Presentation is loading. Please wait.

Presentation is loading. Please wait.

Delay Claims from the Owner and Contractor’s Perspectives

Similar presentations


Presentation on theme: "Delay Claims from the Owner and Contractor’s Perspectives"— Presentation transcript:

1 Delay Claims from the Owner and Contractor’s Perspectives
Annual Program of the Claims Avoidance and Resolution Committee of the Construction Institute March 11, 2010 – Los Angeles

2 Delay Claims from the Owner and Contractor’s Perspectives
Claims Avoidance and Resolution Committee Understanding Claims Subcommittee Dennis M. Mac Bride, Chair - SEPTA Craig Lindquist – CCS Group, Inc. Patrick Watz – AECOM John (Jack) Chiaverini – Retired, Perini Corporation

3 AGENDA What is a Delay Claim? Contract Language Related to Delay
Types of Delays Types of Damages Requirements for a Successful Claim

4 AGENDA Contractor’s Delay Claim Submission Owner’s Defense
Owner’s Damages / Counterclaim Contractor’s Defense Case Study

5 What is a Delay Claim? In simple terms:
Contractor: A request for compensation and/or time due to owner-caused delays Owner: An assessment of liquidated damages or a claim for actual damages due to contractor-caused delays

6 Contract Language “Time is of the essence” Contract time of completion
Contract milestones / Phasing Scheduling specifications (CPM or bar chart) Notice provisions

7 Contract Language Time extension requests (time impact analysis)
Time extensions / change orders Liquidated damages “No damage for delay” clause Delays by other contractors clause Disputes clause

8 Types of Delays Examples of Owner-Caused Delays Site access
Differing site conditions Shop drawing approval Design errors and omissions Extra work / change orders Failure by owner to timely provide materials Changed conditions, e.g., working hour restrictions Work suspension

9 Types of Delays Examples of Contractor-Caused Delays
Procurement/Submittal problems (material & equipment) Subcontractor delays Lack of adequate resources (labor, material, equipment) Poor work sequencing Lack of productivity Rework Financial difficulties

10 Types of Delays Third-Party Delays Permit acquisition
Utility relocations Adjacent contractors Government Actions/Inactions

11 Types of Delays - Analysis
Excusable / Non-excusable delays Compensable / Non-compensable delays Force majeur (Beyond either party’s control) Concurrent delays

12 Examples of Contractor Delay Damages
Recoverable Field office overhead (General conditions) Trailers, utilities, on-site supervision, etc. Added cost of work, e.g., winter work protection Subcontractor pass through Labor and material escalation Acceleration Directed and constructive acceleration Idle labor and equipment Lost productivity (inefficiencies) Insurance and bonding costs

13 Examples of Contractor Delay Damages
Not Recoverable (Depends on contract language) Home office overhead (G & A) Delay vs. total suspension of work Lost opportunities Lost business revenue, loss of bonding capacity Legal and consultant fees

14 Owner Damages Liquidated Damages Examples of Owner’s Actual Damages
Described in contract $ per day for each day substantial completion is beyond the current contract completion date Must be a reasonable estimate of damages and not a penalty Examples of Owner’s Actual Damages Owner costs Lost revenue, interest on financing, project management, inspection, etc. Architect/Engineer costs/fees Additional shop drawing reviews, rate escalation, etc. Construction Manager costs/fees

15 Requirements for a Successful Claim
The burden of proof is on the contractor

16 Requirements for a Successful Claim
Three elements needed: Liability (Entitlement) Causation Damages (Quantification)

17 Requirements for a Successful Claim
Liability Contractual duties and obligations Notice provisions Site access, accurate plans and specs Adequate resources, workmanship Causation “Cause and effect” Link between delay and damages Damages Substantiating documentation for extended costs Actual costs or daily rates

18 Contractor’s Delay Claim Submission
Why the owner is responsible for delays and associated costs Schedule analysis Damages Substantiating documentation Transparency

19 Determine Type of Delay:
Owner’s Defense Determine Type of Delay: Excusable Non-excusable Owner-caused Force majeur Contractor-caused Compensable Non-compensable

20 Identify Concurrent Delays:
Owner’s Defense Identify Concurrent Delays: Excusable Caused by Owner and Contractor Non-compensable

21 Owner’s Defense Liability Review - Contract terms
Causation Review - Schedules, daily reports, shop drawing logs, meeting minutes, etc. Damage Review Receipts, invoices, cost reports, etc. Reasonable estimates ___________________________________________ Owner Costs that Offset Contractor Damages: Overhead paid as part of change orders during the extended period Liquidated or actual damages

22 Owner’s Damages / Counterclaim
Why the contractor is responsible for delays and liquidated or actual damages Schedule analysis Damage calculations Substantiating documentation

23 Contractor’s Defense Contract Terms / Plans & Specs
Ambiguities, conflicts, errors & omissions Change orders, RFI’s, etc. – Effect on schedule and costs Schedule Analysis Owner-caused delays Concurrent delays

24 Delay Claim Case Study

25 Case Study This is the story of a construction project that was planned to be completed in 24 months. Unfortunately, stuff happened and it was completed much later. Because of this, the contractor incurred extra costs and requested additional compensation from the owner. The following describes the process that was used to resolve this delay claim.

26 The As-Planned Schedule (What was supposed to happen)

27

28 The As-Built Schedule (What actually happened)

29

30 The As-built Schedule shows that there were six delays that resulted in an eight month delay to the project.

31

32 Because the project finished eight months late, the contractor submitted the following claim to the owner:

33

34 Before analyzing the contractor’s costs, the owner performed a Delay Responsibility Analysis as follows:

35

36 Delay Responsibility Analysis
Delay Type Access Delay Differing Site Conditions Re-design Strike Lack of Progress Re-work Responsibility Owner Neither Contractor

37

38 Based on its Delay Responsibility Analysis, the owner apportioned the contractor’s claimed costs and estimated the contractor’s entitlement to additional compensation as follows:

39

40 The contractor requested more than $700,000 in additional compensation due to project delays.
The owner estimated that the contractor was entitled to approximately $260,000. They negotiated a settlement somewhere in between . . . . . . and everyone lived happily ever after.

41 THE END

42 Delay Claims from the Owner and Contractor’s Perspectives
Questions?

43 Delay Claims from the Owner and Contractor’s Perspectives
Additional Information Construction Delay Claims, Third Edition, Barry B. Bramble & Michael T. Callahan, 1999 Construction Delays: Documenting Causes, Winning Claims, Recovering Costs, Theodore J. Trauner, 1990 Construction Scheduling: Preparation, Liability, and Claims, John M. Wickshire, Thomas J. Driscoll, Stephen B. Hurlbut, 2008 CPM in Construction Management, Seventh Edition, Fredric Plotnick & James O’Brien, 2009 Proving and Pricing Construction Claims, Robert F. Cushman, 2000 Recommended Practice No. 29R-03, Forensic Schedule Analysis, AACE International, 2007


Download ppt "Delay Claims from the Owner and Contractor’s Perspectives"

Similar presentations


Ads by Google