Presentation is loading. Please wait.

Presentation is loading. Please wait.

Hamid Shoaee LCLS Facility Advisory Committee 20 April 2006 1 Controls Overview April 20, 2006 LCLS Controls Group Outline Goals.

Similar presentations


Presentation on theme: "Hamid Shoaee LCLS Facility Advisory Committee 20 April 2006 1 Controls Overview April 20, 2006 LCLS Controls Group Outline Goals."— Presentation transcript:

1 Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu 20 April 2006 1 Controls Overview April 20, 2006 LCLS Controls Group Outline Goals Commissioning Schedule Responses to FAC Concerns Status update Conclusions

2 Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu 20 April 2006 2 The focus of controls effort in the last three months has been to assure readiness for injector installation and commissioning Collaborate with control system customers to prioritize needs & develop a detailed installation plan Accelerate procurement activities to ensure availability for installation Concentrated (and heroic) effort to align cable plant design and procurement with the project-wide installation schedule Complete the design of critical systems and follow through with final design reviews

3 Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu 20 April 2006 3 Integration with the SLC Control System SLC Alpha All High Level Apps KISSNet (fast closed loop control data) PNet (Pulse ID / User ID) MPG SLC Net (Data Communication) micro Camac I/O RF reference clock Xterm EPICS WS Distributed High Level Applications Ethernet (EPICS Protocol) I/OC (SLC-aware) EVGEVG Micro emulator PNETPNET

4 Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu 20 April 2006 4 System Design CPUCPU EVGEVG Beam Code + EPICS Time + EPICS Events LLRF 16 triggers CPUCPU EVREVR Diag 16 triggers IOC EVREVR HPRF I/O Boards CPUCPU EVREVR Pwr Supply Ctrl IOC Channel Access SLC Alpha Apps Xterm EPICS WS Distributed High Level Applications CPUCPU Vacuum Ctrl SLC-Net over Ethernet Fast Feedback over Ethernet? Machine Protection Drive Laser Off Single Bunch Beam Dumper

5 Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu 20 April 2006 5 Injector Commissioning Schedule C. Limborg-Deprey Schedule Outline Dec1 st ‘06 to July 31 st ‘07 Injector + BC1 (+ to BSY in ~ March) December 2006 Run beam to 250 MeV (TD11) Jan-March 2007 Commissioning all diagnostics Commissioning feedback systems April 2007 – July 2007 Optimization of beamline Measure Compression

6 Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu 20 April 2006 6 LCLS Accelerator and Compressor Schematic SLAC linac tunnel research yard Linac-0 L =6 m Linac-1 L  9 m  rf   25° Linac-2 L  330 m  rf   41° Linac-3 L  550 m  rf  0° BC1 L  6 m R 56   39 mm BC2 L  22 m R 56   25 mm DL2 L =275 m R 56  0 DL1 L  12 m R 56  0 undulator L =130 m 6 MeV  z  0.83 mm    0.05 % 135 MeV  z  0.83 mm    0.10 % 250 MeV  z  0.19 mm    1.6 % 4.30 GeV  z  0.022 mm    0.71 % 13.6 GeV  z  0.022 mm    0.01 % Linac-X L =0.6 m  rf =  21-1 b,c,d...existing linac L0-a,b rfgun 21-3b24-6d X 25-1a30-8c Commission in Dec. 2006 Commission in Nov. 2007 From P. Emma

7 Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu 20 April 2006 7

8 Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu 20 April 2006 8 November 06- Pre-Beam Checkouts NEEDED Mid-November 1- Vault/Linac Checkouts Power on access: Check polarity of magnets Read-backs, Motion controller: Exercise motion-control YAG/OTR camera images: Use Alignment laser to define screen center 2- PreBeam preparation Laser stabilization system completed Fiducialization real cathode location w.r.t virtual cathode completed LLRF for Gun, L0a, L0b (Volt. feedback, Phase Lock) Start conditioning (Gun, L0a, L0b) if PPS ready Dark current measurement if FC1 ready Vacuum pumps and gauges reading available CS for closing temperature control loop for gun

