Luminosity Monitor MWPCs. Status and plans. A.Kiselev OLYMPUS Collaboration Meeting DESY, Hamburg, 26.04.2010.

Similar presentations


Presentation on theme: "Luminosity Monitor MWPCs. Status and plans. A.Kiselev OLYMPUS Collaboration Meeting DESY, Hamburg, 26.04.2010."— Presentation transcript:

1 Luminosity Monitor MWPCs. Status and plans. A.Kiselev OLYMPUS Collaboration Meeting DESY, Hamburg, 26.04.2010

2 Current activity Funding Electronics, infrastructure, etc GEANT3 Monte-Carlo simulations Space limitations? Construction plans

3 Space limitations 180x180mm 2 @z=200cm possible? Wire chamber frame/cabling? Coil installation tolerance? 12.00 degree view19.45 degree view0.00 degree view

4 Tentative schedule Design, materials, etcMay-Jul 2010 First 3 chambers readyDec 2010 Test run installationDec 2010 – Feb 2011 Test runFeb-Jul 2011 Remaining chambers readyJul 2011 Final installationJul-Aug 2011 CommissioningAug-Dec 2011


Download ppt "Luminosity Monitor MWPCs. Status and plans. A.Kiselev OLYMPUS Collaboration Meeting DESY, Hamburg, 26.04.2010."