 "dry land" bores and a hydrogeological survey. The supplementary geotechnical surveys are not suitably assessed.4312 M Consultation with the specialist geotechnical service, continuous presence of the specialist service during construction. 5420L The geotechnical specialist service maps the strata found during excavation continuously and provides information about it to construction management. River water level 0.5 m higher than the highest flood level of the Danube.339 H During the preparation of construction drawings, protection shall be planned. Continuous assessment of water level reports, a technical and personnel protection plan shall be prepared. 4416L Groundwater level exceeds the estimated nominal design level236 H Continuous monitoring and evaluation of data from groundwater monitoring wells and the Danube water levels. Preparation of a technical and personnel plan for protection against high groundwater levels. 4416L Soil and rock conditions differ from those established by the supplementary geotechnical survey. 3412 M Consultation with the specialist geotechnical service and the designer, additional geotechnical and hydrogeological tests and surveys to be performed as required. 4416L

14 Geotechnical general risk from the level of geotechnical investigation, at Buda side At the time of GBR After additional investigation and monitoring

15 Geotechnical General Risk from the Level of Geotechnical Investigation, at Danube River Crossing

16 Geotechnical General Risk from the Level of Geotechnical Investigation at Pest side

17 Volume of Geotechnical Investigation

18 Total Volume of the Investigation at the End of Construction Work

19 Length of boring versus length of tunnel (stations with SCL method)

20 Length of boring versus boring length / tunnell length Length of boring (m)

21 Length of boring versus length of tunnell Recommended rate of USTNC/TT=1,2 * * U.S. National Committe on Tunnelling Technology, 2005

22 Cost of geotechnical investigation / cost construction at SCL tunnells

23 Budapest metro 4, Kelenföld station, portal land slip

24 Budapest metro 4 Fővám station Due to the detailed investigation and monitoring the tunneling work has been safe and successful in very dangerous – difficult geotechnical conditions.

25 Budapest metro 4 Rákóczi station SCL tunnell collapse – wash out

26

27

28

29 Budapest metro 4 Rákóczi station SCL tunnel collapse – wash out

30 Conclusions and recommendations The Geotechnical Risk Assessment comes from a suitable site investigation and the consequent building of an appropriate and coherent Engineering Geological model. It is desirable to create an international standard for the Geotechnical Risk Assessment, and to agree the parameters and guidelines for these recommendations. The Geotechnical Risk Assessment has a relationship to the quantity of meters of site investigation holes bored and the excavated length of tunnel. For the SCL tunnel ( soft tunneling at shallow depth ) the ratio of site investigation / excavated tunnel length should be 1.2. For the Budapest metro 4 project, the recommended ratio was followed. This resulted in a project which was very safe, in geological, geotechnical terms also the project had very few disputes related to the geotechnical risk clauses

31 Thank you for your kind attention!


Download ppt "Geotechnical investigation and risk assessment at Budapest metro line 4 Dr. Tibor Horváth Geovil Ltd. INTERNATIONAL SOCIETY FOR SOIL MECHANICS AND."

Similar presentations


Ads by Google