9 Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu 20 April 2006 9 There has been a re-prioritization of control software development to ensure control system availability for injector commissioning The applications group has been temporarily re-assigned to other tasks Supporting Timing System, Fast Feedback, Magnet control, etc. The new plan for Injector commissioning calls for… Making heavy use of MATLAB for application development Providing access to most control subsystems from MATLAB Enlisting the support of accelerator physicists in developing some of the required applications The Applications Group to provide the MATLAB interface to the accelerator data and the supporting infrastructure To migrate the applications to the XAL environment at a later date The critical Bunch Length Measurement application will be first prototyped it in MATLAB by the applications group The physics group will develop prototype Emittance / Energy spread applications in MATLAB

10 Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu 20 April 2006 10 FAC Response 1 – Database Due to the late hire of an experienced database expert, the central RDB is behind where one would hope for at this point in the project, and the controls team is currently planning to use the RDB for the online model, but not for other control system configuration needs. The online model will be needed for both the new XAL based applications and the old SLC applications, and it is important that both models are derived from the same source (RDB) rather than attempting to make updates in two or more places that will quickly become unsynchronized. It does appear that there are plans in place to store hardware configuration information in the RDB, but there is not yet a plan in place for how the database will be populated and maintained, or used during the construction and operations. The use of an RDB received a late start in the project and as a result it has not played a central role in the control system. Our plans still include making extensive use of an RDB as soon as we have addressed the injector commissioning schedule

11 Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu 20 April 2006 11 FAC Response 2 – SLC Integration and High Level Applications With the recent evaluation of the requirements for High Level Applications, plans to use a combination of existing SLC applications and newer XAL based applications, it is apparent there will need to be the ability to send commands (such as writing set points) from XAL applications and/or EPICS IOCs to hardware controlled on the SLC side. This was not previously planned and will need to be addressed soon. We are also concerned about plans to share the PEP proxy server during LCLS testing while PEP continues to run. Such tests could introduce loads or other problems that would impact PEP operations and an isolated proxy server should be provided if possible This will be addressed when we resume the development of XAL high level applications. Injector commissioning will make use of the existing SLC applications as well as MATLAB based tools.

12 Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu 20 April 2006 12 FAC Response 3 – PPS The PPS system plan calls for a PLC based implementation. Since this implementation choice is new for PPS systems at SLAC, an internal review is required, and tentatively scheduled for November 2005. It is important that this review take place on schedule so work on the PPS system can proceed on schedule. The internal review of the PLC-based PPS has taken place and the committee is nearing approval of the implementation. The project has also been reviewed by experts from other labs such as Jlab and APS. The design of the PPS is more than 90% complete and the Final Design Review is scheduled for next week. There will be a detailed presentation on this subject during the Controls Breakout session.

13 Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu 20 April 2006 13 FAC Response 4 – MPS (Himel wins 5 ¢) Work on the MPS system was recently started. This is a late start, and we are still concerned that it is a complex enough system that will be difficult to complete on time. We suggest that the functional requirements of the SLC “new MPS system” and the SNS MPS system be examined to help you determine the requirements for the LCLS MPS system. Also, to encourage prompt completion of the project, Himel made a high stakes bet (5 cents) with Dalesio. Dalesio wins if the MPS system is operational at the end of the November 2006 shut-down. To address the late start in the MPS system for the injector commissioning, a decision has been made to extend the existing Linac MPS to the injector and BC1 region as an interim solution. There is a detailed schedule for this activity and the plan is on course.

