Presentation is loading. Please wait.

Presentation is loading. Please wait.

Delays and the consequences and time management

Similar presentations


Presentation on theme: "Delays and the consequences and time management"— Presentation transcript:

1 Delays and the consequences and time management
Luise Lorenz Christina Mohr

2 DELAYS Completion of a project in time and within budget is a common goal of contractor and client Delays  failure of budget  disputes (time = money) Delayed completion of work compared to the planned/contract schedule (= loss of time) It’s possible to make up time by working faster or rearranging the work sequence Contractor related delays are the most significant ones

3 GENERAL REASONS FOR DELAYS
Delays can be caused by one or more of the following agencies: Client and his team-mates Contractor and his team-mates Nature (i.e. earthquakes) Due to a third party (i.e. strike)

4 SOME REASONS FOR DELAYS
faults in documents, designs or decisions insufficient number of equipment inaccurate cost or time estimation poor site management and supervision shortage of construction materials incompetent project team contractor’s/client’s financial difficulties etc.

5 TYPES OF DELAY The following types of delay help to determine the impact of a delay on the project. critical or non-critical excusable or non-excusable concurrent or non-concurrent compensable or non-compensable

6 1. CRITICAL or NON-CRITICAL
Critical delays: the delay interferes with the total time frame Non-critical delays: the delay does not interfere with the total time frame

7 2. EXCUSABLE or NON-EXCUSABLE
Excusable delays delay caused by the client, e.g. the owner denies access to the site delay caused by strike, fire, unusual weather etc. Non-excusable delays: delay caused by the sub-/contractor, e.g. not enough manpower on site to complete the job in time

8 3. CONCURRENT Concurrent delays:
two or more delay events occur at the same time or overlap to some degree at least one of the delays has to be caused by the contractor and one by the client Non-concurrent delays: delays do not overlap

9 4. COMPENSABLE the client’s failure to coordinate several prime contractors the client’s failure to provide adequate access to the project change orders placed by the client any interference by the client delays caused by a third party under the control of the client

10 CONSEQUENCES The claim depends on the cause of the delay, which must be identified. Therefore the responsibility is being clarified. Possible Claims: Time extensions (for the contractor) Financial compensations (for client and contractor)

11 FOLLOW-UP For the client: For the contractor: Delay in use of project
Capital is blocked Escalation in subsequent investment For the contractor: Delay in getting profit Idle of resources (machines, workers etc.) Productivity loss due to uncontracted work period

12 MINIMIZING DELAYS Identifying the cause that led to the delay
Providing enough financial resources Competent project management Resource availability Frequent progress meetings Choosing the right (experienced) consultants, suppliers and contractors Accurate cost estimation etc.

13 TIME MANAGEMENT Part of the construction budgeting process
Project management team determines the amount of time which is needed for the project Determining the amount of man hours and employees Major role for cost estimation

14 Thank you!

15 References Singh, P. (n.d.). Delay in construction project and its consequences. Retrieved from and-Its-Consequences Ibbnu Abbas, M. (2006). Causes and effect of delays in aceh construction industry. Retrieved from Cooke, B., & Williams, P. Construction planning, programming and control. Wiley-Blackwell.


Download ppt "Delays and the consequences and time management"

Similar presentations


Ads by Google