14 Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu 20 April 2006 14 FAC Response 5 – Management Organizationally, the distributed nature of Controls throughout the WBS structure still makes things a bit confusing. It would be helpful if the Controls manager was provided the same type of reports for all controls activities, as are available for higher level WBS elements. The controls activities appear to be well planned and running smoothly under the leadership of Bob Dalesio, however, it has long been recognized that a “local” and more permanent group leader is necessary. With this hire now imminent, it is important to plan for a smooth transition to ensure there is no disruption to the current activities which need to proceed on schedule to meet project milestones. We recommend a period of overlap for Bob and the new group leader to help keep progress on track. The new group management is in place and there has been a smooth hand off in the process

15 Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu 20 April 2006 15 FAC Response 6 – Process It appears that controls work is now being reviewed (internally in most cases) at appropriate stages, however, care should be taken to ensure these reviews are documented for future reference. Since the last FAC review there has been a concerted effort to produce the required set of documents for each project as defined by the LCLS project office. These include PRDs, ESDs, ICDs, etc. We are also proceeding with formal reviews of each project including magnet power supplies, vacuum system, cable plant, PPS, etc.

16 Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu 20 April 2006 16 FAC Responses 7 – BPMs Schedule is tight for BPM readout electronics. A first version of the Analog Front End (AFE) for the BPM system has been produced and its performance (resolution, linearity, etc.) has been verified on bench top and with actual beam. A revision to this board is currently under design.

17 Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu 20 April 2006 17 FAC Response 8 – Security For the next FAC meeting, we would like to see the overall network and cyber security plans. There is a separate presentation on this topic during the Controls Breakout session.

18 Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu 20 April 2006 18 Update October 2005 – April 2006 Long Haul cable plant design is complete and reviewed. Procurement is almost complete. Contractor for cable installation has been selected. SLC-Aware IOC is complete. PNet module is operational Timing – EVG/EVR200 is operational Power Supply using the SLC power supplies. Ethernet controller for more stable power supplies is running at SSRL Final Design Review conducted successfully Procurement for injector installation almost complete We are looking for an embedded controller as the ultimate solution for power supply control.

19 Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu 20 April 2006 19 Update October 2005 – April 2006 Vacuum System Hardware design complete Final design review completed April 2006 Architecture: Allen-Bradley PLC is used for interlocks and for status and control PLC and gauge and pump controllers standardized across LCLS project Long haul cable design complete Hardware procurement in progress Long lead items (pump controllers) have been ordered, June 2006 delivery Remaining hardware (gauge controllers, PLC) June 2006 delivery Video – cameras is operational and integrated with EPICS LLRF with the embedded controller is undergoing testing BPM AFE prototype has been successfully tested Parts for the wire scanner test are in hand The RTEMS BSPs for the 6100 cpus is operational.

20 Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu 20 April 2006 20 Update October 2005 – April 2006 The Laser Safety System design is complete and has been successfully reviewed PPS – The design is almost complete, FDR next week. Parts have been ordered The design for an interim MPS for injector commissioning is complete Required High Level Applications have been identified and are under development WBS being updated to reflect current approach to engineering development and installation

21 Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu 20 April 2006 21 Update October 2005 – April 2006 Laser Installation Support Thales laser controlled in Labview for first year Newport motor controls for laser table prototype is operational and all motors identified Video diagnostic prototype is operational and integrated with EPICS Laser safety system has been reviewed

22 Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu 20 April 2006 22 Breakout Session 4 – CONTROLS Location: Orange Conference Room 11:30 Controls Organization Overview H. Shoaee 12:00 Timing System UpdateD. Kotturi 12:30 Lunch 1:30 LLRF Update R. Akre 2:00 Injector/Linac Controls InstallationR. Fuller 2:30 PLC-based Personnel Protection SystemsM. Saleski 3:00 High-Level Applications and FeedbackD. Fairley 3:30 Break 4:00 Network Security T. Lahey 4:30 Discussions

23 Hamid Shoaee LCLS Facility Advisory Committee hamid@slac.stanford.edu 20 April 2006 23 Conclusions An excellent team is in place There is very productive involvement by other departments at SLAC The WBS is being changed to reflect the current approach to development and installation By the end of this exercise we should have a better handle on the control system cost We are on course for control system installation for the injector. The schedule is very tight with very little float We need to resume the development of long term high level applications, feedback systems and the use of RDB


Download ppt "Hamid Shoaee LCLS Facility Advisory Committee 20 April 2006 1 Controls Overview April 20, 2006 LCLS Controls Group Outline Goals."

Similar presentations


Ads by Google